10810 W RENNES ST 91602

Certificate Information: 10810 W RENNES ST 91602

Application / Permit
17010-10000-04744
Plan Check / Job No.
B17LA22063
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
3-STORY W/ ROOF DECK SINGLE FAMILY DWELLING (lot 12, floor plan P2R) "Small lot subdivision pursuant to Tentative Tract Map No 75015-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded"
Permit Issued
Issued on 11/21/2018
Issuing Office
Metro
Current Status
CofO Issued on 9/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2017 APPLICANT
Green Plans Picked Up 12/19/2017 APPLICANT
Assigned to Plan Check Engineer 12/21/2017 HERNAN ARREOLA
Corrections Issued 1/2/2018 SHUNYU ZHANG
Quality Review Completed 1/11/2018 MINYE PAK
Building Plans Picked Up 1/16/2018 APPLICANT
Plan Check Approved 11/21/2018 HERNAN ARREOLA
Issued 11/21/2018 LADBS
CofO in Progress 9/1/2020 JOSEPH SAGEN
Permit Finaled 9/2/2020 DONALD SUNSERI
CofO Issued 9/2/2020 DONALD SUNSERI
Permit Finaled 9/2/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 3/28/2018 STEVE MELGAR
Low Impact Development Cleared 6/27/2018 SAM NAVID
Hydrant and Access approval Cleared 9/5/2018 JOHN DALLAS
Frnt yard landscape/Water mgmt Cleared 10/17/2018 SOPHIE GABEL-SCHEINBAU
Green Code Cleared 10/17/2018 KATHRYN BUTTERWORTH
Green Code Cleared 10/17/2018 SHUNYU ZHANG
Tract Map conditions Cleared 10/17/2018 SOPHIE GABEL-SCHEINBAU
Tract Map conditions Cleared 10/17/2018 SOPHIE GABEL-SCHEINBAU
Tract Map conditions Cleared 10/17/2018 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 10/17/2018 SOPHIE GABEL-SCHEINBAU
Eng Process Fee Ord 176,300 Cleared 11/5/2018 NAZILA NOORIFAR
Highway dedication Cleared 11/5/2018 LEE GUILBEAUX
Permit Cleared 11/5/2018 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/5/2018 LEE GUILBEAUX
Sewer availability Cleared 11/5/2018 NAZILA NOORIFAR

Contact Information

Architect Texter, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Warmington Residential California Inc; Lic. No.: 852282-B 3090 PULLMAN STREET      COSTA MESA, CA 92626
Engineer Allen, Thomas Christopher; Lic. No.: S5460 2 VENTURE, SUITE 200      IRVINE, CA 92618
Engineer Awad, Ramy F; Lic. No.: C41729 14169 WILDROSE LN      CHINO HILLS, CA 91709
Engineer Berliner, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Geocon, West Inc; Lic. No.: GE3092 3303 N SAN FERNANDO BLVD   SUITE 100    BURBANK, CA 91504

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/2/2019 Not Ready for Inspection DONALD SUNSERI
Footing/Foundation/Slab 1/2/2019 Not Ready for Inspection DONALD SUNSERI
Excavation/Setback/Form/Re-Bar 1/29/2019 Approved JOHN KIDWELL
Footing/Foundation/Slab 1/29/2019 Approved JOHN KIDWELL
Deputy Reinf. Concrete 1/30/2019 Conditional Approval JOHN KIDWELL
Deputy Wood Construction 3/14/2019 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 3/15/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 3/20/2019 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 3/28/2019 Partial Approval DONALD SUNSERI
Deputy Wood Construction 4/19/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 4/19/2019 Partial Approval BRUCE ROZAK
Deputy Wood Construction 6/11/2019 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 6/12/2019 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 7/22/2019 Not Ready for Inspection JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 7/29/2019 Not Ready for Inspection JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 8/12/2019 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 8/14/2019 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 9/16/2019 Partial Approval JOSEPH SAGEN
Deputy Wood Construction 9/25/2019 Approved DONALD SUNSERI
PLUMBING-Rough 10/22/2019 Approved JOSEPH SAGEN
Deputy Wood Construction 10/24/2019 Approved JOSEPH SAGEN
Pre-Inspection 10/29/2019 Partial Approval JOSEPH SAGEN
ELECTRICAL-Rough 10/31/2019 Approved JOSEPH SAGEN
HVAC-Rough 10/31/2019 Not Ready for Inspection JOSEPH SAGEN
HVAC-Rough 11/4/2019 Approved JOSEPH SAGEN
Deputy Wood Construction 11/5/2019 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 11/7/2019 Partial Approval JOSEPH SAGEN
Insulation 11/7/2019 Partial Approval JOSEPH SAGEN
BUILDING-Rough-Frame 11/14/2019 Not Ready for Inspection JOSEPH SAGEN
Green Building Rough 11/14/2019 Not Ready for Inspection JOSEPH SAGEN
MERV13>=Rough 11/14/2019 Not Ready for Inspection JOSEPH SAGEN
Verify Sprinkler Sign Off 11/14/2019 Not Ready for Inspection JOSEPH SAGEN
BUILDING-Rough-Frame 11/18/2019 Approved JOSEPH SAGEN
Green Building Rough 11/18/2019 Approved JOSEPH SAGEN
MERV13>=Rough 11/18/2019 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 11/18/2019 Approved JOSEPH SAGEN
Interior/Exterior Lathing 12/3/2019 Approved JOSEPH SAGEN
Drywall Nailing 12/10/2019 Approved JOSEPH SAGEN
Interior/Exterior Lathing 1/7/2020 Approved DONALD SUNSERI
Gas Test 2/20/2020 Approved JOSEPH SAGEN
Underground Mechanical 2/28/2020 Partial Approval JOSEPH SAGEN
Underground Mechanical 3/5/2020 Partial Approval JOSEPH SAGEN
Underground Mechanical 5/22/2020 Partial Approval JOSEPH SAGEN
Service/Power Release 5/27/2020 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 5/29/2020 SGSOV Approved JOSEPH SAGEN
ELECTRICAL-Final 7/28/2020 Approved JOSEPH SAGEN
HVAC-Final 7/28/2020 Approved JOSEPH SAGEN
PLUMBING-Final 7/28/2020 Approved JOSEPH SAGEN
Final 8/31/2020 OK to Issue CofO JOSEPH SAGEN
Green Building Final 8/31/2020 Approved JOSEPH SAGEN
MERV13>=Final 8/31/2020 Approved JOSEPH SAGEN
Smoke Detectors 8/31/2020 Approved JOSEPH SAGEN