2320 N FERNLEAF ST 90031

Certificate Information: 2320 N FERNLEAF ST 90031

Application / Permit
17010-10000-04583
Plan Check / Job No.
B17LA21300
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW ADU PER AB 494 AND SB 229 ON TOP OF 2-CAR GARAGE AND ROOFTOP DECK AT THE REAR OF THE LOT
Permit Issued
Issued on 11/6/2018
Issuing Office
Metro
Current Status
CofO Issued on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2017 APPLICANT
Assigned to Plan Check Engineer 11/30/2017 SINA KHOSRAVI
Corrections Issued 12/2/2017 SINA KHOSRAVI
Quality Review Completed 12/27/2017 BILL STUTSMAN
Building Plans Picked Up 12/28/2017 APPLICANT
Green Plans Picked Up 2/16/2018 APPLICANT
Plan Check Approved 5/14/2018 SINA KHOSRAVI
Issued 11/6/2018 LADBS
CofO in Progress 10/6/2022 KATHRYN BUTTERWORTH
CofO Issued 11/18/2022 DEROLD HAUFF
Permit Finaled 11/18/2022 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 2/13/2018 WALTER RAMIREZ
Construction within easement Cleared 2/13/2018 WALTER RAMIREZ
Low Impact Development Cleared 3/9/2018 SAM NAVID
Address approval Cleared 3/30/2018 KAREN LE
Eng Process Fee Ord 176,300 Cleared 3/30/2018 KAREN LE
Green Code Cleared 3/30/2018 DONALD CRICHLOW
Hydrant and Access approval Cleared 3/30/2018 JOHN CONNEALLY
Permit Cleared 3/30/2018 KAREN LE
Roof/Waste drainage to street Cleared 3/30/2018 KAREN LE
Sewer availability Cleared 3/30/2018 KAREN LE
ZI Cleared 3/30/2018 SEAN VEAL

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo, Margarito; Lic. No.: S4808 1327 LOMA AVE      LONG BEACH, CA 90804

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/29/2020 Partial Inspection RUBEN SALAS
PLUMBING-Rough 12/11/2020 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/18/2020 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/22/2020 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 2/26/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 6/16/2021 Approved KATHRYN BUTTERWORTH
HVAC-Rough 6/16/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 6/16/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/27/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/27/2021 Approved KATHRYN BUTTERWORTH
Green Building Rough 7/27/2021 Approved KATHRYN BUTTERWORTH
HVAC-Rough 7/27/2021 Approved KATHRYN BUTTERWORTH
MERV13>=Rough 7/27/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 7/27/2021 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 7/27/2021 Approved KATHRYN BUTTERWORTH
Insulation 8/12/2021 Approved KATHRYN BUTTERWORTH
Drywall Nailing 8/26/2021 Approved KATHRYN BUTTERWORTH
Shower Pan 8/26/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/1/2021 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/18/2022 Approved KATHRYN BUTTERWORTH
Final 5/18/2022 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 5/18/2022 Approved KATHRYN BUTTERWORTH
MERV13>=Final 5/18/2022 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 5/18/2022 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 5/18/2022 Approved KATHRYN BUTTERWORTH
Smoke Detectors 5/18/2022 Approved KATHRYN BUTTERWORTH
Final 8/29/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 9/27/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 10/4/2022 OK to Issue CofO KATHRYN BUTTERWORTH