2324 N FERNLEAF ST 90031
Certificate Information: 2324 N FERNLEAF ST 90031
- Application / Permit
- 17010-10000-04580
- Plan Check / Job No.
- B17LA21298
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New ADU per AB-2299 and SB-1069 with attached garage and deck above at rear of the property. **2 OF 2**
- Permit Issued
- Issued on 11/6/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2017 | ZAW HAN |
| Corrections Issued | 12/2/2017 | ZAW HAN |
| Quality Review Completed | 12/11/2017 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 12/19/2017 | APPLICANT |
| Green Plans Picked Up | 2/16/2018 | APPLICANT |
| Applicant returned to address corrections | 5/17/2018 | ZAW HAN |
| Plan Check Approved | 6/20/2018 | Zaw Han |
| Issued | 11/6/2018 | LADBS |
| CofO in Progress | 10/6/2022 | KATHRYN BUTTERWORTH |
| Permit Finaled | 11/18/2022 | DEROLD HAUFF |
| CofO Issued | 11/18/2022 | DEROLD HAUFF |
| Permit Finaled | 11/18/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/13/2018 | WALTER RAMIREZ |
| Construction within easement | Cleared | 2/13/2018 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 3/9/2018 | SAM NAVID |
| Address approval | Cleared | 3/30/2018 | KAREN LE |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2018 | KAREN LE |
| Green Code | Cleared | 3/30/2018 | DONALD CRICHLOW |
| Hydrant and Access approval | Cleared | 3/30/2018 | JOHN CONNEALLY |
| Permit | Cleared | 3/30/2018 | KAREN LE |
| Roof/Waste drainage to street | Cleared | 3/30/2018 | KAREN LE |
| Sewer availability | Cleared | 3/30/2018 | KAREN LE |
| ZI | Cleared | 3/30/2018 | SEAN VEAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/29/2020 | Partial Inspection | RUBEN SALAS |
| PLUMBING-Rough | 10/20/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 11/20/2020 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/20/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/4/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 12/4/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 12/4/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 12/4/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 12/4/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/4/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 12/4/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 12/9/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 12/9/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 6/16/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 6/16/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/16/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/27/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/27/2021 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 7/27/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/27/2021 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 7/27/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 7/27/2021 | Approved | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 7/27/2021 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 8/12/2021 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 8/26/2021 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 8/26/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 9/1/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 3/29/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 3/29/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 4/6/2022 | No Access for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 4/11/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 4/11/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 4/11/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 4/11/2022 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Final | 4/11/2022 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 4/11/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 4/11/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 4/11/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 4/11/2022 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 4/19/2022 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 4/19/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/17/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 5/17/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 5/17/2022 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 5/17/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 8/29/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 9/27/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 10/5/2022 | OK to Issue CofO | KATHRYN BUTTERWORTH |