1518 N ECHO PARK AVE 90026
Certificate Information: 1518 N ECHO PARK AVE 90026
- Application / Permit
- 17010-10000-04549
- Plan Check / Job No.
- B17LA21140
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TYPE VB, 3 STORY SINGLE FAMILY DWELLING ATTACHED 2 CAR GARAGE; SMALL LOT SUBDIVISION PURSUANT TO TENATIVE TRACT MAP NO VTT 71990, lot #4.
- Permit Issued
- Issued on 12/4/2019
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 4/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2017 | TSE MING HUANG |
| Corrections Issued | 12/1/2017 | TSE MING HUANG |
| Green Plans Picked Up | 12/11/2017 | APPLICANT |
| Quality Review Completed | 12/15/2017 | VERONICA LOPEZ |
| Building Plans Picked Up | 12/19/2017 | APPLICANT |
| Applicant returned to address corrections | 5/17/2018 | TSE MING HUANG |
| Applicant returned to address corrections | 9/20/2019 | TSE MING HUANG |
| Plan Check Approved | 12/4/2019 | TSE MING HUANG |
| Issued | 12/4/2019 | LADBS |
| CofO in Progress | 4/28/2021 | SCOTT FINNILA |
| CofO Issued-Status Void | 4/29/2021 | DEROLD HAUFF |
| Permit Finaled-Status Void | 4/29/2021 | DEROLD HAUFF |
| Re-Activate Permit | 4/30/2021 | DEROLD HAUFF |
| Permit Finaled | 4/30/2021 | DEROLD HAUFF |
| CofO Corrected | 4/30/2021 | DEROLD HAUFF |
| Permit Finaled | 4/30/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2018 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 5/3/2018 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 5/3/2018 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 5/3/2018 | STEVE MELGAR |
| Highway dedication | Cleared | 5/3/2018 | STEVE MELGAR |
| Permit | Cleared | 5/3/2018 | STEVE MELGAR |
| Encroachment in public way | Cleared | 5/30/2018 | FATIMA GUERRA |
| Frnt yard landscape/Water mgmt | Cleared | 5/30/2018 | DIANA JIMENEZ |
| ZA Case | Cleared | 5/30/2018 | DIANA JIMENEZ |
| ZA Case | Cleared | 5/30/2018 | DIANA JIMENEZ |
| Low Impact Development | Cleared | 7/9/2019 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 7/10/2019 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 7/10/2019 | NGOC KIEM |
| "Q" conditions | Cleared | 7/11/2019 | DAISY BENICIA |
| Sewer availability | Cleared | 7/17/2019 | JEANETTE VONG |
| Miscellaneous | Cleared | 7/22/2019 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 7/22/2019 | SOPHIE GABEL-SCHEINBAU |
| Tract Map conditions | Cleared | 7/22/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 7/22/2019 | SOPHIE GABEL-SCHEINBAU |
| Green Code | Cleared | 8/16/2019 | DONALD CRICHLOW |
| Miscellaneous | Cleared | 11/7/2019 | JOE LUCKEY |
| Grading Pre-Inspection | Cleared | 12/4/2019 | TSE MING HUANG |
Contact Information
| Architect | Texter,, Christopher S; Lic. No.: C25901 | 2 BUELLTON IRVINE, CA 92602 |
| Contractor | Planet Home Development Inc; Lic. No.: 975236-B | 1048 IRVINE AVENUE #421 NEWPORT BEACH, CA 92660 |
| Engineer | Kim,, Hyun Jin; Lic. No.: GE3106 | 6412 STANFORD AVENUE GARDEN GROVE, CA 92845 |
| Engineer | Soma_Jr.,, Philip George; Lic. No.: C46231 | 252 S BRENTWOOD PLACE ANAHEIM, CA 92804 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/16/2019 | Partial Inspection | SCOTT FINNILA |
| Underground Mechanical | 12/16/2019 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/19/2019 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 12/19/2019 | Partial Approval | SCOTT FINNILA |
| Masonry Wall/Backfill | 1/2/2020 | Conditional Approval | SCOTT FINNILA |
| Reinforced Masonry Frame | 1/2/2020 | Conditional Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 1/6/2020 | Partial Approval | SCOTT FINNILA |
| Reinforced Concrete Frame | 1/6/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 1/10/2020 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 1/14/2020 | Partial Approval | BRAD BESCOS |
| Reinforced Concrete Frame | 1/14/2020 | Partial Approval | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 1/21/2020 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 1/21/2020 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 1/22/2020 | Approved | SCOTT FINNILA |
| Deputy Reinf. Concrete | 1/23/2020 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 2/5/2020 | Not Ready for Inspection | MICHAEL FAUNCE |
| Drywall Nailing | 2/7/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2020 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 3/13/2020 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 3/17/2020 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2020 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 3/31/2020 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2020 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 4/17/2020 | Partial Inspection | SCOTT FINNILA |
| Wood Frame | 4/24/2020 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/8/2020 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 6/8/2020 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 6/8/2020 | Corrections Issued | SCOTT FINNILA |
| Wood Frame | 6/29/2020 | Corrections Issued | SCOTT FINNILA |
| Wood Frame | 7/10/2020 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 8/5/2020 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/21/2020 | Not Ready for Inspection | SCOTT FINNILA |
| HVAC-Rough | 8/21/2020 | Not Ready for Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 8/21/2020 | Not Ready for Inspection | SCOTT FINNILA |
| Pre-Inspection | 8/26/2020 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 9/4/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/11/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/11/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/11/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 9/11/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 9/15/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/17/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 9/23/2020 | Approved | SCOTT FINNILA |
| Wood Frame | 9/25/2020 | Approved | SCOTT FINNILA |
| Insulation | 9/29/2020 | Approved | SCOTT FINNILA |
| Wood Frame | 9/29/2020 | Approved | SCOTT FINNILA |
| Drywall Nailing | 10/7/2020 | Corrections Issued | SCOTT FINNILA |
| Interior/Exterior Lathing | 10/7/2020 | Partial Inspection | SCOTT FINNILA |
| Drywall Nailing | 10/13/2020 | Conditional Approval | SCOTT FINNILA |
| Underground Mechanical | 10/21/2020 | Partial Inspection | SCOTT FINNILA |
| Underground Mechanical | 10/26/2020 | Partial Approval | SCOTT FINNILA |
| Gas Test | 1/12/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 3/18/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 3/18/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 3/18/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 3/19/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 3/19/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 3/19/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 3/23/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/23/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/26/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/13/2021 | Approved | SCOTT FINNILA |
| Final | 4/13/2021 | Partial Inspection | SCOTT FINNILA |
| Green Building Final | 4/13/2021 | Approved | SCOTT FINNILA |
| Green Building Rough | 4/13/2021 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 4/13/2021 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 4/13/2021 | Approved | SCOTT FINNILA |
| Final | 4/28/2021 | OK to Issue CofO | SCOTT FINNILA |