1516 1/4 N ECHO PARK AVE 90026

Certificate Information: 1516 1/4 N ECHO PARK AVE 90026

Application / Permit
17010-10000-04547
Plan Check / Job No.
B17LA21140
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW TYPE VB, 3 STORY SINGLE FAMILY DWELLING ATTACHED 2 CAR GARAGE; SMALL LOT SUBDIVISION PURSUANT TO TENATIVE TRACT MAP NO VTT 71990, lot #2, see comment.
Permit Issued
Issued on 12/4/2019
Issuing Office
Metro
Current Status
CofO Corrected on 4/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2017 APPLICANT
Assigned to Plan Check Engineer 11/21/2017 TSE MING HUANG
Corrections Issued 12/1/2017 TSE MING HUANG
Green Plans Picked Up 12/11/2017 APPLICANT
Quality Review Completed 12/15/2017 VERONICA LOPEZ
Building Plans Picked Up 12/19/2017 APPLICANT
Applicant returned to address corrections 5/17/2018 TSE MING HUANG
Applicant returned to address corrections 9/20/2019 TSE MING HUANG
Plan Check Approved 12/4/2019 TSE MING HUANG
Issued 12/4/2019 LADBS
CofO in Progress 4/28/2021 SCOTT FINNILA
CofO Issued-Status Void 4/29/2021 DEROLD HAUFF
Permit Finaled-Status Void 4/29/2021 DEROLD HAUFF
Re-Activate Permit 4/30/2021 DEROLD HAUFF
Permit Finaled 4/30/2021 DEROLD HAUFF
CofO Corrected 4/30/2021 DEROLD HAUFF
Permit Finaled 4/30/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/3/2018 STEVE MELGAR
BHO/Hillside ordinance Cleared 5/3/2018 STEVE MELGAR
BHO/Hillside ordinance Cleared 5/3/2018 STEVE MELGAR
BHO/Hillside ordinance Cleared 5/3/2018 STEVE MELGAR
Highway dedication Cleared 5/3/2018 STEVE MELGAR
Permit Cleared 5/3/2018 STEVE MELGAR
Encroachment in public way Cleared 5/30/2018 FATIMA GUERRA
Frnt yard landscape/Water mgmt Cleared 5/30/2018 DIANA JIMENEZ
Miscellaneous Cleared 5/30/2018 DIANA JIMENEZ
ZA Case Cleared 5/30/2018 DIANA JIMENEZ
ZA Case Cleared 5/30/2018 DIANA JIMENEZ
Eng Process Fee Ord 176,300 Cleared 7/10/2019 ELAINE LEI
Hydrant and Access approval Cleared 7/10/2019 ROBERT DUFF
"Q" conditions Cleared 7/11/2019 DAISY BENICIA
Sewer availability Cleared 7/17/2019 JEANETTE VONG
Miscellaneous Cleared 7/18/2019 TERRY PHAN
Miscellaneous Cleared 7/22/2019 SOPHIE GABEL-SCHEINBAU
Tract Map conditions Cleared 7/22/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 7/22/2019 SOPHIE GABEL-SCHEINBAU
Green Code Cleared 8/16/2019 DONALD CRICHLOW
Miscellaneous Cleared 11/7/2019 JOE LUCKEY
Grading Pre-Inspection Cleared 12/4/2019 TSE MING HUANG

Contact Information

Architect Texter,, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Planet Home Development Inc; Lic. No.: 975236-B 1048 IRVINE AVENUE #421      NEWPORT BEACH, CA 92660
Engineer Kim,, Hyun Jin; Lic. No.: GE3106 6412 STANFORD AVENUE      GARDEN GROVE, CA 92845
Engineer Soma_Jr.,, Philip George; Lic. No.: C46231 252 S BRENTWOOD PLACE      ANAHEIM, CA 92804

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/16/2019 Partial Inspection SCOTT FINNILA
Underground Mechanical 12/16/2019 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 12/19/2019 Partial Approval SCOTT FINNILA
Underground Mechanical 12/19/2019 Partial Approval SCOTT FINNILA
Masonry Wall/Backfill 1/2/2020 Conditional Approval SCOTT FINNILA
Reinforced Masonry Frame 1/2/2020 Conditional Approval SCOTT FINNILA
Footing/Foundation/Slab 1/21/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Masonry 1/23/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 2/5/2020 Not Ready for Inspection MICHAEL FAUNCE
Drywall Nailing 2/7/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/27/2020 Partial Approval SCOTT FINNILA
Wood Frame 2/27/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 3/10/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 3/31/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/10/2020 Partial Approval SCOTT FINNILA
Wood Frame 4/17/2020 Partial Inspection SCOTT FINNILA
Wood Frame 4/24/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 5/21/2020 Partial Inspection SCOTT FINNILA
HVAC-Rough 5/21/2020 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 5/21/2020 Partial Inspection SCOTT FINNILA
ELECTRICAL-Rough 6/8/2020 Corrections Issued SCOTT FINNILA
HVAC-Rough 6/8/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 6/8/2020 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 6/10/2020 Corrections Issued SCOTT FINNILA
HVAC-Rough 6/10/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 6/10/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 6/12/2020 Approved SCOTT FINNILA
HVAC-Rough 6/12/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 6/12/2020 Partial Approval SCOTT FINNILA
Wood Frame 6/16/2020 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 6/22/2020 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 6/23/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 7/8/2020 Approved SCOTT FINNILA
HVAC-Rough 7/8/2020 Approved SCOTT FINNILA
PLUMBING-Rough 7/8/2020 Approved SCOTT FINNILA
BUILDING-Rough-Frame 7/14/2020 Approved JOSEPH MCGARRY
Green Building Rough 7/14/2020 Approved JOSEPH MCGARRY
Insulation 7/14/2020 Corrections Issued JOSEPH MCGARRY
Verify Sprinkler Sign Off 7/14/2020 Approved JOSEPH MCGARRY
Insulation 7/29/2020 Corrections Issued SCOTT FINNILA
Insulation 8/5/2020 Conditional Approval SCOTT FINNILA
Drywall Nailing 8/21/2020 Corrections Issued SCOTT FINNILA
Drywall Nailing 8/27/2020 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 8/31/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 10/21/2020 Partial Inspection SCOTT FINNILA
Underground Mechanical 10/26/2020 Partial Approval SCOTT FINNILA
Gas Test 1/12/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 3/18/2021 Corrections Issued SCOTT FINNILA
HVAC-Final 3/18/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Final 3/18/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 3/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 3/23/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/26/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 3/26/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 3/26/2021 Approved ALEJANDRO DE ARTOLA
Service/Power Release 3/26/2021 Approved ALEJANDRO DE ARTOLA
Final 4/13/2021 Partial Inspection SCOTT FINNILA
Footing/Foundation/Slab 4/13/2021 Approved SCOTT FINNILA
Green Building Final 4/13/2021 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 4/13/2021 SGSOV Approved SCOTT FINNILA
Smoke Detectors 4/13/2021 Approved SCOTT FINNILA
Final 4/28/2021 OK to Issue CofO SCOTT FINNILA