744 E VERNON AVE 90291

Certificate Information: 744 E VERNON AVE 90291

Application / Permit
17010-10000-04520
Plan Check / Job No.
B17LA21034
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 - STORY 32' X 97' SINGLE FAMILY DWELLING, TYPE-VB, OCC-R3/U WITH ATTACHED 2 CAR GARAGE
Permit Issued
Issued on 7/25/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2017 APPLICANT
Assigned to Plan Check Engineer 11/21/2017 PINANK PATEL
Corrections Issued 12/6/2017 PINANK PATEL
Quality Review Completed 12/18/2017 WING SUEN
Building Plans Picked Up 1/3/2018 APPLICANT
Green Plans Picked Up 1/3/2018 APPLICANT
Applicant returned to address corrections 2/1/2018 PINANK PATEL
Plan Check Approved 3/14/2018 PINANK PATEL
Plan Check Approved 6/19/2018 PINANK PATEL
Issued 7/25/2018 LADBS
CofO in Progress 3/2/2022 DAVID FEILER
Permit Finaled 3/8/2022 DANIEL ORRANTE
CofO Issued 3/8/2022 DANIEL ORRANTE
Permit Finaled 3/8/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/1/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 2/1/2018 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 2/1/2018 ROBERT DUFF
Sewer availability Cleared 2/1/2018 ADRIAN SANCHEZ
Green Code Cleared 2/8/2018 WILLIAM ROSE
Specific Plan Cleared 2/8/2018 CLIVE GRAWE
CPC Cleared 3/14/2018 IVORY CHAMBESHI
Coastal Zone Cleared 3/14/2018 IVORY CHAMBESHI
Frnt yard landscape/Water mgmt Cleared 3/14/2018 IVORY CHAMBESHI
Low Impact Development Cleared 3/14/2018 MARTIN FRAGOSO
Miscellaneous Cleared 3/14/2018 IVORY CHAMBESHI
Miscellaneous Cleared 3/14/2018 IVORY CHAMBESHI
Miscellaneous Cleared 3/14/2018 IVORY CHAMBESHI
Miscellaneous Cleared 3/14/2018 IVORY CHAMBESHI
Roof/Waste drainage to street Cleared 3/14/2018 KAREN LE
Specific Plan Cleared 3/14/2018 IVORY CHAMBESHI

Contact Information

Architect Hertz, David Randall; Lic. No.: C25190 2420 MCKINLEY AVENUE      VENICE, CA 90291
Contractor Abbott R T Construction Inc; Lic. No.: 746685-B 543 COUNTRY CLUB DRIVE BOX 205      SIMI VALLEY, CA 93065
Engineer De, Leon Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Mercado, Lizandro; Lic. No.: S4331 25583 AVENUE STANFORD      VALENCIA, CA 91355
Landscape Architect Laforga, David Martinez; Lic. No.: LA5555 956 3RD AVENUE      LOS ANGELES, CA 90019

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/22/2018 Partial Approval MICHAEL TEMPLE
Underground Mechanical 11/5/2018 Corrections Issued CRAIG DAVIS
Green Building Rough 11/16/2018 Not Ready for Inspection CRAIG DAVIS
Underground Mechanical 11/30/2018 No Access for Inspection CRAIG DAVIS
Underground Mechanical 12/4/2018 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 12/18/2018 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 12/18/2018 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 1/8/2019 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 1/8/2019 Partial Approval CRAIG DAVIS
Deputy Reinf. Concrete 1/9/2019 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 1/24/2019 Partial Approval CRAIG DAVIS
Underground Mechanical 1/24/2019 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 1/29/2019 Partial Approval CRAIG DAVIS
Reinforced Concrete Frame 1/29/2019 Approved CRAIG DAVIS
BUILDING-Rough-Frame 3/7/2019 Partial Approval DAVID HEINE
Green Building Rough 3/7/2019 Not Ready for Inspection DAVID HEINE
Verify Sprinkler Sign Off 3/7/2019 Not Ready for Inspection DAVID HEINE
BUILDING-Rough-Frame 3/21/2019 Partial Approval DAVID HEINE
Green Building Rough 3/21/2019 Not Ready for Inspection DAVID HEINE
Verify Sprinkler Sign Off 3/21/2019 Not Ready for Inspection DAVID HEINE
BUILDING-Rough-Frame 4/11/2019 Partial Approval DAVID HEINE
Green Building Rough 4/11/2019 Not Ready for Inspection DAVID HEINE
Verify Sprinkler Sign Off 4/11/2019 Not Ready for Inspection DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 4/19/2019 Partial Approval TIM CHRISTENSEN
Green Building Rough 4/19/2019 Not Ready for Inspection TIM CHRISTENSEN
Verify Sprinkler Sign Off 4/19/2019 Not Ready for Inspection TIM CHRISTENSEN
BUILDING-Rough-Frame 5/13/2019 Corrections Issued DAVID HEINE
Green Building Rough 5/13/2019 Not Ready for Inspection DAVID HEINE
Verify Sprinkler Sign Off 5/13/2019 Not Ready for Inspection DAVID HEINE
ELECTRICAL-Rough 6/4/2019 Not Ready for Inspection DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 6/4/2019 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 6/13/2019 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 6/19/2019 Partial Approval DAVID HEINE
PLUMBING-Rough 7/3/2019 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 7/18/2019 Corrections Issued DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 8/1/2019 Partial Approval DAVID HEINE
PLUMBING-Rough 8/1/2019 Approved DAVID HEINE
Sewer 8/15/2019 Approved DAVID HEINE
HVAC-Rough 9/12/2019 Approved DAVID HEINE
BUILDING-Rough-Frame 10/30/2019 Not Ready for Inspection DAVID HEINE
ELECTRICAL-Rough 10/30/2019 Approved DAVID HEINE
Green Building Rough 10/30/2019 Not Ready for Inspection DAVID HEINE
Verify Sprinkler Sign Off 10/30/2019 Not Ready for Inspection DAVID HEINE
BUILDING-Rough-Frame 11/25/2019 Approved DAVID HEINE
Green Building Rough 11/25/2019 Approved DAVID HEINE
Verify Sprinkler Sign Off 11/25/2019 Approved DAVID HEINE
Insulation 12/6/2019 Approved DAVID HEINE
Drywall Nailing 12/16/2019 Approved CRAIG DAVIS
Interior/Exterior Lathing 12/16/2019 Approved CRAIG DAVIS
Interior/Exterior Lathing 5/18/2020 Partial Approval DAVID HEINE
Interior/Exterior Lathing 6/16/2020 Partial Approval DAVID HEINE
Shower Pan 7/17/2020 Approved DAVID HEINE
Interior/Exterior Lathing 7/24/2020 Partial Approval DAVID HEINE
Interior/Exterior Lathing 8/14/2020 Approved DAVID HEINE
Deputy Reinf. Concrete 11/19/2020 Partial Approval DAVID HEINE
Deputy Steel/Welding 12/21/2020 Approved DAVID HEINE
Structural Steel Frame 1/15/2021 Partial Approval JUAN VALENZUELA
Wood Frame 1/15/2021 Partial Approval JUAN VALENZUELA
Structural Steel Frame 3/24/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 5/26/2021 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Final 6/16/2021 Approved JOHNNY MIRANDA
HVAC-Final 6/16/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 6/16/2021 Approved JOHNNY MIRANDA
HVAC-Final 7/8/2021 Approved JOHNNY MIRANDA
Final 1/28/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 1/28/2022 Approved DAVID FEILER
Green Building Final 1/28/2022 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 1/28/2022 SGSOV Approved DAVID FEILER
Service/Power Release 1/28/2022 Not Ready for Inspection DAVID FEILER
Smoke Detectors 1/28/2022 Approved DAVID FEILER
Final 3/2/2022 OK to Issue CofO DAVID FEILER
Green Building Final 3/2/2022 Approved DAVID FEILER
Service/Power Release 3/2/2022 Approved DAVID FEILER