2648 N LAUREL CANYON BLVD 90046
Certificate Information: 2648 N LAUREL CANYON BLVD 90046
- Application / Permit
- 17010-10000-04279
- Plan Check / Job No.
- B17LA20184
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New ADU with attached garage per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO in Progress on 3/8/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/3/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2017 | SHANGQIN XIE |
| Green Plans Picked Up | 11/17/2017 | APPLICANT |
| Corrections Issued | 11/21/2017 | SHANGQIN XIE |
| Quality Review Completed | 11/27/2017 | SIAVOSH POURSABAHIAN |
| Applicant returned to address corrections | 2/20/2018 | SHANGQIN XIE |
| Applicant returned to address corrections | 9/11/2018 | SHANGQIN XIE |
| Plan Check Approved | 12/17/2020 | SHANGQIN XIE |
| Issued | 2/19/2021 | APPLICANT |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| CofO in Progress | 3/8/2023 | PATRICK LIEBREGT |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2018 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 3/16/2018 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 3/16/2018 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 3/16/2018 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2018 | ADRIAN SANCHEZ |
| Green Code | Cleared | 3/16/2018 | DONALD CRICHLOW |
| Hydrant and Access approval | Cleared | 3/16/2018 | JOHN CONNEALLY |
| Sewer availability | Cleared | 3/16/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 7/2/2018 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/2/2018 | MICHAEL CASTILLO |
| Address approval | Cleared | 7/30/2020 | RENZ SORIANO |
| CPC | Cleared | 8/20/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 8/20/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 10/13/2020 | TRACY WILLIAMS |
| Specific Plan | Cleared | 10/13/2020 | TRACY WILLIAMS |
| Low Impact Development | Cleared | 11/16/2020 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 12/17/2020 | SHANGQIN XIE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Ibarra,, Marco Antonio; Lic. No.: C74010 | 16 N MARENGON AVE STE 604 PASADENA, CA 91101 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/3/2021 | Partial Inspection | GORDON ZUBER |
| PLUMBING-Rough | 5/27/2021 | Partial Approval | JOEL WILLIAMS |
| Reinforced Concrete Frame | 5/27/2021 | Partial Approval | JOEL WILLIAMS |
| Underground Mechanical | 5/27/2021 | Partial Approval | JOEL WILLIAMS |
| Footing/Foundation/Slab | 6/14/2021 | Approved | GORDON ZUBER |
| Underground Mechanical | 6/14/2021 | Approved | GORDON ZUBER |
| Reinforced Masonry Frame | 6/30/2021 | Corrections Issued | GORDON ZUBER |
| Masonry Wall/Backfill | 7/7/2021 | Not Ready for Inspection | JOEL WILLIAMS |
| Underground Mechanical | 7/19/2021 | Partial Approval | JOEL WILLIAMS |
| ELECTRICAL-Rough | 8/2/2021 | Not Ready for Inspection | GORDON ZUBER |
| Excavation/Setback/Form/Re-Bar | 8/2/2021 | Corrections Issued | GORDON ZUBER |
| Excavation/Setback/Form/Re-Bar | 12/7/2021 | Approved | GORDON ZUBER |
| Masonry Wall/Backfill | 12/21/2021 | Approved | GORDON ZUBER |
| Reinforced Masonry Frame | 12/21/2021 | Approved | GORDON ZUBER |
| Reinforced Masonry Frame | 1/6/2022 | Approved | GORDON ZUBER |
| Masonry Wall/Backfill | 2/23/2022 | Corrections Issued | GORDON ZUBER |
| Special/Order Compliance | 2/23/2022 | Partial Inspection | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Corrections Issued | GORDON ZUBER |
| ELECTRICAL-Rough | 5/18/2022 | Corrections Issued | GORDON ZUBER |
| Gas Test | 5/18/2022 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Rough | 5/18/2022 | No Access for Inspection | GORDON ZUBER |
| ELECTRICAL-Rough | 5/31/2022 | Not Ready for Inspection | GORDON ZUBER |
| Gas Test | 5/31/2022 | Not Ready for Inspection | GORDON ZUBER |
| HVAC-Rough | 5/31/2022 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Rough | 5/31/2022 | Not Ready for Inspection | GORDON ZUBER |
| ELECTRICAL-Rough | 6/9/2022 | Corrections Issued | GORDON ZUBER |
| HVAC-Rough | 6/9/2022 | Corrections Issued | GORDON ZUBER |
| PLUMBING-Rough | 6/9/2022 | Corrections Issued | GORDON ZUBER |
| ELECTRICAL-Rough | 6/23/2022 | Not Ready for Inspection | GORDON ZUBER |
| HVAC-Rough | 6/23/2022 | Not Ready for Inspection | GORDON ZUBER |
| Interior/Exterior Lathing | 6/23/2022 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Rough | 6/23/2022 | Not Ready for Inspection | GORDON ZUBER |
| Rough-Elec/Plmb/HVAC | 6/23/2022 | Not Ready for Inspection | GORDON ZUBER |
| Verify Sprinkler Sign Off | 6/23/2022 | Not Ready for Inspection | GORDON ZUBER |
| BUILDING-Rough-Frame | 6/28/2022 | Approved | GORDON ZUBER |
| ELECTRICAL-Rough | 6/28/2022 | Approved | GORDON ZUBER |
| Green Building Rough | 6/28/2022 | Approved | GORDON ZUBER |
| HVAC-Rough | 6/28/2022 | Partial Approval | GORDON ZUBER |
| PLUMBING-Rough | 6/28/2022 | Approved | GORDON ZUBER |
| Special/Order Compliance | 6/28/2022 | Approved | GORDON ZUBER |
| Verify Sprinkler Sign Off | 6/28/2022 | Approved | GORDON ZUBER |
| Interior/Exterior Lathing | 8/17/2022 | Approved | GORDON ZUBER |
| Drywall Nailing | 12/6/2022 | Approved | ROBERT MINASSIANS |
| ELECTRICAL-Final | 12/6/2022 | Approved | ROBERT MINASSIANS |
| Final | 12/6/2022 | Corrections Issued | ROBERT MINASSIANS |
| Green Building Final | 12/6/2022 | Not Ready for Inspection | ROBERT MINASSIANS |
| HVAC-Final | 12/6/2022 | Approved | ROBERT MINASSIANS |
| PLUMBING-Final | 12/6/2022 | Approved | ROBERT MINASSIANS |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Approved | ROBERT MINASSIANS |
| Service/Power Release | 12/6/2022 | Not Required | ROBERT MINASSIANS |
| Smoke Detectors | 12/6/2022 | Approved | ROBERT MINASSIANS |
| Final | 2/2/2023 | Not Ready for Inspection | PATRICK LIEBREGT |
| Green Building Final | 2/2/2023 | Corrections Issued | PATRICK LIEBREGT |
| Verify Rec and Parks Fee Memo | 2/2/2023 | Approved | ROBERT MINASSIANS |
| Final | 3/8/2023 | OK to Issue CofO | PATRICK LIEBREGT |
| Green Building Final | 3/8/2023 | Approved | PATRICK LIEBREGT |