1622 W EWING ST 90026

Certificate Information: 1622 W EWING ST 90026

Application / Permit
17010-10000-04272
Plan Check / Job No.
B17LA20122
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING WITH 2-CAR CARPORT
Permit Issued
Issued on 10/23/2018
Issuing Office
Metro
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2017 APPLICANT
Assigned to Plan Check Engineer 11/8/2017 SINA KHOSRAVI
Green Plans Picked Up 11/16/2017 APPLICANT
Corrections Issued 11/22/2017 SINA KHOSRAVI
Quality Review Completed 12/18/2017 BILL STUTSMAN
Building Plans Picked Up 12/22/2017 APPLICANT
Applicant returned to address corrections 1/26/2018 SINA KHOSRAVI
Applicant returned to address corrections 2/2/2018 SINA KHOSRAVI
Applicant returned to address corrections 4/11/2018 SINA KHOSRAVI
Plan Check Approved 5/8/2018 SINA KHOSRAVI
Issued 10/23/2018 LADBS
CofO in Progress 2/22/2024 THOMAS LOGRASSO
Permit Finaled 2/27/2024 DEROLD HAUFF
CofO Issued 2/27/2024 DEROLD HAUFF
Permit Finaled 2/27/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/26/2018 ADRIAN SANCHEZ
Construction near power lines Cleared 1/26/2018 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 1/26/2018 ADRIAN SANCHEZ
Green Code Cleared 1/26/2018 KATHRYN BUTTERWORTH
Hydrant and Access approval Cleared 1/26/2018 JOHN CONNEALLY
Permit Cleared 1/26/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 4/27/2018 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/27/2018 NAZILA NOORIFAR
GPI Written Notices Cleared 5/8/2018 SINA KHOSRAVI
Grading Pre-Inspection Cleared 5/8/2018 SINA KHOSRAVI
Sewer availability Cleared 5/8/2018 CELINA MORENO

Contact Information

Contractor Property Developers Group Inc; Lic. No.: 975534-B 3835 E THOUSAND OAKS BLVD   SUITE #205    WESTLAKE VILLAGE, CA 91362
Engineer Le, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Minas, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Geologist Shant, Minas; Lic. No.: EG2607 566 RIVERDALE DR      GLENDALE, CA 91204

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/28/2019 Partial Approval DAVID CHAN
Footing/Foundation/Slab 8/2/2019 Conditional Approval DAVID CHAN
PLUMBING-Rough 8/26/2019 Not Ready for Inspection PIERRE VEGA
Footing/Foundation/Slab 8/29/2019 Partial Approval DAVID CHAN
PLUMBING-Rough 8/29/2019 Partial Approval DAVID CHAN
ELECTRICAL-Rough 10/18/2019 Partial Approval DAVID CHAN
PLUMBING-Rough 10/18/2019 Conditional Approval DAVID CHAN
PLUMBING-Rough 11/26/2019 Partial Inspection DAVID CHAN
Footing/Foundation/Slab 2/21/2020 Approved AJA COLLAY
ELECTRICAL-Rough 4/10/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 4/10/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 4/10/2020 Partial Approval KATHRYN BUTTERWORTH
Reinforced Concrete Frame 4/10/2020 Partial Approval KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 4/10/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Corrections Issued HAMIK HARTOUNIAN
Special/Order Compliance 1/15/2021 No Access for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/9/2021 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2021 Partial Approval STUART CHAPMAN
HVAC-Rough 4/9/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 4/9/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 4/21/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 4/21/2021 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 4/21/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 11/19/2021 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 11/19/2021 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 11/19/2021 Approved THOMAS LOGRASSO
Pre-Inspection 4/7/2022 Partial Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 6/1/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 6/1/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 6/1/2022 Not Ready for Inspection THOMAS LOGRASSO
Sewer 7/19/2022 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 7/21/2022 Partial Approval THOMAS LOGRASSO
Sewer 7/21/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 7/29/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 8/18/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 8/23/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 8/23/2022 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 8/23/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/6/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 10/3/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 10/3/2022 Not Ready for Inspection THOMAS LOGRASSO
Insulation 10/18/2022 Not Ready for Inspection THOMAS LOGRASSO
Insulation 10/27/2022 Conditional Approval THOMAS LOGRASSO
Underground Mechanical 10/27/2022 Partial Approval THOMAS LOGRASSO
Drywall Nailing 11/4/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Final 5/8/2023 Corrections Issued THOMAS LOGRASSO
Gas Test 5/8/2023 Approved THOMAS LOGRASSO
HVAC-Final 5/8/2023 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 5/8/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 5/26/2023 Approved THOMAS LOGRASSO
Drywall Nailing 5/26/2023 Approved THOMAS LOGRASSO
Final 5/26/2023 Corrections Issued THOMAS LOGRASSO
Green Building Final 5/26/2023 Not Ready for Inspection THOMAS LOGRASSO
Reinforced Concrete Frame 5/26/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 5/26/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 5/26/2023 Approved THOMAS LOGRASSO
Final 10/11/2023 Corrections Issued STUART CHAPMAN
Green Building Final 10/11/2023 Not Ready for Inspection STUART CHAPMAN
Service/Power Release 10/11/2023 Not Ready for Inspection STUART CHAPMAN
Final 2/2/2024 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 2/2/2024 Approved THOMAS LOGRASSO
Service/Power Release 2/2/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 2/21/2024 Approved THOMAS LOGRASSO
Final 2/21/2024 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Final 2/21/2024 Approved THOMAS LOGRASSO
PLUMBING-Final 2/21/2024 Approved THOMAS LOGRASSO
Service/Power Release 2/21/2024 Approved THOMAS LOGRASSO
Final 2/22/2024 OK to Issue CofO THOMAS LOGRASSO