|
Green Building Rough
|
6/24/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
6/24/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
6/24/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Green Building Rough
|
6/27/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
6/27/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Reinforced Masonry Frame
|
6/27/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
6/27/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
6/28/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/1/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/1/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
7/1/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/2/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/2/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
7/2/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
7/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
7/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/8/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/8/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/9/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/9/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/10/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/10/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/11/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Masonry
|
7/11/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
7/12/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Masonry
|
7/12/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
7/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Reinforced Masonry Frame
|
7/17/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
7/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
7/30/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
7/31/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/1/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/2/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/7/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/8/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
8/9/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/12/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/13/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/14/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
8/15/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/20/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Footing/Foundation/Slab
|
8/20/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
8/21/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
8/22/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Light Gage Steel Frame
|
8/22/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
8/23/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Steel/Welding
|
8/23/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
8/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
8/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
8/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Green Building Rough
|
8/26/2019
|
Approved
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
8/26/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
8/26/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
8/26/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
8/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
8/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/28/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
8/28/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
8/28/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/29/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
8/29/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
8/29/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
8/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
8/30/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/4/2019
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Steel/Welding
|
9/4/2019
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
9/4/2019
|
Partial Inspection
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Masonry
|
9/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
9/16/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/24/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Masonry
|
9/24/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Wood Construction
|
9/24/2019
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
9/25/2019
|
Approved
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Masonry
|
9/25/2019
|
Approved
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
9/25/2019
|
Approved
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
9/25/2019
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
9/25/2019
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Light Gage Steel Frame
|
9/25/2019
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
9/25/2019
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
9/25/2019
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
9/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/26/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
9/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
9/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
9/27/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
10/7/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/7/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
10/7/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
10/7/2019
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/9/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
10/10/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
10/11/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Footing/Foundation/Slab
|
10/11/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
10/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
10/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
10/16/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/21/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/21/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/24/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/24/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Steel/Welding
|
10/24/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
10/25/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
10/25/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
10/28/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Verify Sprinkler Sign Off
|
10/28/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Wood Frame
|
10/28/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
10/30/2019
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Masonry
|
10/30/2019
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Concrete
|
10/31/2019
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Masonry
|
10/31/2019
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Concrete
|
11/1/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
11/1/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
11/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/4/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/5/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/6/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/7/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/7/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/7/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
11/7/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
11/8/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/8/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/8/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/12/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/12/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/12/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Verify Sprinkler Sign Off
|
11/12/2019
|
Approved
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/13/2019
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Masonry
|
11/13/2019
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Wood Construction
|
11/13/2019
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Concrete
|
11/14/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/14/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/14/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Footing/Foundation/Slab
|
11/14/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/15/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
11/19/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/20/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
11/21/2019
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Masonry
|
11/21/2019
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Concrete
|
11/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Masonry
|
11/22/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
11/25/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
11/25/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
11/27/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
12/3/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Wood Frame
|
12/3/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
12/11/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Interior/Exterior Lathing
|
12/11/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
12/11/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
12/17/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Wood Frame
|
12/17/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
12/18/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Wood Frame
|
12/20/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
12/24/2019
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Masonry
|
12/27/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Wood Frame
|
12/30/2019
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
1/8/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
1/10/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Wood Frame
|
1/10/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
1/14/2020
|
Corrections Issued
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
1/15/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
1/15/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
1/16/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
1/17/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
1/21/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
1/21/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
1/21/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
1/22/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
1/29/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
1/29/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/3/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
2/4/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Insulation
|
2/4/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
2/4/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
2/6/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
2/7/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Light Gage Steel Frame
|
2/10/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/11/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/11/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Light Gage Steel Frame
|
2/11/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wall Anchors
|
2/11/2020
|
Partial Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/12/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
2/13/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Wood Frame
|
2/13/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
2/18/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
2/20/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/21/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/24/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Wood Frame
|
2/24/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
2/25/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Insulation
|
2/25/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
2/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/2/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
3/2/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/6/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
3/6/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
3/6/2020
|
Corrections Issued
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/9/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Insulation
|
3/9/2020
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
3/10/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
3/10/2020
|
Not Ready for Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/12/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
3/13/2020
|
No Access for Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/13/2020
|
No Access for Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/16/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
3/17/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
3/17/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/19/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
3/23/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wall Anchors
|
3/24/2020
|
Approved
|
ERNESTO CORRAL
|
|
Insulation
|
3/25/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/26/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/27/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Insulation
|
3/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
3/27/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
3/31/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
3/31/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/31/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
3/31/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
4/1/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Drywall Nailing
|
4/2/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Insulation
|
4/2/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Wood Frame
|
4/2/2020
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
4/3/2020
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Wood Construction
|
4/6/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
4/6/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
4/6/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
4/7/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Wood Frame
|
4/8/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Wood Construction
|
4/10/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
4/10/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Insulation
|
4/10/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
4/10/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
4/14/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
4/14/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
4/14/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Wood Construction
|
4/21/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
4/22/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
4/22/2020
|
Partial Inspection
|
DANIEL COLLINS
|
|
Deputy Wood Construction
|
4/24/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
4/27/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
4/27/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Wood Frame
|
4/27/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
4/28/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
4/28/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
5/4/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Interior/Exterior Lathing
|
5/4/2020
|
Partial Inspection
|
DANIEL COLLINS
|
|
Light Gage Steel Frame
|
5/4/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Interior/Exterior Lathing
|
5/5/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
5/8/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
5/8/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Insulation
|
5/11/2020
|
Not Ready for Inspection
|
RONALD PACHECO
|
|
Interior/Exterior Lathing
|
5/11/2020
|
Partial Approval
|
RONALD PACHECO
|
|
Drywall Nailing
|
5/14/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
5/18/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
5/18/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Interior/Exterior Lathing
|
5/18/2020
|
Partial Inspection
|
DANIEL COLLINS
|
|
Insulation
|
5/20/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Interior/Exterior Lathing
|
5/20/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
5/27/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Interior/Exterior Lathing
|
5/27/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
5/29/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
6/4/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Wood Construction
|
6/8/2020
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
6/9/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
6/11/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Wood Frame
|
6/11/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
6/15/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
6/15/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
6/16/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
6/19/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
6/24/2020
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
6/29/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Wood Frame
|
6/29/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
7/2/2020
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
7/8/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
7/10/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
7/13/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Light Gage Steel Frame
|
7/13/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
7/16/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Insulation
|
7/16/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
7/20/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
7/27/2020
|
Partial Approval
|
KATY RAMIREZ
|
|
Light Gage Steel Frame
|
7/28/2020
|
Partial Approval
|
RONALD PACHECO
|
|
Drywall Nailing
|
7/31/2020
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
8/4/2020
|
Corrections Issued
|
KATY RAMIREZ
|
|
Drywall Nailing
|
8/7/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Wood Construction
|
8/13/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Other (see comments)
|
8/18/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Special/Order Compliance
|
8/18/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Concrete
|
8/20/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Footing/Foundation/Slab
|
8/20/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Masonry Wall/Backfill
|
8/20/2020
|
Approved
|
DANIEL COLLINS
|
|
Drywall Nailing
|
8/26/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Masonry Wall/Backfill
|
8/26/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Masonry
|
8/27/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
8/27/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Concrete
|
8/31/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Steel/Welding
|
9/1/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Interior/Exterior Lathing
|
9/2/2020
|
Approved
|
DANIEL COLLINS
|
|
Masonry Wall/Backfill
|
9/2/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Masonry
|
9/3/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Deputy Reinf. Concrete
|
9/10/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Reinforced Concrete Frame
|
9/10/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
9/15/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
9/16/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
T-Bar Ceiling
|
9/29/2020
|
Conditional Approval
|
DANIEL COLLINS
|
|
Drywall Nailing
|
10/6/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Footing/Foundation/Slab
|
10/6/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Interior/Exterior Lathing
|
10/6/2020
|
Approved
|
DANIEL COLLINS
|
|
T-Bar Ceiling
|
10/20/2020
|
Partial Approval
|
NICK DANERI
|
|
T-Bar Ceiling
|
10/23/2020
|
Approved
|
DANIEL COLLINS
|
|
Green Building Final
|
10/26/2020
|
Not Ready for Inspection
|
DANIEL COLLINS
|
|
Special/Order Compliance
|
10/26/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Special/Order Compliance
|
11/9/2020
|
Partial Inspection
|
DANIEL COLLINS
|
|
SGSOV-Seismic Gas S/O Valve
|
11/13/2020
|
SGSOV Approved
|
DANIEL COLLINS
|
|
Pre-Inspection
|
11/23/2020
|
Not Ready for Inspection
|
DANIEL COLLINS
|
|
Pre-Inspection
|
11/24/2020
|
Partial Inspection
|
DANIEL COLLINS
|
|
Verify Rec and Parks Fee Memo
|
11/24/2020
|
Approved
|
DANIEL COLLINS
|
|
Smoke Detectors
|
11/25/2020
|
Approved
|
DANIEL COLLINS
|
|
Pre-Inspection
|
11/30/2020
|
Partial Inspection
|
DANIEL COLLINS
|
|
Special/Order Compliance
|
12/1/2020
|
Partial Inspection
|
DANIEL COLLINS
|
|
Drywall Nailing
|
12/2/2020
|
Approved
|
DANIEL COLLINS
|
|
Final
|
12/2/2020
|
Not Ready for Inspection
|
DANIEL COLLINS
|
|
Footing/Foundation/Slab
|
12/2/2020
|
Approved
|
DANIEL COLLINS
|
|
Green Building Final
|
12/2/2020
|
Not Ready for Inspection
|
DANIEL COLLINS
|
|
Reinforced Concrete Frame
|
12/2/2020
|
Approved
|
DANIEL COLLINS
|
|
Wood Frame
|
12/2/2020
|
Approved
|
DANIEL COLLINS
|
|
Pre-Inspection
|
12/3/2020
|
Partial Approval
|
DANIEL COLLINS
|
|
Pre-Inspection
|
4/26/2021
|
Approved
|
DANIEL COLLINS
|
|
Special/Order Compliance
|
5/11/2021
|
Partial Approval
|
DANIEL COLLINS
|
|
Final
|
6/1/2021
|
OK to Issue CofO
|
ERNESTO CORRAL
|
|
Green Building Final
|
6/1/2021
|
Approved
|
ERNESTO CORRAL
|