2200 E TROJAN WAY 90033

Certificate Information: 2200 E TROJAN WAY 90033

Application / Permit
17010-10000-04213
Plan Check / Job No.
B17LA19919
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
<<PDPP>>New 5-story, 200 room, Hotel / Retail /Restaurant over 1-level Basement Conference center <<4 story Type VA over first floor Type IA and Type IA basement>>
Permit Issued
Issued on 6/19/2019
Issuing Office
Metro
Current Status
CofO Issued on 6/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 DEAN LEE
Corrections Issued 4/23/2018 DEAN LEE
Quality Review Completed 4/25/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 4/27/2018 APPLICANT
Applicant returned to address corrections 6/29/2018 DEAN LEE
Applicant returned to address corrections 8/10/2018 DEAN LEE
Applicant returned to address corrections 10/11/2018 DEAN LEE
Applicant returned to address corrections 11/8/2018 DEAN LEE
Applicant returned to address corrections 12/13/2018 DEAN LEE
Applicant returned to address corrections 12/14/2018 DEAN LEE
Applicant returned to address corrections 12/20/2018 DEAN LEE
Applicant returned to address corrections 3/15/2019 DEAN LEE
Applicant returned to address corrections 4/12/2019 DEAN LEE
Applicant returned to address corrections 4/25/2019 DEAN LEE
Applicant returned to address corrections 5/1/2019 DEAN LEE
Applicant returned to address corrections 5/1/2019 NEGAR NEJAD
Applicant returned to address corrections 5/15/2019 DEAN LEE
Applicant returned to address corrections 5/17/2019 DEAN LEE
Plan Check Approved 5/17/2019 DEAN LEE
Issued 6/19/2019 LADBS
TCO Issued (Expire Date: 06-06-2021) 12/8/2020 ERNESTO CORRAL
CofO in Progress 6/1/2021 ERNESTO CORRAL
CofO Issued 6/1/2021 ERNESTO CORRAL
Permit Finaled 6/1/2021 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/7/2018 MICHAEL CASTILLO
Building over 3-story or 36-ft Cleared 5/9/2018 CALOSHA APPROVED
Permit Cleared 5/17/2018 STEVE MELGAR
Grading Pre-Inspection Cleared 5/18/2018 DEAN LEE
Miscellaneous Cleared 5/24/2018 TERRY PHAN
Project located in CRA area Cleared 6/6/2018 JIM URQUHART
Excavation more than 5-ft deep Cleared 7/31/2018 CALOSHA APPROVED
"Q" conditions Cleared 11/7/2018 MOTOUMI SASAKI
"T" removal Cleared 11/7/2018 MOTOUMI SASAKI
CPC Cleared 11/7/2018 MOTOUMI SASAKI
Highway dedication Cleared 11/7/2018 TERRY PHAN
ZA Case Cleared 11/7/2018 MOTOUMI SASAKI
ZA Case Cleared 11/7/2018 MOTOUMI SASAKI
Address approval Cleared 12/7/2018 NAZILA NOORIFAR
Low Impact Development Cleared 2/25/2019 AMMAR ELTAWIL
Work Adjacent to Public Way Cleared 3/7/2019 BOK GOH
Low Impact Development Cleared 3/12/2019 AMMAR ELTAWIL
Food Service Establishment Cleared 3/28/2019 KENNETH BROWNE
Roof/Waste drainage to street Cleared 4/1/2019 ELAINE LEI
Food establishment approval Cleared 4/4/2019 LACDHS APPROVED
CPC Cleared 4/26/2019 ANNA VAN
Fire Marshall Fire Life Safety Cleared 4/26/2019 OSCAR SALGADO JR
Hydrant and Access approval Cleared 5/3/2019 JOHN CONNEALLY
Miscellaneous Cleared 5/3/2019 KIT AWAKUNI
DAS Clearance Cleared 5/8/2019 DEAN LEE
Sewer availability Cleared 5/8/2019 KAREN LE
Green Code Cleared 5/17/2019 DEAN LEE
Miscellaneous Cleared 6/19/2019 ANNA VAN

Contact Information

Architect Wirz,, Patrick; Lic. No.: C16854 2841 CHESTNUT AVENUE      LONG BEACH, CA 90806
Contractor Kunzik & Sara Construction Inc; Lic. No.: 847939-B 1699 LA COSTA MEADOWS DR #102      SAN MARCOS, CA 92078
Engineer Gavazza,, Jeffrey Bryan; Lic. No.: C59894 472 35TH ST      MANHATTAN BEACH, CA 90266
Engineer Tang,, Stanley Siu Kei; Lic. No.: C56178 1105 N AVON STREET      BURBANK, CA 91505
Engineer Tanouye,, Russell; Lic. No.: S2850 888 S FIGUEROA ST 18TH FLOOR      LOS ANGELES, CA 90017

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 6/24/2019 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 6/24/2019 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 6/24/2019 Not Ready for Inspection ERNESTO CORRAL
Green Building Rough 6/27/2019 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 6/27/2019 Partial Inspection ERNESTO CORRAL
Reinforced Masonry Frame 6/27/2019 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 6/27/2019 Not Ready for Inspection ERNESTO CORRAL
Deputy Steel/Welding 6/28/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/1/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/1/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/1/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/2/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/2/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/2/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/3/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/3/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/3/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 7/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/8/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/8/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/9/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/9/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/10/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/10/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 7/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 7/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/17/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/17/2019 Conditional Approval ERNESTO CORRAL
Reinforced Masonry Frame 7/17/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/30/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 7/30/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/31/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/1/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/2/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/6/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/7/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/9/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/12/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/13/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/14/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/15/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/15/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 8/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/20/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/20/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/21/2019 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 8/22/2019 Conditional Approval LESLIE TRUJILLO
Light Gage Steel Frame 8/22/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/23/2019 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 8/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/26/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/26/2019 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 8/26/2019 Conditional Approval ERNESTO CORRAL
Green Building Rough 8/26/2019 Approved ERNESTO CORRAL
Light Gage Steel Frame 8/26/2019 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 8/26/2019 Not Ready for Inspection ERNESTO CORRAL
Wood Frame 8/26/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 8/27/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/27/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 8/27/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/28/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/28/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/28/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 8/29/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/29/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 8/29/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/30/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/30/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 9/4/2019 Approved HAMID PISHEHVAR
Deputy Steel/Welding 9/4/2019 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 9/4/2019 Partial Inspection HAMID PISHEHVAR
Deputy Reinf. Masonry 9/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/6/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 9/6/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 9/16/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 9/16/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 9/17/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 9/17/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 9/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 9/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/20/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 9/20/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/24/2019 Conditional Approval JEFFREY FULTON
Deputy Reinf. Masonry 9/24/2019 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/24/2019 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 9/25/2019 Approved RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/25/2019 Approved RAFAEL ESPINOZA
Deputy Wood Construction 9/25/2019 Approved RAFAEL ESPINOZA
Drywall Nailing 9/25/2019 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 9/25/2019 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/25/2019 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/25/2019 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 9/25/2019 Corrections Issued RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/26/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 9/26/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 9/27/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 9/27/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 9/27/2019 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 10/7/2019 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 10/7/2019 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 10/7/2019 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 10/7/2019 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 10/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/11/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/11/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 10/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 10/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/17/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/21/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 10/21/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/22/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 10/22/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/24/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 10/24/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 10/24/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/25/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 10/25/2019 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 10/28/2019 Conditional Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/28/2019 Conditional Approval LESLIE TRUJILLO
Wood Frame 10/28/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/30/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 10/30/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/31/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 10/31/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/1/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/1/2019 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 11/4/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/4/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/4/2019 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 11/4/2019 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 11/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 11/6/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/6/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/6/2019 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 11/7/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/7/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/7/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 11/7/2019 Partial Inspection ERNESTO CORRAL
Deputy Drilled-In Anchors 11/8/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/8/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/8/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/12/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/12/2019 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 11/12/2019 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 11/12/2019 Approved ERNESTO CORRAL
Deputy Reinf. Concrete 11/13/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 11/13/2019 Conditional Approval DANIEL COLLINS
Deputy Wood Construction 11/13/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/14/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/14/2019 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 11/14/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 11/14/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 11/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/18/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 11/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/20/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/20/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/21/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 11/21/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/22/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 11/22/2019 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 11/25/2019 Partial Inspection ERNESTO CORRAL
Wood Frame 11/25/2019 Partial Inspection ERNESTO CORRAL
Drywall Nailing 11/27/2019 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 12/3/2019 Conditional Approval ERNESTO CORRAL
Wood Frame 12/3/2019 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 12/11/2019 Conditional Approval ERNESTO CORRAL
Interior/Exterior Lathing 12/11/2019 Partial Inspection ERNESTO CORRAL
Wood Frame 12/11/2019 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 12/17/2019 Conditional Approval ERNESTO CORRAL
Wood Frame 12/17/2019 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 12/18/2019 Conditional Approval ERNESTO CORRAL
Wood Frame 12/20/2019 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 12/24/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 12/27/2019 Conditional Approval ERNESTO CORRAL
Wood Frame 12/30/2019 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 1/8/2020 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 1/10/2020 Conditional Approval ERNESTO CORRAL
Wood Frame 1/10/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 1/14/2020 Corrections Issued ERNESTO CORRAL
Drywall Nailing 1/15/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 1/15/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 1/16/2020 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 1/17/2020 Conditional Approval ERNESTO CORRAL
Drywall Nailing 1/21/2020 Partial Inspection ERNESTO CORRAL
Insulation 1/21/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 1/21/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 1/22/2020 Conditional Approval ERNESTO CORRAL
Drywall Nailing 1/29/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 1/29/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 2/3/2020 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 2/4/2020 Conditional Approval ERNESTO CORRAL
Insulation 2/4/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 2/4/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 2/6/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 2/7/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 2/10/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 2/11/2020 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Partial Inspection ERNESTO CORRAL
Light Gage Steel Frame 2/11/2020 Partial Inspection ERNESTO CORRAL
Wall Anchors 2/11/2020 Partial Approval ERNESTO CORRAL
Deputy Wood Construction 2/12/2020 Conditional Approval ERNESTO CORRAL
Drywall Nailing 2/13/2020 Partial Approval DANIEL COLLINS
Wood Frame 2/13/2020 Partial Approval DANIEL COLLINS
Insulation 2/18/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 2/20/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 2/21/2020 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 2/24/2020 Conditional Approval ERNESTO CORRAL
Wood Frame 2/24/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 2/25/2020 Conditional Approval ERNESTO CORRAL
Insulation 2/25/2020 Partial Inspection ERNESTO CORRAL
Drywall Nailing 2/27/2020 Partial Inspection ERNESTO CORRAL
Insulation 3/2/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 3/2/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 3/6/2020 Conditional Approval ERNESTO CORRAL
Drywall Nailing 3/6/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 3/6/2020 Corrections Issued ERNESTO CORRAL
Deputy Wood Construction 3/9/2020 Conditional Approval ERNESTO CORRAL
Insulation 3/9/2020 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 3/10/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 3/10/2020 Not Ready for Inspection ERNESTO CORRAL
Insulation 3/12/2020 Partial Inspection ERNESTO CORRAL
Drywall Nailing 3/13/2020 No Access for Inspection ERNESTO CORRAL
Insulation 3/13/2020 No Access for Inspection ERNESTO CORRAL
Deputy Wood Construction 3/16/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 3/17/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 3/17/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 3/19/2020 Conditional Approval RAFAEL ESPINOZA
Insulation 3/23/2020 Partial Inspection ERNESTO CORRAL
Wall Anchors 3/24/2020 Approved ERNESTO CORRAL
Insulation 3/25/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 3/26/2020 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 3/27/2020 Conditional Approval ERNESTO CORRAL
Insulation 3/27/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 3/27/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 3/31/2020 Conditional Approval ERNESTO CORRAL
Drywall Nailing 3/31/2020 Partial Inspection ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Inspection ERNESTO CORRAL
Insulation 3/31/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 4/1/2020 Conditional Approval ERNESTO CORRAL
Drywall Nailing 4/2/2020 Partial Inspection ERNESTO CORRAL
Insulation 4/2/2020 Partial Inspection ERNESTO CORRAL
Wood Frame 4/2/2020 Partial Inspection ERNESTO CORRAL
Deputy Wood Construction 4/3/2020 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 4/6/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 4/6/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 4/6/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 4/7/2020 Conditional Approval DANIEL COLLINS
Wood Frame 4/8/2020 Partial Approval DANIEL COLLINS
Deputy Wood Construction 4/10/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 4/10/2020 Partial Approval RAFAEL ESPINOZA
Insulation 4/10/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 4/10/2020 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/14/2020 Conditional Approval DANIEL COLLINS
Drywall Nailing 4/14/2020 Partial Approval DANIEL COLLINS
Insulation 4/14/2020 Partial Approval DANIEL COLLINS
Deputy Wood Construction 4/21/2020 Conditional Approval DANIEL COLLINS
Drywall Nailing 4/22/2020 Partial Approval DANIEL COLLINS
Insulation 4/22/2020 Partial Inspection DANIEL COLLINS
Deputy Wood Construction 4/24/2020 Conditional Approval DANIEL COLLINS
Drywall Nailing 4/27/2020 Partial Approval DANIEL COLLINS
Insulation 4/27/2020 Partial Approval DANIEL COLLINS
Wood Frame 4/27/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 4/28/2020 Partial Approval DANIEL COLLINS
Insulation 4/28/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 5/4/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 5/4/2020 Partial Inspection DANIEL COLLINS
Light Gage Steel Frame 5/4/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 5/5/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 5/8/2020 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/8/2020 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 5/11/2020 Not Ready for Inspection RONALD PACHECO
Interior/Exterior Lathing 5/11/2020 Partial Approval RONALD PACHECO
Drywall Nailing 5/14/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 5/18/2020 Partial Approval DANIEL COLLINS
Insulation 5/18/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 5/18/2020 Partial Inspection DANIEL COLLINS
Insulation 5/20/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 5/20/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 5/27/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 5/27/2020 Partial Approval DANIEL COLLINS
Insulation 5/29/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 6/4/2020 Partial Approval DANIEL COLLINS
Deputy Wood Construction 6/8/2020 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 6/9/2020 Partial Approval DANIEL COLLINS
Insulation 6/11/2020 Partial Approval DANIEL COLLINS
Wood Frame 6/11/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 6/15/2020 Partial Approval DANIEL COLLINS
Insulation 6/15/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 6/16/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 6/19/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 6/24/2020 Partial Approval NICK DANERI
Drywall Nailing 6/29/2020 Partial Approval DANIEL COLLINS
Wood Frame 6/29/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 7/2/2020 Partial Approval NICK DANERI
Drywall Nailing 7/8/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 7/10/2020 Partial Approval DANIEL COLLINS
Insulation 7/13/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 7/13/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 7/16/2020 Partial Approval DANIEL COLLINS
Insulation 7/16/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 7/20/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 7/27/2020 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 7/28/2020 Partial Approval RONALD PACHECO
Drywall Nailing 7/31/2020 Partial Approval NICK DANERI
Drywall Nailing 8/4/2020 Corrections Issued KATY RAMIREZ
Drywall Nailing 8/7/2020 Partial Approval DANIEL COLLINS
Deputy Wood Construction 8/13/2020 Conditional Approval DANIEL COLLINS
Deputy Other (see comments) 8/18/2020 Conditional Approval DANIEL COLLINS
Special/Order Compliance 8/18/2020 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 8/20/2020 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 8/20/2020 Partial Approval DANIEL COLLINS
Masonry Wall/Backfill 8/20/2020 Approved DANIEL COLLINS
Drywall Nailing 8/26/2020 Partial Approval DANIEL COLLINS
Masonry Wall/Backfill 8/26/2020 Partial Approval DANIEL COLLINS
Deputy Reinf. Masonry 8/27/2020 Conditional Approval DANIEL COLLINS
Drywall Nailing 8/27/2020 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 8/31/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 9/1/2020 Conditional Approval DANIEL COLLINS
Interior/Exterior Lathing 9/2/2020 Approved DANIEL COLLINS
Masonry Wall/Backfill 9/2/2020 Partial Approval DANIEL COLLINS
Deputy Reinf. Masonry 9/3/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 9/10/2020 Conditional Approval DANIEL COLLINS
Reinforced Concrete Frame 9/10/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 9/15/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 9/16/2020 Partial Approval DANIEL COLLINS
T-Bar Ceiling 9/29/2020 Conditional Approval DANIEL COLLINS
Drywall Nailing 10/6/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 10/6/2020 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 10/6/2020 Approved DANIEL COLLINS
T-Bar Ceiling 10/20/2020 Partial Approval NICK DANERI
T-Bar Ceiling 10/23/2020 Approved DANIEL COLLINS
Green Building Final 10/26/2020 Not Ready for Inspection DANIEL COLLINS
Special/Order Compliance 10/26/2020 Partial Approval DANIEL COLLINS
Special/Order Compliance 11/9/2020 Partial Inspection DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 11/13/2020 SGSOV Approved DANIEL COLLINS
Pre-Inspection 11/23/2020 Not Ready for Inspection DANIEL COLLINS
Pre-Inspection 11/24/2020 Partial Inspection DANIEL COLLINS
Verify Rec and Parks Fee Memo 11/24/2020 Approved DANIEL COLLINS
Smoke Detectors 11/25/2020 Approved DANIEL COLLINS
Pre-Inspection 11/30/2020 Partial Inspection DANIEL COLLINS
Special/Order Compliance 12/1/2020 Partial Inspection DANIEL COLLINS
Drywall Nailing 12/2/2020 Approved DANIEL COLLINS
Final 12/2/2020 Not Ready for Inspection DANIEL COLLINS
Footing/Foundation/Slab 12/2/2020 Approved DANIEL COLLINS
Green Building Final 12/2/2020 Not Ready for Inspection DANIEL COLLINS
Reinforced Concrete Frame 12/2/2020 Approved DANIEL COLLINS
Wood Frame 12/2/2020 Approved DANIEL COLLINS
Pre-Inspection 12/3/2020 Partial Approval DANIEL COLLINS
Pre-Inspection 4/26/2021 Approved DANIEL COLLINS
Special/Order Compliance 5/11/2021 Partial Approval DANIEL COLLINS
Final 6/1/2021 OK to Issue CofO ERNESTO CORRAL
Green Building Final 6/1/2021 Approved ERNESTO CORRAL