2450 E HOUSTON ST 1-10 90033

Certificate Information: 2450 E HOUSTON ST 1-10 90033

Application / Permit
17010-10000-04210
Plan Check / Job No.
B17LA19907
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3-STORY TYPE VB, 10 UNIT APARTMENT WITH 2 UNITS SET ASIDE FOR LOW INCOME
Permit Issued
Issued on 10/25/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2017 APPLICANT
Assigned to Plan Check Engineer 11/16/2017 CATHERINE CHEN
Green Plans Picked Up 11/21/2017 APPLICANT
Corrections Issued 11/28/2017 CATHERINE CHEN
Quality Review Completed 11/30/2017 JOHN VASQUEZ
Building Plans Picked Up 12/6/2017 APPLICANT
Disabled Access Plans Picked Up 12/6/2017 APPLICANT
Applicant returned to address corrections 4/27/2018 ZAW HAN
Applicant returned to address corrections 5/9/2018 ZAW HAN
Applicant returned to address corrections 6/13/2018 ZAW HAN
Plan Check Approved 6/25/2019 ZAW HAN
Issued 10/25/2019 LADBS
TCO Issued (Expire Date: 10-11-2023) 4/14/2023 ERNESTO CORRAL
CofO in Progress 7/12/2023 RAFAEL ESPINOZA
Permit Finaled 7/12/2023 ERNESTO CORRAL
CofO Issued 7/12/2023 ERNESTO CORRAL
Permit Finaled 7/12/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/16/2018 JAMES MORALEZ
Permit Cleared 3/16/2018 JAMES MORALEZ
ZI Cleared 3/21/2018 DIANA JIMENEZ
Green Code Cleared 3/30/2018 DONALD CRICHLOW
DAS Clearance Cleared 4/11/2018 CATHERINE CHEN
Hydrant and Access approval Cleared 5/21/2018 ROBERT DUFF
Frnt yard landscape/Water mgmt Cleared 6/13/2018 JESSE RAMOS
Opn space landscape/Water mgmt Cleared 6/13/2018 JESSE RAMOS
Prkng lot landscape/Water mgmt Cleared 6/13/2018 JESSE RAMOS
ZI Cleared 6/13/2018 JESSE RAMOS
Fire Marshall Fire Life Safety Cleared 7/5/2018 DOMINIQUE MEDINA
Eng Process Fee Ord 176,300 Cleared 3/14/2019 JEANETTE VONG
Low Impact Development Cleared 3/14/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/14/2019 JEANETTE VONG
Sewer availability Cleared 3/14/2019 JEANETTE VONG
Density Bonus 12.22.A.31 Cleared 5/29/2019 LOUIE MILLER
Grading Pre-Inspection Cleared 6/25/2019 CATHERINE CHEN

Contact Information

Architect Kivotos, Juan M; Lic. No.: C26491 1323 N NIAGARA STREET      BURBANK, CA 91505
Contractor Ponderosa Pines Gen Contractors; Lic. No.: 450947-B 9616 RIESHEL STREET      PICO RIVERA, CA 90660
Engineer Yogurtian, Arpinee; Lic. No.: C49916 2529 FOOTHILL BLVD, STE 208      LA CRESCENTA, CA 91214

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/14/2021 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 1/21/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 1/28/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Not Ready for Inspection RONALD PACHECO
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Partial Approval NICK DANERI
Green Building Rough 4/19/2021 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 4/19/2021 Partial Inspection NICK DANERI
Wood Frame 4/19/2021 Partial Approval NICK DANERI
Green Building Rough 5/11/2021 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 5/11/2021 Not Ready for Inspection NICK DANERI
Wood Frame 5/11/2021 Corrections Issued NICK DANERI
Green Building Rough 5/17/2021 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 5/17/2021 Conditional Approval NICK DANERI
Wood Frame 5/17/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Not Ready for Inspection NICK DANERI
Green Building Rough 6/1/2021 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 6/1/2021 Not Ready for Inspection NICK DANERI
Wood Frame 6/1/2021 Corrections Issued NICK DANERI
Green Building Rough 6/10/2021 Approved NICK DANERI
Verify Sprinkler Sign Off 6/10/2021 Not Ready for Inspection NICK DANERI
Wood Frame 6/10/2021 Partial Approval NICK DANERI
Insulation 6/16/2021 Partial Approval RAFAEL ESPINOZA
Insulation 6/21/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/13/2021 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/13/2021 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 8/24/2021 Partial Inspection RAFAEL ESPINOZA
Wood Frame 9/3/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 9/17/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 9/17/2021 Partial Approval RAFAEL ESPINOZA
Insulation 9/21/2021 Approved RAFAEL ESPINOZA
Interior/Exterior Lathing 9/21/2021 Approved RAFAEL ESPINOZA
Insulation 9/29/2021 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 10/6/2021 Approved RAFAEL ESPINOZA
Interior/Exterior Lathing 11/8/2021 Approved RAFAEL ESPINOZA
Final 5/6/2022 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 5/6/2022 Approved RAFAEL ESPINOZA
Green Building Final 5/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 5/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 5/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 5/12/2022 Corrections Issued RAFAEL ESPINOZA
Green Building Final 5/12/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 5/12/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 5/12/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/12/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 5/12/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 5/18/2022 Partial Inspection RAFAEL ESPINOZA
Final 7/22/2022 Partial Inspection RAFAEL ESPINOZA
Green Building Final 7/22/2022 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 7/22/2022 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/22/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 7/22/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 9/13/2022 Partial Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 9/13/2022 SGSOV Not Ready RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/13/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 9/13/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 12/19/2022 Partial Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Not Ready RAFAEL ESPINOZA
Verify Sprinkler Sign Off 12/19/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 12/19/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 2/16/2023 Partial Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 2/16/2023 SGSOV Not Ready RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/16/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 2/16/2023 Partial Approval RAFAEL ESPINOZA
Final 4/4/2023 Partial Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/4/2023 Approved RAFAEL ESPINOZA
Wood Frame 4/4/2023 Approved RAFAEL ESPINOZA
Final 4/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 7/12/2023 OK to Issue CofO RAFAEL ESPINOZA