2332 W LAS COLINAS AVE 90041
Certificate Information: 2332 W LAS COLINAS AVE 90041
- Application / Permit
- 17010-10000-04160
- Plan Check / Job No.
- B17LA19708
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF ACCESSORY DWELLING UNIT TO EXISTING GARAGE.
- Permit Issued
- Issued on 3/1/2021
- Issuing Office
- Current Status
- CofO Issued on 4/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2017 | TEODORO DIAZ RODRIGUEZ |
| Corrections Issued | 11/16/2017 | TEODORO DIAZ RODRIGUEZ |
| Quality Review Completed | 11/17/2017 | LARRY LEE |
| Green Plans Picked Up | 12/13/2017 | APPLICANT |
| Plan Check Approved | 2/26/2021 | TEODORO DIAZ RODRIGUEZ |
| Issued | 3/1/2021 | APPLICANT |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| CofO in Progress | 3/3/2022 | CRAIG VAUGHAN |
| CofO Issued | 4/25/2022 | DEROLD HAUFF |
| Permit Finaled | 4/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2018 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 6/4/2018 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 6/4/2018 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 6/4/2018 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2018 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 6/4/2018 | JOHN CONNEALLY |
| Sewer availability | Cleared | 6/4/2018 | STEVE MELGAR |
| Construction near power lines | Cleared | 1/17/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/11/2021 | MARTIN FRAGOSO |
| GPI Written Notices | Cleared | 2/26/2021 | TEODORO DIAZ RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 2/26/2021 | TEODORO DIAZ RODRIGUEZ |
| Green Code | Cleared | 2/26/2021 | DONALD CRICHLOW |
| Roof/Waste drainage to street | Cleared | 2/26/2021 | STEVE MELGAR |
Contact Information
| Architect | Allen, Daniel L; Lic. No.: C26736 | 1010 NORDICA DRIVE LOS ANGELES, CA 90065 |
| Contractor | Allwest Construction; Lic. No.: 513550-B | 550 E CALIFORNIA BLVD #18 PASADENA, CA 91106 |
| Engineer | Kim, Seung Su; Lic. No.: S5909 | 15808 APOLLO PLACE GARDENA, CA 90249 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2021 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 3/18/2021 | Approved | CRAIG VAUGHAN |
| Sewer | 4/6/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2021 | Approved | HAMIK HARTOUNIAN |
| Sewer | 4/20/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/10/2021 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/10/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 5/10/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 5/10/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/10/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 5/10/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/19/2021 | Approved | COREY HUPP |
| HVAC-Rough | 5/19/2021 | Approved | COREY HUPP |
| PLUMBING-Rough | 5/19/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 5/28/2021 | Approved | JOEL WILLIAMS |
| Interior/Exterior Lathing | 5/28/2021 | Partial Approval | JOEL WILLIAMS |
| Insulation | 6/2/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 6/7/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 6/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 8/25/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 8/25/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 8/25/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 8/25/2021 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 8/25/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 1/28/2022 | Approved | CRAIG VAUGHAN |
| Final | 1/28/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 1/28/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 1/28/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 1/28/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 1/28/2022 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 1/28/2022 | Approved | CRAIG VAUGHAN |
| Final | 3/2/2022 | OK to Issue CofO | CRAIG VAUGHAN |