12621 W RYE ST 91604
Certificate Information: 12621 W RYE ST 91604
- Application / Permit
- 17010-10000-04080
- Plan Check / Job No.
- B17LA19332
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (4) Gymnasium
- Work Description
- NEW 1-STORY GYMNASIUM RECREATION BUILDING
- Permit Issued
- Issued on 9/28/2023
- Issuing Office
- Metro
- Current Status
- Issued on 9/28/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/23/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2017 | RODOLFO ARIAS |
| Disabled Access Plans Picked Up | 11/14/2017 | APPLICANT |
| Green Plans Picked Up | 11/17/2017 | APPLICANT |
| Corrections Issued | 11/20/2017 | RICARDO SUPAN |
| Quality Review Completed | 11/28/2017 | SHUNYU ZHANG |
| Building Plans Picked Up | 11/30/2017 | APPLICANT |
| Applicant returned to address corrections | 10/30/2018 | RICARDO SUPAN |
| Applicant returned to address corrections | 11/1/2018 | RICARDO SUPAN |
| Applicant returned to address corrections | 11/29/2018 | RICARDO SUPAN |
| Plan Check Approved | 1/17/2019 | RODOLFO ARIAS |
| Issued | 9/28/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2018 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2018 | NAZILA NOORIFAR |
| Trees in Parkway | Cleared | 10/22/2018 | LUIS TORRES |
| Green Code | Cleared | 5/14/2019 | NEGAR NEJAD |
| DAS Clearance | Cleared | 5/23/2019 | WAI LAU |
| Hydrant and Access approval | Cleared | 5/23/2019 | GILBERT URREA |
| Permit | Cleared | 5/23/2019 | KARAN PATEL |
| Roof/Waste drainage to street | Cleared | 5/23/2019 | KARAN PATEL |
| Sewer availability | Cleared | 5/23/2019 | KARAN PATEL |
| Fire Marshall Fire Life Safety | Cleared | 6/25/2019 | MENOA AGHAJANI |
| Low Impact Development | Cleared | 6/25/2019 | RYAN HUDSON |
| Prkng lot landscape/Water mgmt | Cleared | 6/25/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 6/25/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 6/25/2019 | SOPHIE GABEL-SCHEINBAU |
| ZI | Cleared | 6/25/2019 | SOPHIE GABEL-SCHEINBAU |
| City owned building/parcel | Cleared | 6/26/2019 | HAROOT AVANESIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nastarin, Hooman; Lic. No.: C62199 | 1436 S LA CIENEGA BLVD 101 LOS ANGELES, CA 90035 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 3/19/2024 | Partial Inspection | JOHN KITCKO |
| Pre-Inspection | 10/16/2024 | Partial Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 11/12/2024 | Corrections Issued | JOHN KITCKO |
| Footing/Foundation/Slab | 11/13/2024 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 11/19/2024 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/11/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/12/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/13/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/16/2024 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/17/2024 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/19/2024 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/20/2024 | Approved | JOHN KITCKO |
| Reinforced Concrete Frame | 12/20/2024 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/23/2024 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 2/10/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 2/21/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 2/24/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 2/25/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 2/26/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 2/27/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/3/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 3/4/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/5/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/6/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 3/7/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 3/18/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 3/19/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 3/20/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 3/21/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 3/24/2025 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 3/27/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 3/28/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/8/2025 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 4/9/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/10/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/11/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/14/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/15/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/16/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/17/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/18/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/21/2025 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 4/22/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/23/2025 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 4/23/2025 | Partial Approval | JOHN KITCKO |
| Reinforced Concrete Frame | 4/23/2025 | Partial Approval | JOHN KITCKO |
| Deputy Steel/Welding | 4/24/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 4/25/2025 | Approved | JOHN KITCKO |
| Light Gage Steel Frame | 4/30/2025 | Partial Inspection | JOHN KITCKO |
| Pre-Inspection | 4/30/2025 | Partial Inspection | JOHN KITCKO |
| Deputy Pre-Stress Concrete | 5/2/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 5/8/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 5/9/2025 | Approved | JOHN KITCKO |
| Light Gage Steel Frame | 5/9/2025 | Partial Inspection | JOHN KITCKO |
| Deputy Steel/Welding | 5/12/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 5/13/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 5/14/2025 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 5/19/2025 | Partial Approval | JOHN KITCKO |
| Light Gage Steel Frame | 6/23/2025 | Partial Inspection | JOHN KITCKO |
| Deputy Steel/Welding | 7/30/2025 | Approved | JOHN KITCKO |
| Light Gage Steel Frame | 7/30/2025 | Partial Inspection | JOHN KITCKO |
| Deputy Steel/Welding | 7/31/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/1/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/4/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/5/2025 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 11/24/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 11/25/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 11/26/2025 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 1/6/2026 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 1/7/2026 | Conditional Approval | GREGORY POMISH |
| Deputy Steel/Welding | 1/8/2026 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 1/9/2026 | Approved | JOHN KITCKO |
| Deputy Steel/Welding | 1/12/2026 | Approved | JOHN KITCKO |