6565 E PICKWICK ST 90042

Certificate Information: 6565 E PICKWICK ST 90042

Application / Permit
17010-10000-04070
Plan Check / Job No.
B17LA19274
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW TWO-STORY 34'-10" X 37'-11" SINGLE FAMILY DWELLING WITH ATTACHED 400 SF BASEMENT GARAGE AND AN IRREGULAR 22.5' X 25' ROOFTOP DECK. WORK PER DESIGN.
Permit Issued
Issued on 9/10/2021
Issuing Office
Valley
Current Status
CofO Issued on 10/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2017 APPLICANT
Assigned to Plan Check Engineer 11/2/2017 NIKTA MOUSAVI
Corrections Issued 11/14/2017 NIKTA MOUSAVI
Green Plans Picked Up 11/15/2017 APPLICANT
Quality Review Completed 12/11/2017 BILL STUTSMAN
Applicant returned to address corrections 2/16/2018 NIKTA MOUSAVI
Applicant returned to address corrections 4/20/2018 NIKTA MOUSAVI
Applicant returned to address corrections 5/10/2018 NIKTA MOUSAVI
Applicant returned to address corrections 6/7/2018 NIKTA MOUSAVI
Applicant returned to address corrections 9/8/2020 LUIS RINCON
Applicant returned to address corrections 10/6/2020 LUIS RINCON
Applicant returned to address corrections 1/6/2021 LUIS RINCON
Applicant returned to address corrections 3/11/2021 LUIS RINCON
Applicant returned to address corrections 4/10/2021 LUIS RINCON
Applicant returned to address corrections 5/13/2021 LUIS RINCON
Applicant returned to address corrections 6/25/2021 LUIS RINCON
Plan Check Approved 8/12/2021 LUIS RINCON
Issued 9/10/2021 APPLICANT
Building Plans Picked Up 9/10/2021 APPLICANT
CofO in Progress 10/1/2024 LILIANA PORTILLO
Permit Finaled 10/24/2024 RUBEN SALAS
CofO Issued 10/24/2024 RUBEN SALAS
Permit Finaled 10/24/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/29/2018 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/29/2018 LEE GUILBEAUX
Green Code Cleared 7/10/2018 NEGAR NEJAD
Hydrant and Access approval Cleared 7/19/2018 JOHN DALLAS
Construction near power lines Cleared 8/18/2018 RIDWAN HARDY
BHO/Hillside ordinance Cleared 8/1/2019 JULIUS GARCIA
BHO/Hillside ordinance Cleared 8/1/2019 JULIUS GARCIA
HPOZ Cleared 9/30/2019 MARITZA PRZEKOP
Miscellaneous Cleared 9/30/2019 MARITZA PRZEKOP
ZA Case Cleared 9/30/2019 MARITZA PRZEKOP
ZA Case Cleared 9/30/2019 MARITZA PRZEKOP
BHO/Hillside ordinance Cleared 10/1/2019 THOMAS LANG
Permit Cleared 10/1/2019 THOMAS LANG
Low Impact Development Cleared 10/4/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/4/2019 THOMAS LANG
Excavation more than 5-ft deep Cleared 12/20/2019 CALOSHA APPROVED
Sewer availability Cleared 7/10/2020 THOMAS LANG
Encroachment in public way Cleared 4/1/2021 ELAINE LEI
Public Works-Open Permits Cleared 9/24/2024 MANLEEN UBHI

Contact Information

Contractor Owner-Builder       ,
Engineer Husain, Shahzain; Lic. No.: C62744 1710 N MOORPARK RD #100      THOUSAND OAKS, CA 91360
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670
Engineer Lewis, Stephen H; Lic. No.: C70304 169 S BALDWIN AVE      SIERRA MADRE, CA 91024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/6/2022 Conditional Approval AMY COLIN
Deputy Reinf. Concrete 4/11/2022 Conditional Approval AMY COLIN
Footing/Foundation/Slab 9/27/2022 Partial Approval AMY COLIN
Footing/Foundation/Slab 10/21/2022 Partial Approval AMY COLIN
Footing/Foundation/Slab 12/7/2022 Partial Approval AMY COLIN
PLUMBING-Rough 12/7/2022 Partial Approval AMY COLIN
Deputy Shotcrete 4/3/2023 Conditional Approval AMY COLIN
PLUMBING-Rough 4/11/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 4/17/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Corrections Issued AMY COLIN
Insulation 6/26/2023 Not Ready for Inspection AMY COLIN
ELECTRICAL-Rough 7/5/2023 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 7/5/2023 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 7/10/2023 Approved AMY COLIN
PLUMBING-Rough 7/10/2023 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 7/25/2023 Partial Approval AMY COLIN
PLUMBING-Rough 7/31/2023 Approved AMY COLIN
BUILDING-Rough-Frame 8/21/2023 Partial Approval AMY COLIN
Green Building Rough 8/21/2023 Approved AMY COLIN
HVAC-Rough 8/21/2023 Approved AMY COLIN
Interior/Exterior Lathing 8/21/2023 Partial Approval AMY COLIN
Verify Sprinkler Sign Off 8/21/2023 Approved AMY COLIN
BUILDING-Rough-Frame 9/1/2023 Approved AMY COLIN
Insulation 9/1/2023 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Corrections Issued AMY COLIN
Drywall Nailing 9/14/2023 Approved AMY COLIN
Sewer 10/12/2023 Corrections Issued AMY COLIN
Sewer 10/13/2023 Approved AMY COLIN
ELECTRICAL-Final 1/9/2024 Approved AMY COLIN
PLUMBING-Final 1/9/2024 Approved AMY COLIN
HVAC-Final 5/6/2024 Corrections Issued LILIANA PORTILLO
HVAC-Final 5/31/2024 Approved LILIANA PORTILLO
Final 9/26/2024 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 9/26/2024 Approved ROY SPAULDING
Green Building Final 9/26/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 9/26/2024 SGSOV Approved ROY SPAULDING
Service/Power Release 9/26/2024 Not Ready for Inspection ROY SPAULDING
Smoke Detectors 9/26/2024 Approved ROY SPAULDING
Final 9/30/2024 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 9/30/2024 Approved LILIANA PORTILLO