1371 N DOUGLAS ST 90026
Certificate Information: 1371 N DOUGLAS ST 90026
- Application / Permit
- 17010-10000-04040
- Plan Check / Job No.
- B17LA19034
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SMALL LOT SUBDIVISION (lot 1) - 1 SINGLE FAMILY DWELLING W/ ATT. GARAGE AND ROOF DECK, USING STATE APPROVED STRUCTURES
- Permit Issued
- Issued on 7/17/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2017 | SAM CHANG |
| Green Plans Picked Up | 11/3/2017 | APPLICANT |
| Corrections Issued | 11/7/2017 | SAM CHANG |
| Quality Review Completed | 11/16/2017 | JOHN VASQUEZ |
| Building Plans Picked Up | 11/16/2017 | APPLICANT |
| Applicant returned to address corrections | 11/29/2017 | SAM CHANG |
| Applicant returned to address corrections | 12/21/2017 | SAM CHANG |
| Applicant returned to address corrections | 5/10/2018 | SAM CHANG |
| Applicant returned to address corrections | 8/7/2018 | SAM CHANG |
| Applicant returned to address corrections | 10/12/2018 | SAM CHANG |
| Applicant returned to address corrections | 11/15/2018 | SAM CHANG |
| Applicant returned to address corrections | 11/29/2018 | SAM CHANG |
| Applicant returned to address corrections | 12/6/2018 | SAM CHANG |
| Applicant returned to address corrections | 2/21/2019 | SAM CHANG |
| Plan Check Approved | 3/6/2019 | SAM CHANG |
| Plan Check Approved | 7/9/2019 | SAM CHANG |
| Issued | 7/17/2019 | LADBS |
| CofO in Progress | 3/2/2022 | SCOTT FINNILA |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
| CofO Issued | 3/5/2022 | DEROLD HAUFF |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2018 | STEVE MELGAR |
| Low Impact Development | Cleared | 3/19/2018 | MITESH PATEL |
| Miscellaneous | Cleared | 3/20/2018 | ZEMAMU GEBREWOLD |
| Permit | Cleared | 3/20/2018 | ZEMAMU GEBREWOLD |
| Frnt yard landscape/Water mgmt | Cleared | 3/22/2018 | SEAN VEAL |
| Miscellaneous | Cleared | 3/22/2018 | SEAN VEAL |
| Roof/Waste drainage to street | Cleared | 3/22/2018 | STEVE MELGAR |
| ZA Case | Cleared | 3/22/2018 | SEAN VEAL |
| Sewer availability | Cleared | 3/23/2018 | NAZILA NOORIFAR |
| GPI Written Notices | Cleared | 11/15/2018 | SAM CHANG |
| Grading Pre-Inspection | Cleared | 11/15/2018 | SAM CHANG |
| Miscellaneous | Cleared | 12/3/2018 | JOSE ROMERO-NAVARRO |
| Miscellaneous | Cleared | 12/3/2018 | JOSE ROMERO-NAVARRO |
| Address approval | Cleared | 3/6/2019 | ERIK BEASLEY |
| Green Code | Cleared | 4/22/2019 | SAM CHANG |
| Hydrant and Access approval | Cleared | 4/24/2019 | GEORGE SUCHAND |
| Hold | Cleared | 8/1/2019 | CYNTHIA RYAN |
Contact Information
| Architect | Krager,, Christopher Ronald; Lic. No.: C36896 | 916 SPRINGDALE ROAD, BLDG #5 AUSTIN, TX 78702 |
| Contractor | Owner-Builder | , |
| Engineer | Albus,, David Edward; Lic. No.: GE2455 | 1612 WINDSOR LN SANTA ANA, CA 92705 |
| Engineer | Lothrop,, Shawn Duane; Lic. No.: S5627 | 40810 COUNTY CENTER DR STE 110 TEMECULA, CA 92563 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 7/22/2019 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 7/23/2019 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 7/29/2019 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/7/2019 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/20/2019 | Conditional Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/23/2019 | Partial Approval | SCOTT FINNILA |
| Masonry Wall/Backfill | 9/17/2019 | Conditional Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/30/2019 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 9/30/2019 | Not Ready for Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 9/30/2019 | Not Ready for Inspection | SCOTT FINNILA |
| Deputy Reinf. Masonry | 10/1/2019 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 10/4/2019 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2019 | Partial Approval | SCOTT FINNILA |
| Structural Steel Frame | 10/8/2019 | Corrections Issued | SCOTT FINNILA |
| Deputy Steel/Welding | 10/10/2019 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 10/10/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2019 | Partial Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 10/30/2019 | Partial Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 10/31/2019 | Conditional Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 11/1/2019 | Partial Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 11/5/2019 | Partial Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 2/21/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 3/5/2020 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/17/2020 | No Access for Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/18/2020 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 4/21/2020 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 4/21/2020 | Corrections Issued | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 4/21/2020 | Corrections Issued | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/14/2020 | Partial Inspection | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/18/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/22/2020 | Conditional Approval | SCOTT FINNILA |
| PLUMBING-Rough | 6/22/2020 | Conditional Approval | SCOTT FINNILA |
| Drywall Nailing | 7/27/2020 | Corrections Issued | SCOTT FINNILA |
| Sewer | 8/28/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/15/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 9/15/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/17/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/14/2020 | Approved | SCOTT FINNILA |
| Green Building Rough | 10/14/2020 | Approved | SCOTT FINNILA |
| Insulation | 10/14/2020 | Approved | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 10/14/2020 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 10/14/2020 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/21/2021 | SGSOV Not Required | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 5/11/2021 | Partial Inspection | SCOTT FINNILA |
| Underground Mechanical | 5/11/2021 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Final | 7/27/2021 | Approved | SCOTT FINNILA |
| Service/Power Release | 7/27/2021 | Partial Inspection | SCOTT FINNILA |
| Service/Power Release | 9/9/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 9/14/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 9/20/2021 | Approved | SCOTT FINNILA |
| Smoke Detectors | 9/20/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 9/28/2021 | Not Ready for Inspection | SCOTT FINNILA |
| PLUMBING-Final | 10/4/2021 | Approved | SCOTT FINNILA |
| Final | 10/20/2021 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 10/20/2021 | Approved | SCOTT FINNILA |
| Grading Pre-Inspection | 10/26/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 11/13/2021 | Off-Hour Fees Due | |
| Service/Power Release | 11/13/2021 | Off-Hour Fees Due | |
| Final | 11/15/2021 | Corrections Issued | SCOTT FINNILA |
| Service/Power Release | 11/15/2021 | Partial Inspection | SCOTT FINNILA |
| Service/Power Release | 11/17/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 12/7/2021 | Corrections Issued | SCOTT FINNILA |
| Service/Power Release | 2/23/2022 | Approved | SCOTT FINNILA |
| Final | 2/28/2022 | Corrections Issued | SCOTT FINNILA |
| Final | 3/2/2022 | OK to Issue CofO | SCOTT FINNILA |