2948 S HARVARD BLVD 90018

Certificate Information: 2948 S HARVARD BLVD 90018

Application / Permit
17010-10000-03993
Plan Check / Job No.
B17LA18720
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ONE-STORY DETACHED ACCESSORY DWELLING UNIT PER AB2299 AND SB1069 WITH ATTACHED STORAGE
Permit Issued
Issued on 8/21/2018
Issuing Office
Metro
Current Status
CofO Issued on 2/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2017 APPLICANT
Assigned to Plan Check Engineer 10/19/2017 CHRISTOPHER KOMANCHECK
Green Plans Picked Up 10/31/2017 APPLICANT
Corrections Issued 11/6/2017 CHRISTOPHER KOMANCHECK
Quality Review Completed 11/13/2017 ROSHANAK VARJAVAND
Building Plans Picked Up 11/15/2017 APPLICANT
Plan Check Approved 3/27/2018 CHRISTOPHER KOMANCHECK
Plan Check Approved 5/21/2018 CHRISTOPHER KOMANCHECK
Issued 8/21/2018 LADBS
CofO in Progress 2/23/2022 ALIZAH MAYAGOITIA
Permit Finaled 2/26/2022 DEROLD HAUFF
CofO Issued 2/26/2022 DEROLD HAUFF
Permit Finaled 2/26/2022 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 11/6/2017 PRECY SANCHEZ
Address approval Cleared 2/16/2018 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 2/16/2018 JAMES MORALEZ
Sewer availability Cleared 2/16/2018 JAMES MORALEZ
Green Code Cleared 2/22/2018 NEGAR NEJAD
Low Impact Development Cleared 2/22/2018 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/22/2018 NAZILA NOORIFAR

Contact Information

Architect , ; Lic. No.: C35777 1375 HAUSER BLVD      LOS ANGELES, CA 90019
Contractor Owner-Builder       ,
Engineer Abedian, Vanik; Lic. No.: S5323 2906 JOLLEY DR      BURBANK, CA 91504

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/21/2018 Approved VICTOR PUKHALSKY
BUILDING-Rough-Frame 4/17/2019 Partial Approval AJA COLLAY
METHANE-Barrier 4/17/2019 Approved AJA COLLAY
METHANE-Subgrade 4/17/2019 Approved AJA COLLAY
Insulation 4/19/2019 Conditional Approval ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 4/22/2019 Not Ready for Inspection AJA COLLAY
Floor/Roof Diaphrgm/Shear Wall 4/26/2019 Approved AJA COLLAY
Insulation 8/26/2019 Approved ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 8/27/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/29/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/18/2019 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 1/13/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 1/13/2020 Corrections Issued DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 1/13/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 2/11/2020 Conditional Approval ROBERT MCDOWELL
ELECTRICAL-Rough 2/11/2020 Approved ROBERT MCDOWELL
Green Building Rough 2/11/2020 Approved ROBERT MCDOWELL
HVAC-Rough 2/11/2020 Approved ROBERT MCDOWELL
METHANE-Rough 2/11/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 2/11/2020 Approved ROBERT MCDOWELL
Underground Mechanical 2/11/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 2/11/2020 Not Ready for Inspection ROBERT MCDOWELL
Insulation 2/14/2020 Not Ready for Inspection DAVID CHAN
Insulation 2/19/2020 Approved HORACE FULTZ
Drywall Nailing 2/26/2020 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 3/2/2020 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/2/2020 Corrections Issued ALEJANDRO DE ARTOLA
Shower Pan 3/2/2020 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 3/6/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 3/6/2020 Partial Approval RUBEN SALAS
Shower Pan 3/6/2020 Approved RUBEN SALAS
Service/Power Release 8/24/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/10/2021 Approved KATHRYN BUTTERWORTH
Final 11/10/2021 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 11/10/2021 Approved KATHRYN BUTTERWORTH
Green Building Final 11/10/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 11/10/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 11/10/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 11/10/2021 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 11/10/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 2/22/2022 Approved ALIZAH MAYAGOITIA
Final 2/22/2022 OK to Issue CofO ALIZAH MAYAGOITIA
HVAC-Final 2/22/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 2/22/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/22/2022 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 2/22/2022 Approved ALIZAH MAYAGOITIA