950 W 76TH ST 1-50 90044
Certificate Information: 950 W 76TH ST 1-50 90044
- Application / Permit
- 17010-10000-03985
- Plan Check / Job No.
- B17LA18684
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- PROPOSED 3 STORY 50 UNIT AFFORDABLE HOUSING OVER 1 STORY PARKING GARAGE AND RETAIL/RECORDING STUDIO (CORE&SHELL ONLY) PER DIR-2018-5601-TOC. 6 VERY LOW INCOME AND 43 LOW INCOME UNITS.
- Permit Issued
- Issued on 7/23/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2017 | ARMEN JIVALAGIAN |
| Disabled Access Plans Picked Up | 10/31/2017 | APPLICANT |
| Corrections Issued | 11/7/2017 | ARMEN JIVALAGIAN |
| Quality Review Completed | 11/13/2017 | SIAVOSH POURSABAHIAN |
| Building Plans Picked Up | 11/16/2017 | APPLICANT |
| Applicant returned to address corrections | 2/22/2018 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 2/28/2018 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 3/19/2019 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 5/2/2019 | ARMEN JIVALAGIAN |
| Plan Check Approved | 7/19/2019 | ARMEN JIVALAGIAN |
| Issued | 7/23/2019 | LADBS |
| TCO Issued (Expire Date: 09-18-2021) | 3/22/2021 | ERNESTO CORRAL |
| TCO Issued (Expire Date: 03-19-2022) | 9/20/2021 | DAVID TSAU |
| CofO in Progress | 12/8/2021 | JAMES POWERS |
| Permit Finaled | 12/30/2021 | ERNESTO CORRAL |
| CofO Issued | 12/30/2021 | ERNESTO CORRAL |
| Permit Finaled | 12/30/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 12/5/2017 | NORALI MARTINEZ |
| Comm Cor/Mini-Mall | Cleared | 12/5/2017 | NORALI MARTINEZ |
| ZA Case | Cleared | 12/5/2017 | NORALI MARTINEZ |
| ZA Case | Cleared | 12/5/2017 | NORALI MARTINEZ |
| Address approval | Cleared | 12/12/2017 | KENNETH PHAM |
| Bicycle Parking | Cleared | 12/14/2017 | FATIMA GUERRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2017 | JAMES MORALEZ |
| Encroachment in public way | Cleared | 12/20/2017 | JAMES KHO |
| Building over 3-story or 36-ft | Cleared | 1/24/2018 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 1/24/2018 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 2/23/2018 | JOHN CONNEALLY |
| Green Code | Cleared | 3/2/2018 | DONALD CRICHLOW |
| Disturb/Remove Protected Trees | Cleared | 3/23/2018 | LUIS TORRES |
| Construction near power lines | Cleared | 8/24/2018 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 5/8/2019 | ERIK BEASLEY |
| Community Plan Implem. Overlay | Cleared | 5/8/2019 | WALTER RAMIREZ |
| Construction within easement | Cleared | 5/8/2019 | WALTER RAMIREZ |
| Community Plan Implem. Overlay | Cleared | 5/9/2019 | MOHAMMAD HASAN |
| Fire Marshall Fire Life Safety | Cleared | 5/13/2019 | ANDREW KO |
| Community Plan Implem. Overlay | Cleared | 5/15/2019 | JOHN KIM |
| Trees in Parkway | Cleared | 5/15/2019 | JOHN KIM |
| DAS Clearance | Cleared | 5/16/2019 | ARMEN JIVALAGIAN |
| Project located in CRA area | Cleared | 6/7/2019 | JIM URQUHART |
| Low Impact Development | Cleared | 6/13/2019 | ORVAL HERNANDEZ-MARCI |
| Certificate of Compliance | Cleared | 6/18/2019 | MARC WOERSCHING |
| Miscellaneous | Cleared | 6/18/2019 | MARC WOERSCHING |
| Roof/Waste drainage to street | Cleared | 6/21/2019 | ELAINE LEI |
| DCP conditions approval | Cleared | 6/24/2019 | LOUIE MILLER |
| Density Bonus 12.22.A.31 | Cleared | 6/24/2019 | LOUIE MILLER |
| Miscellaneous | Cleared | 6/26/2019 | JOE LUCKEY |
| Site Plan review | Cleared | 6/26/2019 | JOE LUCKEY |
| ZI | Cleared | 6/26/2019 | JOE LUCKEY |
| Comm Cor/Mini-Mall | Cleared | 6/27/2019 | KIT AWAKUNI |
| Miscellaneous | Cleared | 6/27/2019 | DIANA JIMENEZ |
| Miscellaneous | Cleared | 6/27/2019 | DIANA JIMENEZ |
| Opn space landscape/Water mgmt | Cleared | 6/27/2019 | DIANA JIMENEZ |
| Sewer availability | Cleared | 6/27/2019 | JEANIE LAM |
| Highway dedication | Cleared | 6/28/2019 | VICTOR MENDOZA |
| Permit | Cleared | 6/28/2019 | VICTOR MENDOZA |
| Work Adjacent to Public Way | Cleared | 7/1/2019 | BOK GOH |
Contact Information
| Architect | Yanez, Arturo; Lic. No.: C24019 | 4061 BEVERLY GLEN BL SHERMAN OAKS, CA 91423 |
| Contractor | United Building Company Inc; Lic. No.: 1034972-B | 250 N. HARBOR DRIVE SUITE 311 REDONDO BEACH, CA 90277 |
| Engineer | Berliner,, Neal David; Lic. No.: GE2576 | 4913 MONUMENT ST SIMI VALLEY, CA 93063 |
| Engineer | Nam, Young-Keun; Lic. No.: S4029 | 17 SANTA EUGENIA IRVINE, CA 92606 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/18/2019 | Not Ready for Inspection | JAMES POWERS |
| Pre-Inspection | 9/18/2019 | Approved | JAMES POWERS |
| Deputy Reinf. Concrete | 9/23/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/24/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/25/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/26/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/27/2019 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 10/1/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 10/8/2019 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 10/8/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 10/16/2019 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 10/16/2019 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 10/21/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 10/22/2019 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 10/23/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 11/6/2019 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 11/6/2019 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 11/13/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 11/14/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 11/15/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 12/11/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 12/13/2019 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 12/13/2019 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 12/16/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 12/18/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 12/19/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 12/20/2019 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/3/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/6/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/7/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/8/2020 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 1/8/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/9/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/10/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/13/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/14/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/15/2020 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 1/15/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/16/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/17/2020 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 1/23/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 1/28/2020 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 1/28/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/29/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/30/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/31/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 2/14/2020 | Partial Approval | JAMES POWERS |
| Reinforced Concrete Frame | 2/14/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 2/19/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 2/20/2020 | Conditional Approval | LESLIE TRUJILLO |
| Excavation/Setback/Form/Re-Bar | 2/21/2020 | Not Ready for Inspection | JAMES POWERS |
| Green Building Rough | 2/27/2020 | Approved | JAMES POWERS |
| Reinforced Concrete Frame | 2/27/2020 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 2/27/2020 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Concrete Frame | 2/28/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 3/27/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 4/14/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 5/12/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2020 | Partial Approval | JAMES POWERS |
| Wood Frame | 5/14/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 5/26/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Partial Approval | JAMES POWERS |
| Insulation | 6/3/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 6/12/2020 | Partial Approval | JAMES POWERS |
| Insulation | 6/12/2020 | Partial Approval | JAMES POWERS |
| Insulation | 6/17/2020 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 6/17/2020 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 6/30/2020 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 7/9/2020 | Partial Approval | JAMES POWERS |
| Insulation | 7/9/2020 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 7/23/2020 | Partial Approval | JAMES POWERS |
| Insulation | 7/23/2020 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/27/2020 | Approved | JAMES POWERS |
| Interior/Exterior Lathing | 8/27/2020 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 12/7/2020 | Partial Approval | JAMES POWERS |
| T-Bar Ceiling | 12/7/2020 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 1/26/2021 | Approved | JAMES POWERS |
| Final | 2/22/2021 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 2/22/2021 | Approved | JAMES POWERS |
| Green Building Final | 2/22/2021 | Approved | JAMES POWERS |
| Reinforced Concrete Frame | 2/22/2021 | Partial Approval | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2021 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 2/22/2021 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 2/22/2021 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 2/22/2021 | Partial Approval | JAMES POWERS |
| Special/Order Compliance | 8/26/2021 | Approved | JAMES POWERS |
| Final | 12/8/2021 | OK to Issue CofO | JAMES POWERS |
| Reinforced Concrete Frame | 12/8/2021 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 12/8/2021 | Approved | JAMES POWERS |
| Wood Frame | 12/8/2021 | Approved | JAMES POWERS |