950 W 76TH ST 1-50 90044

Certificate Information: 950 W 76TH ST 1-50 90044

Application / Permit
17010-10000-03985
Plan Check / Job No.
B17LA18684
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
PROPOSED 3 STORY 50 UNIT AFFORDABLE HOUSING OVER 1 STORY PARKING GARAGE AND RETAIL/RECORDING STUDIO (CORE&SHELL ONLY) PER DIR-2018-5601-TOC. 6 VERY LOW INCOME AND 43 LOW INCOME UNITS.
Permit Issued
Issued on 7/23/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2017 APPLICANT
Assigned to Plan Check Engineer 10/26/2017 ARMEN JIVALAGIAN
Disabled Access Plans Picked Up 10/31/2017 APPLICANT
Corrections Issued 11/7/2017 ARMEN JIVALAGIAN
Quality Review Completed 11/13/2017 SIAVOSH POURSABAHIAN
Building Plans Picked Up 11/16/2017 APPLICANT
Applicant returned to address corrections 2/22/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 2/28/2018 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/19/2019 ARMEN JIVALAGIAN
Applicant returned to address corrections 5/2/2019 ARMEN JIVALAGIAN
Plan Check Approved 7/19/2019 ARMEN JIVALAGIAN
Issued 7/23/2019 LADBS
TCO Issued (Expire Date: 09-18-2021) 3/22/2021 ERNESTO CORRAL
TCO Issued (Expire Date: 03-19-2022) 9/20/2021 DAVID TSAU
CofO in Progress 12/8/2021 JAMES POWERS
Permit Finaled 12/30/2021 ERNESTO CORRAL
CofO Issued 12/30/2021 ERNESTO CORRAL
Permit Finaled 12/30/2021 ERNESTO CORRAL

Permit Application Clearance Information

Comm Cor/Mini-Mall Cleared 12/5/2017 NORALI MARTINEZ
Comm Cor/Mini-Mall Cleared 12/5/2017 NORALI MARTINEZ
ZA Case Cleared 12/5/2017 NORALI MARTINEZ
ZA Case Cleared 12/5/2017 NORALI MARTINEZ
Address approval Cleared 12/12/2017 KENNETH PHAM
Bicycle Parking Cleared 12/14/2017 FATIMA GUERRA
Eng Process Fee Ord 176,300 Cleared 12/14/2017 JAMES MORALEZ
Encroachment in public way Cleared 12/20/2017 JAMES KHO
Building over 3-story or 36-ft Cleared 1/24/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/24/2018 CALOSHA APPROVED
Hydrant and Access approval Cleared 2/23/2018 JOHN CONNEALLY
Green Code Cleared 3/2/2018 DONALD CRICHLOW
Disturb/Remove Protected Trees Cleared 3/23/2018 LUIS TORRES
Construction near power lines Cleared 8/24/2018 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 5/8/2019 ERIK BEASLEY
Community Plan Implem. Overlay Cleared 5/8/2019 WALTER RAMIREZ
Construction within easement Cleared 5/8/2019 WALTER RAMIREZ
Community Plan Implem. Overlay Cleared 5/9/2019 MOHAMMAD HASAN
Fire Marshall Fire Life Safety Cleared 5/13/2019 ANDREW KO
Community Plan Implem. Overlay Cleared 5/15/2019 JOHN KIM
Trees in Parkway Cleared 5/15/2019 JOHN KIM
DAS Clearance Cleared 5/16/2019 ARMEN JIVALAGIAN
Project located in CRA area Cleared 6/7/2019 JIM URQUHART
Low Impact Development Cleared 6/13/2019 ORVAL HERNANDEZ-MARCI
Certificate of Compliance Cleared 6/18/2019 MARC WOERSCHING
Miscellaneous Cleared 6/18/2019 MARC WOERSCHING
Roof/Waste drainage to street Cleared 6/21/2019 ELAINE LEI
DCP conditions approval Cleared 6/24/2019 LOUIE MILLER
Density Bonus 12.22.A.31 Cleared 6/24/2019 LOUIE MILLER
Miscellaneous Cleared 6/26/2019 JOE LUCKEY
Site Plan review Cleared 6/26/2019 JOE LUCKEY
ZI Cleared 6/26/2019 JOE LUCKEY
Comm Cor/Mini-Mall Cleared 6/27/2019 KIT AWAKUNI
Miscellaneous Cleared 6/27/2019 DIANA JIMENEZ
Miscellaneous Cleared 6/27/2019 DIANA JIMENEZ
Opn space landscape/Water mgmt Cleared 6/27/2019 DIANA JIMENEZ
Sewer availability Cleared 6/27/2019 JEANIE LAM
Highway dedication Cleared 6/28/2019 VICTOR MENDOZA
Permit Cleared 6/28/2019 VICTOR MENDOZA
Work Adjacent to Public Way Cleared 7/1/2019 BOK GOH

Contact Information

Architect Yanez, Arturo; Lic. No.: C24019 4061 BEVERLY GLEN BL      SHERMAN OAKS, CA 91423
Contractor United Building Company Inc; Lic. No.: 1034972-B 250 N. HARBOR DRIVE   SUITE 311    REDONDO BEACH, CA 90277
Engineer Berliner,, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Nam, Young-Keun; Lic. No.: S4029 17 SANTA EUGENIA      IRVINE, CA 92606

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/18/2019 Not Ready for Inspection JAMES POWERS
Pre-Inspection 9/18/2019 Approved JAMES POWERS
Deputy Reinf. Concrete 9/23/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/24/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/25/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/26/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/27/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/1/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/8/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/8/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/16/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/16/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/21/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/22/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/23/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/6/2019 Partial Approval JAMES POWERS
Reinforced Masonry Frame 11/6/2019 Partial Approval JAMES POWERS
Reinforced Masonry Frame 11/13/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/14/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/15/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/11/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/13/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/13/2019 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/16/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/18/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/19/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/20/2019 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/8/2020 Partial Approval JAMES POWERS
Reinforced Masonry Frame 1/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/15/2020 Partial Approval JAMES POWERS
Reinforced Masonry Frame 1/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/17/2020 Approved JOEY BUCHANAN
Reinforced Masonry Frame 1/23/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 1/28/2020 Partial Approval JAMES POWERS
Reinforced Masonry Frame 1/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/14/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/14/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 2/19/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/20/2020 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 2/21/2020 Not Ready for Inspection JAMES POWERS
Green Building Rough 2/27/2020 Approved JAMES POWERS
Reinforced Concrete Frame 2/27/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 2/27/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 2/28/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 3/27/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 4/14/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/12/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/13/2020 Partial Approval JAMES POWERS
Wood Frame 5/14/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/21/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 5/26/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Partial Approval JAMES POWERS
Insulation 6/3/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 6/12/2020 Partial Approval JAMES POWERS
Insulation 6/12/2020 Partial Approval JAMES POWERS
Insulation 6/17/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/17/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/30/2020 Partial Approval JAMES POWERS
Drywall Nailing 7/9/2020 Partial Approval JAMES POWERS
Insulation 7/9/2020 Partial Approval JAMES POWERS
Drywall Nailing 7/23/2020 Partial Approval JAMES POWERS
Insulation 7/23/2020 Partial Approval JAMES POWERS
Drywall Nailing 8/27/2020 Approved JAMES POWERS
Interior/Exterior Lathing 8/27/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/7/2020 Partial Approval JAMES POWERS
T-Bar Ceiling 12/7/2020 Not Ready for Inspection JAMES POWERS
Drywall Nailing 1/26/2021 Approved JAMES POWERS
Final 2/22/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 2/22/2021 Approved JAMES POWERS
Green Building Final 2/22/2021 Approved JAMES POWERS
Reinforced Concrete Frame 2/22/2021 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 2/22/2021 SGSOV Approved JAMES POWERS
Smoke Detectors 2/22/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 2/22/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 2/22/2021 Partial Approval JAMES POWERS
Special/Order Compliance 8/26/2021 Approved JAMES POWERS
Final 12/8/2021 OK to Issue CofO JAMES POWERS
Reinforced Concrete Frame 12/8/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 12/8/2021 Approved JAMES POWERS
Wood Frame 12/8/2021 Approved JAMES POWERS