20135 W CHAPTER DR 91364
Certificate Information: 20135 W CHAPTER DR 91364
- Application / Permit
- 17010-10000-03835
- Plan Check / Job No.
- B17LA18145
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH BASEMENT AND 3-CAR GARAGE
- Permit Issued
- Issued on 1/3/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2017 | SINA KHOSRAVI |
| Corrections Issued | 10/19/2017 | SINA KHOSRAVI |
| Building Plans Picked Up | 10/31/2017 | APPLICANT |
| Green Plans Picked Up | 10/31/2017 | APPLICANT |
| Quality Review Completed | 11/13/2017 | BILL STUTSMAN |
| Applicant returned to address corrections | 5/1/2018 | SINA KHOSRAVI |
| Applicant returned to address corrections | 5/22/2018 | SINA KHOSRAVI |
| Applicant returned to address corrections | 7/31/2018 | SINA KHOSRAVI |
| Plan Check Approved | 8/28/2018 | SINA KHOSRAVI |
| Issued | 1/3/2019 | LADBS |
| CofO in Progress | 11/30/2023 | JOHN KIDWELL |
| CofO Issued | 12/5/2023 | JOHN JANSON |
| Permit Finaled | 12/5/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2017 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 11/20/2017 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 11/20/2017 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 11/20/2017 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2017 | LEE GUILBEAUX |
| Permit | Cleared | 11/20/2017 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/20/2017 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 3/12/2018 | RINA LARA |
| Specific Plan | Cleared | 3/12/2018 | RINA LARA |
| Low Impact Development | Cleared | 7/30/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/30/2018 | MICHAEL CASTILLO |
| Green Code | Cleared | 8/24/2018 | DONALD CRICHLOW |
Contact Information
| Architect | Wickersham, Brian; Lic. No.: C32742 | 6142 BUENA VISTA TERRACE LOS ANGELES, CA 90042 |
| Contractor | Bluestone Construction Corp; Lic. No.: 952370-B | 6520 PLATT AVENUE #805 WEST HILLS, CA 91307 |
| Engineer | Kazarians, Ardashes; Lic. No.: C36687 | 1528 CANADA BLVD STE 206 GLENDALE, CA 91208 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/15/2019 | Partial Inspection | JOSEPH SAGEN |
| Pre-Inspection | 11/12/2019 | Not Ready for Inspection | JOHN JANSON |
| Excavation/Setback/Form/Re-Bar | 12/21/2019 | Partial Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 1/31/2020 | Partial Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 2/6/2020 | Partial Approval | HENRY KIM |
| Deputy Reinf. Masonry | 2/18/2020 | Conditional Approval | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 2/24/2020 | Partial Approval | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 2/28/2020 | Partial Approval | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 5/4/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 5/4/2020 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 5/6/2020 | Partial Approval | RONALD COWAN |
| Underground Mechanical | 5/6/2020 | Partial Approval | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 5/14/2020 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 5/14/2020 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 5/21/2020 | Conditional Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 6/11/2020 | Partial Approval | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 6/19/2020 | Approved | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 7/20/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Not Ready for Inspection | PAUL CHOPP |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2020 | Partial Approval | PAUL CHOPP |
| PLUMBING-Rough | 8/6/2020 | Corrections Issued | PAUL CHOPP |
| PLUMBING-Rough | 8/18/2020 | Approved | PAUL CHOPP |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2020 | Partial Approval | PAUL CHOPP |
| HVAC-Rough | 9/28/2020 | Corrections Issued | DAVID SANDOVAL |
| Interior/Exterior Lathing | 10/7/2020 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 10/14/2020 | Approved | PAUL CHOPP |
| HVAC-Rough | 10/16/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 10/23/2020 | Conditional Approval | MICHAEL TEMPLE |
| Drywall Nailing | 10/23/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 10/23/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Final | 10/23/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Rough | 10/23/2020 | Corrections Issued | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 10/23/2020 | SGSOV Not Ready | MICHAEL TEMPLE |
| Service/Power Release | 10/23/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Shower Pan | 10/23/2020 | Approved | MICHAEL TEMPLE |
| Smoke Detectors | 10/23/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Verify Sprinkler Sign Off | 10/23/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Insulation | 11/2/2020 | Approved | STEVEN BACK |
| Sewer | 11/6/2020 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 11/14/2020 | Approved | STEVEN BACK |
| Green Building Rough | 11/14/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/10/2020 | Approved | DONALD SUNSERI |
| Gas Test | 3/16/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 3/25/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Final | 7/7/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Final | 7/7/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 7/7/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 11/3/2022 | Corrections Issued | PETER FOLLING |
| PLUMBING-Final | 11/3/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 1/17/2023 | Approved | PETER FOLLING |
| Sewer | 1/17/2023 | Approved | PETER FOLLING |
| Service/Power Release | 3/2/2023 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 5/2/2023 | Approved | PETER FOLLING |
| Final | 5/2/2023 | Corrections Issued | PETER FOLLING |
| Green Building Final | 5/2/2023 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Approved | PETER FOLLING |
| Smoke Detectors | 5/2/2023 | Approved | PETER FOLLING |
| Verify Sprinkler Sign Off | 5/2/2023 | Approved | PETER FOLLING |
| Final | 11/27/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 11/30/2023 | OK to Issue CofO | JOHN KIDWELL |