3019 W WINDSOR AVE 90039
Certificate Information: 3019 W WINDSOR AVE 90039
- Application / Permit
- 17010-10000-03795
- Plan Check / Job No.
- B17LA17937
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW DETACHED 2-CAR GARAGE
- Permit Issued
- Issued on 6/11/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2017 | AUNG SOE |
| Green Plans Picked Up | 10/27/2017 | APPLICANT |
| Corrections Issued | 10/30/2017 | AUNG SOE |
| Quality Review Completed | 10/31/2017 | WING SUEN |
| Building Plans Picked Up | 11/1/2017 | APPLICANT |
| Applicant returned to address corrections | 12/27/2017 | AUNG SOE |
| Applicant returned to address corrections | 3/9/2018 | AUNG SOE |
| Applicant returned to address corrections | 3/19/2018 | AUNG SOE |
| Applicant returned to address corrections | 4/24/2018 | AUNG SOE |
| Plan Check Approved | 5/30/2018 | AUNG SOE |
| Issued | 6/11/2018 | LADBS |
| CofO in Progress | 8/25/2022 | THOMAS LOGRASSO |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| CofO Issued | 9/16/2022 | DEROLD HAUFF |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/18/2017 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 12/18/2017 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 12/18/2017 | RAVIL MANAPOV |
| Encroachment in public way | Cleared | 12/18/2017 | JACOB BIGLER |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2017 | RAVIL MANAPOV |
| Permit | Cleared | 12/18/2017 | RAVIL MANAPOV |
| ZA Case | Cleared | 12/18/2017 | IVORY CHAMBESHI |
| ZA Case | Cleared | 12/18/2017 | IVORY CHAMBESHI |
| Low Impact Development | Cleared | 1/31/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/31/2018 | CELINA MORENO |
| Green Code | Cleared | 3/8/2018 | NEGAR NEJAD |
| GPI Written Notices | Cleared | 3/19/2018 | AUNG SOE |
| Grading Pre-Inspection | Cleared | 3/19/2018 | AUNG SOE |
Contact Information
| Architect | Wickersham, Brian; Lic. No.: C32742 | 6142 BUENA VISTA TERRACE LOS ANGELES, CA 90042 |
| Contractor | J H K Contractors Inc; Lic. No.: 835178-B | 3216-A SANTA MONICA BLVD SANTA MONICA, CA 90404 |
| Engineer | Melnyk, Matthew John; Lic. No.: S5853 | 2100 N MAIN STREET, SUITE A1 LOS ANGELES, CA 90031 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 8/27/2019 | No Access for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 10/10/2019 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 10/24/2019 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 10/24/2019 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 10/28/2019 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 11/19/2019 | Partial Approval | AJA COLLAY |
| Footing/Foundation/Slab | 2/11/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 2/18/2020 | Partial Approval | AJA COLLAY |
| Excavation/Setback/Form/Re-Bar | 4/29/2020 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/1/2020 | Partial Approval | ROBERT VORHIS |
| BUILDING-Rough-Frame | 6/29/2022 | Approved | THOMAS LOGRASSO |
| Final | 6/29/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/29/2022 | Approved | THOMAS LOGRASSO |
| Green Building Final | 6/29/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 6/29/2022 | Approved | THOMAS LOGRASSO |
| Reinforced Concrete Frame | 6/29/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 6/29/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 6/29/2022 | Approved | THOMAS LOGRASSO |
| Final | 8/3/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 8/3/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/24/2022 | OK to Issue CofO | THOMAS LOGRASSO |