1406 W EAGLE VISTA DR 90041

Certificate Information: 1406 W EAGLE VISTA DR 90041

Application / Permit
17010-10000-03749
Plan Check / Job No.
B17LA17694
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD w/ ATT. GARAGE - 3 STORY W/ROOF DECK UNDER SMALL LOT SUBDIVISION PER AA 2013-3578 PMLA-SL
Permit Issued
Issued on 3/28/2019
Issuing Office
Metro
Current Status
CofO Issued on 6/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2017 APPLICANT
Assigned to Plan Check Engineer 10/19/2017 SAM CHANG
Corrections Issued 10/25/2017 SAM CHANG
Quality Review Completed 11/3/2017 JOHN VASQUEZ
Building Plans Picked Up 11/6/2017 APPLICANT
Green Plans Picked Up 1/16/2018 APPLICANT
Applicant returned to address corrections 5/22/2018 SAM CHANG
Plan Check Approved 2/26/2019 SAM CHANG
Issued 3/28/2019 LADBS
CofO in Progress 6/17/2022 SCOTT FINNILA
Permit Finaled 6/18/2022 DEROLD HAUFF
CofO Issued 6/18/2022 DEROLD HAUFF
Permit Finaled 6/18/2022 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 5/22/2018 KAREN LE
Low Impact Development Cleared 9/20/2018 RYAN HUDSON
Address approval Cleared 10/11/2018 KARAN PATEL
Eng Process Fee Ord 176,300 Cleared 10/11/2018 KARAN PATEL
Roof/Waste drainage to street Cleared 10/11/2018 KARAN PATEL
Sewer availability Cleared 10/11/2018 KARAN PATEL
ZA Case Cleared 10/11/2018 HELENE ROTOLO
Miscellaneous Cleared 10/16/2018 ZEMAMU GEBREWOLD
Green Code Cleared 10/19/2018 RICHARD DOCKUS
Highway dedication Cleared 1/16/2019 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 1/29/2019 GILBERT URREA
Miscellaneous Cleared 2/19/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 2/19/2019 SOPHIE GABEL-SCHEINBAU
Building over 3-story or 36-ft Cleared 2/26/2019 CALOSHA APPROVED
GPI Written Notices Cleared 2/26/2019 SAM CHANG
Grading Pre-Inspection Cleared 2/26/2019 SAM CHANG

Contact Information

Architect Kivotos, Juan M; Lic. No.: C26491 1323 N NIAGARA STREET      BURBANK, CA 91505
Contractor Owner-Builder       ,
Engineer Walter, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401
Engineer Yogurtian, Arpinee; Lic. No.: C49916 2529 FOOTHILL BLVD, STE 208      LA CRESCENTA, CA 91214

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/29/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
Pre-Inspection 12/31/2019 Partial Inspection SCOTT FINNILA
Footing/Foundation/Slab 1/10/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Masonry 1/24/2020 No Access for Inspection MICHAEL FAUNCE
Masonry Wall/Backfill 1/24/2020 No Access for Inspection MICHAEL FAUNCE
Masonry Wall/Backfill 1/27/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Masonry 1/29/2020 Partial Approval SCOTT FINNILA
Masonry Wall/Backfill 2/11/2020 Corrections Issued SCOTT FINNILA
Masonry Wall/Backfill 2/14/2020 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 3/5/2020 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 3/5/2020 Corrections Issued SCOTT FINNILA
Deck 3/10/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 3/10/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 4/2/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Partial Inspection SCOTT FINNILA
Drywall Nailing 4/21/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 5/4/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Partial Approval SCOTT FINNILA
Deputy Wood Construction 5/15/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Partial Approval ENRIQUE MIRELES
Interior/Exterior Lathing 5/18/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 5/21/2020 Approved SCOTT FINNILA
HVAC-Rough 6/4/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 6/4/2020 Approved SCOTT FINNILA
BUILDING-Rough-Frame 6/11/2020 Approved SCOTT FINNILA
Green Building Rough 6/11/2020 Approved SCOTT FINNILA
HVAC-Rough 6/11/2020 Approved SCOTT FINNILA
MERV13>=Rough 6/11/2020 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 6/11/2020 Approved SCOTT FINNILA
Underground Mechanical 6/12/2020 Partial Inspection SCOTT FINNILA
Insulation 6/17/2020 Approved SCOTT FINNILA
Shower Pan 6/17/2020 Approved SCOTT FINNILA
Shower Pan 6/18/2020 Approved SCOTT FINNILA
Footing/Foundation/Slab 6/23/2020 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 6/25/2020 Approved SCOTT FINNILA
Interior/Exterior Lathing 6/25/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 6/25/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 7/1/2020 Approved SCOTT FINNILA
Interior/Exterior Lathing 7/1/2020 Approved SCOTT FINNILA
Underground Mechanical 10/14/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 12/16/2020 Corrections Issued SCOTT FINNILA
HVAC-Final 12/16/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Final 12/16/2020 Corrections Issued SCOTT FINNILA
Final 3/1/2022 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 3/1/2022 Approved SCOTT FINNILA
Green Building Final 3/1/2022 Corrections Issued SCOTT FINNILA
MERV13>=Final 3/1/2022 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 3/1/2022 Corrections Issued SCOTT FINNILA
Smoke Detectors 3/1/2022 Corrections Issued SCOTT FINNILA
Final 3/17/2022 Not Ready for Inspection SCOTT FINNILA
Gas Test 3/17/2022 Approved SCOTT FINNILA
Green Building Final 3/17/2022 Approved SCOTT FINNILA
MERV13>=Final 3/17/2022 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 3/17/2022 Not Ready for Inspection SCOTT FINNILA
Smoke Detectors 3/17/2022 Approved SCOTT FINNILA
ELECTRICAL-Final 3/24/2022 Approved SCOTT FINNILA
HVAC-Final 3/24/2022 Approved SCOTT FINNILA
Final 4/29/2022 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 4/29/2022 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 4/29/2022 Approved SCOTT FINNILA
Final 5/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/5/2022 SGSOV Not Ready ALEJANDRO DE ARTOLA
PLUMBING-Final 5/6/2022 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Final 6/17/2022 OK to Issue CofO SCOTT FINNILA