5083 N HIGHLAND VIEW AVE 90041

Certificate Information: 5083 N HIGHLAND VIEW AVE 90041

Application / Permit
17010-10000-03731
Plan Check / Job No.
B17LA15111
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3 story single family dwelling with attached 2-car garage LOT 6 : Small lot subdivision pursuant to VTT-74301-SL. A certificate of occupancy (temporary or final) shall not be issued until the final map has been recorded.
Permit Issued
Issued on 6/15/2018
Issuing Office
Metro
Current Status
CofO Issued on 4/7/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2017 APPLICANT
Assigned to Plan Check Engineer 9/14/2017 KESETE HAREGOT
Green Plans Picked Up 9/14/2017 APPLICANT
Disabled Access Plans Picked Up 9/20/2017 APPLICANT
Corrections Issued 9/28/2017 KESETE HAREGOT
Quality Review Completed 10/5/2017 JOHN VASQUEZ
Building Plans Picked Up 10/6/2017 APPLICANT
Applicant returned to address corrections 1/17/2018 KESETE HAREGOT
Plan Check Approved 6/14/2018 KESETE HAREGOT
Issued 6/15/2018 LADBS
CofO in Progress 4/6/2020 SCOTT FINNILA
Permit Finaled 4/7/2020 DEROLD HAUFF
CofO Issued 4/7/2020 DEROLD HAUFF
Permit Finaled 4/7/2020 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 11/27/2017 WILLIAM ROSE
Hydrant and Access approval Cleared 12/5/2017 JOHN CONNEALLY
Address approval Cleared 1/10/2018 ROCHELLE DUNGCA
Eng Process Fee Ord 176,300 Cleared 1/10/2018 ROCHELLE DUNGCA
DAS Clearance Cleared 1/17/2018 ELIZABETH TOMS
Grading Pre-Inspection Cleared 1/26/2018 PATRICK MISCHLICH
Sewer availability Cleared 4/2/2018 MICHAEL CASTILLO
Tract Map conditions Cleared 4/4/2018 EDBER MACEDO
GPI Written Notices Cleared 4/27/2018 KESETE HAREGOT
Low Impact Development Cleared 5/4/2018 SAM NAVID
Miscellaneous Cleared 6/4/2018 LINDA MARGARET
Permit Cleared 6/4/2018 LINDA MARGARET
Roof/Waste drainage to street Cleared 6/4/2018 LINDA MARGARET

Contact Information

Architect Southern, John Iii; Lic. No.: C31796 817 SILVER LAKE BLVD      LOS ANGELES, CA 90026
Contractor Owner-Builder       ,
Engineer Barajas, Jorge Luis; Lic. No.: L8399 3635 SHADOW GROVE RD      PASADENA, CA 91107
Engineer Houshmand, Mohsen; Lic. No.: C42283 4143 COSTERO RISCO      SAN CLEMENTE, CA 92673
Engineer Minas, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/20/2018 Not Ready for Inspection SCOTT FINNILA
Footing/Foundation/Slab 8/20/2018 Not Ready for Inspection SCOTT FINNILA
Underground Mechanical 8/20/2018 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 8/23/2018 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 8/28/2018 Not Ready for Inspection SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 8/29/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 9/14/2018 Not Ready for Inspection SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 9/18/2018 Not Ready for Inspection SCOTT FINNILA
Footing/Foundation/Slab 9/19/2018 Conditional Approval SCOTT FINNILA
Structural Steel Frame 9/19/2018 Partial Approval SCOTT FINNILA
Structural Steel Frame 9/24/2018 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/3/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 10/5/2018 Not Ready for Inspection SCOTT FINNILA
Green Building Rough 10/5/2018 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 10/9/2018 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 10/10/2018 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/10/2018 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 10/26/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/26/2018 Partial Approval SCOTT FINNILA
Green Building Rough 10/26/2018 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 10/29/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/2/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/20/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 11/26/2018 Partial Approval SCOTT FINNILA
Green Building Rough 11/26/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/4/2019 Partial Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 1/28/2019 Not Ready for Inspection SCOTT FINNILA
Gas Test 2/21/2019 Partial Approval SCOTT FINNILA
HVAC-Rough 2/25/2019 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 3/6/2019 Not Ready for Inspection SCOTT FINNILA
HVAC-Rough 5/24/2019 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/5/2019 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 6/12/2019 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Rough 6/12/2019 Approved SCOTT FINNILA
Green Building Rough 6/12/2019 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 6/12/2019 Approved SCOTT FINNILA
ELECTRICAL-Rough 6/13/2019 Not Ready for Inspection MICHAEL FAUNCE
Wood Frame 6/13/2019 Not Ready for Inspection MICHAEL FAUNCE
ELECTRICAL-Rough 6/21/2019 Partial Approval SCOTT FINNILA
Wood Frame 6/21/2019 Corrections Issued SCOTT FINNILA
Shower Pan 6/27/2019 Approved SCOTT FINNILA
Wood Frame 6/27/2019 Approved SCOTT FINNILA
ELECTRICAL-Rough 7/1/2019 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 7/3/2019 Approved SCOTT FINNILA
Insulation 7/3/2019 Partial Inspection SCOTT FINNILA
Rough-Elec/Plmb/HVAC 7/3/2019 Approved SCOTT FINNILA
Drywall Nailing 7/18/2019 Approved SCOTT FINNILA
Interior/Exterior Lathing 7/18/2019 Approved SCOTT FINNILA
Interior/Exterior Lathing 8/5/2019 Partial Approval SCOTT FINNILA
Final 1/28/2020 Partial Inspection SCOTT FINNILA
Footing/Foundation/Slab 1/28/2020 Approved SCOTT FINNILA
Green Building Final 1/28/2020 Not Ready for Inspection SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 1/28/2020 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 1/28/2020 Corrections Issued SCOTT FINNILA
Smoke Detectors 1/28/2020 Approved SCOTT FINNILA
Final 3/18/2020 Partial Inspection SCOTT FINNILA
Green Building Final 3/18/2020 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/18/2020 SGSOV Approved SCOTT FINNILA
Service/Power Release 3/18/2020 Partial Inspection SCOTT FINNILA
Final 4/2/2020 Partial Inspection SCOTT FINNILA
HVAC-Final 4/2/2020 Approved SCOTT FINNILA
Service/Power Release 4/2/2020 Approved SCOTT FINNILA
ELECTRICAL-Final 4/6/2020 Approved SCOTT FINNILA
Final 4/6/2020 OK to Issue CofO SCOTT FINNILA
PLUMBING-Final 4/6/2020 Approved SCOTT FINNILA