938 N OBAN DR 90065
Certificate Information: 938 N OBAN DR 90065
- Application / Permit
- 17010-10000-03593
- Plan Check / Job No.
- B17LA16836
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY SFD OVER SUBTERRANEAN GARAGE.
- Permit Issued
- Issued on 11/19/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2017 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 10/16/2017 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 10/20/2017 | LARRY LEE |
| Green Plans Picked Up | 10/20/2017 | APPLICANT |
| Building Plans Picked Up | 11/13/2017 | APPLICANT |
| Plan Check Approved | 11/19/2018 | VLADIMIR ARUTYUNYAN |
| Issued | 11/19/2018 | LADBS |
| CofO in Progress | 11/19/2024 | THOMAS LOGRASSO |
| Permit Finaled | 11/22/2024 | DEROLD HAUFF |
| CofO Issued | 11/22/2024 | DEROLD HAUFF |
| Permit Finaled | 11/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/28/2017 | JOSEPH RHYU |
| BHO/Hillside ordinance | Cleared | 12/28/2017 | JOSEPH RHYU |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2017 | JOSEPH RHYU |
| Hydrant and Access approval | Cleared | 12/28/2017 | JOHN DALLAS |
| Permit | Cleared | 12/28/2017 | JOSEPH RHYU |
| Sewer availability | Cleared | 12/28/2017 | JOSEPH RHYU |
| BHO/Hillside ordinance | Cleared | 2/6/2018 | NAZILA NOORIFAR |
| Construction near power lines | Cleared | 2/23/2018 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/24/2018 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/24/2018 | MICHAEL CASTILLO |
| Green Code | Cleared | 10/24/2018 | RICHARD DOCKUS |
| Specific Plan | Cleared | 11/15/2018 | LATANYA ROUX |
Contact Information
| Contractor | Avo'S Construction; Lic. No.: 933286-C-5 | 508 NORTH VERDUGO ROAD GLENDALE, CA 91206 |
| Engineer | Abrahamian, Zaven; Lic. No.: C41672 | 237 S LAMER ST BURBANK, CA 91506 |
| Engineer | Judd, Shane Dennis; Lic. No.: C70991 | 1341 CALLE PIMIENTO THOUSAND OAKS, CA 91360 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/12/2019 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 6/14/2019 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/18/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Pre-Inspection | 9/4/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/6/2020 | Corrections Issued | RUBEN SALAS |
| Footing/Foundation/Slab | 1/9/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 1/13/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/13/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 3/4/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/20/2020 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 6/23/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 6/23/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/21/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 7/21/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/18/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/18/2020 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 8/19/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/9/2020 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 9/9/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/28/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 9/28/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/28/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 10/6/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Methane Barrier | 11/9/2020 | No Access for Inspection | ELMER BLAND |
| Pre-Inspection | 11/10/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Special/Order Compliance | 8/2/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Special/Order Compliance | 8/6/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 11/5/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/12/2024 | Approved | THOMAS LOGRASSO |
| Final | 11/12/2024 | Corrections Issued | THOMAS LOGRASSO |
| Smoke Detectors | 11/12/2024 | Approved | THOMAS LOGRASSO |
| Final | 11/18/2024 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 11/18/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 11/18/2024 | Approved | THOMAS LOGRASSO |