Footing/Foundation/Slab
|
5/24/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
5/24/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
6/12/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
6/19/2019
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
7/5/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
7/5/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
7/5/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/9/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
7/9/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
7/9/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Light Gage Steel Frame
|
7/15/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
7/16/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/24/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
7/24/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
7/24/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Deputy Steel/Welding
|
7/25/2019
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/29/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
8/1/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
8/1/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
8/1/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
8/6/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
8/7/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/13/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
8/13/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
8/13/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/20/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Wood Frame
|
8/22/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
8/26/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
8/26/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
8/26/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/9/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
9/9/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
9/9/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/27/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
10/4/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
10/7/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
10/15/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
10/16/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
10/17/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
10/25/2019
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/28/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
11/21/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
11/27/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/10/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
12/10/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
12/10/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
12/13/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
12/20/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
12/20/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
12/24/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
12/27/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
12/27/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
1/3/2020
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Insulation
|
1/14/2020
|
Approved
|
BRIAN SULLIVAN
|
|
Interior/Exterior Lathing
|
1/17/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
1/23/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
2/5/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Sewer
|
6/24/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
7/20/2020
|
Not Ready for Inspection
|
MATTHEW NUCKOLLS
|
|
Underground Mechanical
|
8/3/2020
|
Conditional Approval
|
SCOTT FINNILA
|
|
Underground Mechanical
|
8/7/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Gas Test
|
8/17/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
8/25/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Gas Test
|
9/1/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
9/1/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Final
|
9/8/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Final
|
9/15/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
9/21/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
11/16/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Final
|
11/16/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Final
|
11/16/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
12/8/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
12/21/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Final
|
12/21/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
12/21/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Green Building Final
|
12/21/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
SGSOV-Seismic Gas S/O Valve
|
12/21/2020
|
SGSOV Approved
|
ALEJANDRO DE ARTOLA
|
|
Smoke Detectors
|
12/21/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Final
|
1/19/2021
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Final
|
1/20/2021
|
OK to Issue CofO
|
ALEJANDRO DE ARTOLA
|