4222 S TERRAZA DR 90008
Certificate Information: 4222 S TERRAZA DR 90008
- Application / Permit
- 17010-10000-03388
- Plan Check / Job No.
- B17LA15912
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story single family dwelling with a full basement. See comments.
- Permit Issued
- Issued on 12/17/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2017 | TU HUA |
| Green Plans Picked Up | 9/27/2017 | APPLICANT |
| Corrections Issued | 9/29/2017 | TU HUA |
| Quality Review Completed | 10/5/2017 | ALLEN MANALANSAN |
| Building Plans Picked Up | 10/12/2017 | APPLICANT |
| Applicant returned to address corrections | 5/23/2018 | TU HUA |
| Applicant returned to address corrections | 8/28/2018 | TU HUA |
| Applicant returned to address corrections | 10/4/2018 | TU HUA |
| Plan Check Approved | 11/20/2018 | TU HUA |
| Issued | 12/17/2018 | LADBS |
| CofO in Progress | 10/18/2023 | ANTHONY EGSON |
| CofO Issued | 11/5/2023 | DEROLD HAUFF |
| Permit Finaled | 11/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2018 | JAMES MORALEZ |
| Low Impact Development | Cleared | 8/7/2018 | SAM NAVID |
| Permit | Cleared | 8/7/2018 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 8/7/2018 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2018 | JAMES MORALEZ |
| Sewer availability | Cleared | 8/16/2018 | JAMES MORALEZ |
| Grading Pre-Inspection | Cleared | 8/17/2018 | PATRICK MISCHLICH |
| Hydrant and Access approval | Cleared | 8/17/2018 | JOHN CONNEALLY |
| Green Code | Cleared | 8/24/2018 | RICHARD DOCKUS |
| Excavation more than 5-ft deep | Cleared | 11/5/2018 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 11/5/2018 | TU HUA |
Contact Information
| Architect | Honles,, Guillermo; Lic. No.: C24928 | 9825 SHADOW ISLAND DRIVE SHADOW HILLS, CA 91040 |
| Contractor | Design Built Inc; Lic. No.: 915920-B | 930 W HYDE PARK BLVD #D INGLEWOOD, CA 90302 |
| Engineer | , ; Lic. No.: C88998 | 7020 LANEWOOD AVE 204 LOS ANGELES, CA 90028 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/16/2019 | Not Ready for Inspection | COREY HUPP |
| METHANE-Barrier | 7/16/2019 | Not Ready for Inspection | COREY HUPP |
| METHANE-Subgrade | 7/16/2019 | Not Ready for Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 8/14/2019 | Partial Inspection | COREY HUPP |
| METHANE-Barrier | 8/14/2019 | Not Ready for Inspection | COREY HUPP |
| METHANE-Subgrade | 8/14/2019 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 8/19/2019 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 8/23/2019 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 8/28/2019 | Partial Approval | COREY HUPP |
| Deputy Shotcrete | 11/15/2019 | Conditional Approval | COREY HUPP |
| Deputy Shotcrete | 11/18/2019 | Conditional Approval | PAUL BECKER |
| Footing/Foundation/Slab | 11/25/2019 | Not Ready for Inspection | COREY HUPP |
| METHANE-Barrier | 11/25/2019 | Not Ready for Inspection | COREY HUPP |
| METHANE-Subgrade | 11/25/2019 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 12/9/2019 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 12/12/2019 | Partial Approval | COREY HUPP |
| METHANE-Barrier | 12/12/2019 | Partial Inspection | COREY HUPP |
| METHANE-Subgrade | 12/12/2019 | Partial Inspection | COREY HUPP |
| METHANE-Barrier | 4/3/2020 | Not Ready for Inspection | COREY HUPP |
| Sewer | 4/3/2020 | Partial Approval | COREY HUPP |
| METHANE-Subgrade | 5/15/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 5/20/2020 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 6/5/2020 | Corrections Issued | SCOTT FINNILA |
| METHANE-Barrier | 6/5/2020 | Partial Inspection | SCOTT FINNILA |
| METHANE-Subgrade | 6/5/2020 | Partial Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/9/2020 | Partial Approval | COREY HUPP |
| Deputy Reinf. Concrete | 6/24/2020 | Order to Comply Issued | COREY HUPP |
| Deputy Methane Barrier | 7/9/2020 | Conditional Approval | COREY HUPP |
| METHANE-Barrier | 7/30/2020 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 11/5/2020 | Conditional Approval | DAVID FEILER |
| METHANE-Barrier | 11/5/2020 | Approved | DAVID FEILER |
| METHANE-Subgrade | 11/5/2020 | Approved | DAVID FEILER |
| Deputy Drilled-In Anchors | 2/9/2021 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2021 | Corrections Issued | DAVID FEILER |
| Deputy Wood Construction | 3/4/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Steel/Welding | 3/8/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Wood Construction | 3/16/2021 | No Access for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2021 | Partial Approval | FREDDIE RIVERA |
| Special/Order Compliance | 7/2/2021 | No Access for Inspection | HORACE FULTZ |
| Special/Order Compliance | 7/2/2021 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Rough | 7/7/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 7/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 7/7/2021 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 7/8/2021 | Corrections Issued | HORACE FULTZ |
| Special/Order Compliance | 7/9/2021 | Corrections Issued | HORACE FULTZ |
| HVAC-Rough | 7/13/2021 | Not Ready for Inspection | DAVID FEILER |
| Verify Sprinkler Sign Off | 7/13/2021 | Not Ready for Inspection | DAVID FEILER |
| Deputy Wood Construction | 7/14/2021 | No Access for Inspection | DAVID FEILER |
| HVAC-Rough | 7/16/2021 | Not Ready for Inspection | HORACE FULTZ |
| Wood Frame | 7/16/2021 | Not Ready for Inspection | HORACE FULTZ |
| Interior/Exterior Lathing | 7/29/2021 | Not Ready for Inspection | DAVID FEILER |
| Pre-Inspection | 7/29/2021 | Partial Inspection | CALEB MEISTER |
| Pre-Inspection | 7/29/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Special/Order Compliance | 7/29/2021 | Corrections Issued | HORACE FULTZ |
| Wood Frame | 7/29/2021 | Partial Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2021 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 8/3/2021 | Corrections Issued | DAVID FEILER |
| Shower Pan | 8/3/2021 | Not Ready for Inspection | DAVID FEILER |
| Special/Order Compliance | 8/3/2021 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | No Access for Inspection | DAVID FEILER |
| Shower Pan | 8/9/2021 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2021 | Conditional Approval | DAVID FEILER |
| Shower Pan | 8/11/2021 | Approved | DAVID FEILER |
| Sewer | 8/16/2021 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 8/23/2021 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 8/23/2021 | Partial Approval | DAVID FEILER |
| Sewer | 8/23/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 8/25/2021 | Approved | DAVID FEILER |
| Green Building Rough | 8/25/2021 | Approved | DAVID FEILER |
| HVAC-Rough | 8/25/2021 | Approved | DAVID FEILER |
| METHANE-Rough | 8/25/2021 | Approved | DAVID FEILER |
| Special/Order Compliance | 8/25/2021 | Partial Approval | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 8/25/2021 | Approved | DAVID FEILER |
| Insulation | 8/31/2021 | Not Ready for Inspection | DAVID FEILER |
| Insulation | 9/9/2021 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 9/9/2021 | Approved | WILLIAM WREN |
| Insulation | 9/15/2021 | Corrections Issued | ALAN MORELOS |
| Insulation | 9/17/2021 | Not Ready for Inspection | JESUS PINEDA |
| Insulation | 9/20/2021 | Approved | JESUS PINEDA |
| Sewer | 9/23/2021 | Not Ready for Inspection | DAVID FEILER |
| Special/Order Compliance | 9/23/2021 | Approved | CALEB MEISTER |
| Drywall Nailing | 9/24/2021 | Partial Approval | CALEB MEISTER |
| Sewer | 9/24/2021 | Corrections Issued | CALEB MEISTER |
| Special/Order Compliance | 9/24/2021 | Approved | CALEB MEISTER |
| Sewer | 9/29/2021 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 9/30/2021 | Approved | CALEB MEISTER |
| Special/Order Compliance | 11/17/2021 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 3/9/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/31/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 3/31/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 5/9/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/1/2022 | Partial Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 8/25/2022 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Final | 1/27/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 2/1/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 2/14/2023 | No Access for Inspection | SABAS ALONSO |
| HVAC-Final | 3/21/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 4/25/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 4/25/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 5/5/2023 | Partial Approval | ANTHONY EGSON |
| HVAC-Final | 5/5/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/26/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 7/27/2023 | Approved | ANTHONY EGSON |
| Final | 8/11/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/11/2023 | Approved | ANTHONY EGSON |
| Green Building Final | 8/11/2023 | Approved | ANTHONY EGSON |
| Reinforced Masonry Frame | 8/11/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 8/11/2023 | Approved | ANTHONY EGSON |
| Structural Steel Frame | 8/11/2023 | Approved | ANTHONY EGSON |
| Special/Order Compliance | 10/5/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 10/17/2023 | Approved | ANTHONY EGSON |
| Final | 10/17/2023 | OK to Issue CofO | ANTHONY EGSON |