1243 N GOWER ST 90038
Certificate Information: 1243 N GOWER ST 90038
- Application / Permit
- 17010-10000-03250
- Plan Check / Job No.
- B17LA15256
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 96' X 36' (4) STORY 5 UNIT APARTMENT BUILDING WITH A ROOFTOP DECK FOR EACH UNIT. NFPA-13 SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 5/7/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2017 | MICHAEL PEREZ |
| Disabled Access Plans Picked Up | 9/22/2017 | APPLICANT |
| Green Plans Picked Up | 9/28/2017 | APPLICANT |
| Corrections Issued | 9/29/2017 | SHUNYU ZHANG |
| Quality Review Completed | 10/10/2017 | MINYE PAK |
| Building Plans Picked Up | 10/11/2017 | APPLICANT |
| Applicant returned to address corrections | 1/4/2018 | SHUNYU ZHANG |
| Applicant returned to address corrections | 4/5/2018 | MICHAEL PEREZ |
| Applicant returned to address corrections | 4/12/2018 | MICHAEL PEREZ |
| Plan Check Approved | 4/20/2018 | MICHAEL PEREZ |
| Issued | 5/7/2018 | LADBS |
| CofO in Progress | 10/6/2021 | DANIEL MC AULIFFE |
| Permit Finaled | 10/6/2021 | TERRY HERR |
| CofO Issued | 10/6/2021 | TERRY HERR |
| Permit Finaled | 10/6/2021 | TERRY HERR |
Permit Application Clearance Information
| ZI | Cleared | 10/18/2017 | BRIDGETTE WOOTEN |
| Address approval | Cleared | 10/19/2017 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2017 | STEVE MELGAR |
| Permit | Cleared | 10/19/2017 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 12/13/2017 | ROBERT DUFF |
| Frnt yard landscape/Water mgmt | Cleared | 12/19/2017 | FIPE LEILUA |
| Green Code | Cleared | 12/28/2017 | JOHN KLARIN |
| Building over 3-story or 36-ft | Cleared | 1/4/2018 | CALOSHA APPROVED |
| DAS Clearance | Cleared | 1/4/2018 | SHINE LIN |
| Excavation more than 5-ft deep | Cleared | 1/4/2018 | CALOSHA APPROVED |
| Project located in CRA area | Cleared | 1/23/2018 | JIM URQUHART |
| Fire Marshall Fire Life Safety | Cleared | 3/9/2018 | VIDAL GARCIA |
| Low Impact Development | Cleared | 3/9/2018 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 4/20/2018 | STEVE MELGAR |
| Sewer availability | Cleared | 4/20/2018 | STEVE MELGAR |
Contact Information
| Architect | Wickersham, Brian; Lic. No.: C32742 | 6142 BUENA VISTA TERRACE LOS ANGELES, CA 90042 |
| Contractor | Calcrete Construction Inc; Lic. No.: 854638-B | 11666 PENDLETON STREET SUN VALLEY, CA 91352 |
| Engineer | Mahn, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Mills, Garrett Ward; Lic. No.: S5271 | 1276 E COLORADO BLVD STE 201 PASADENA, CA 91106 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 8/9/2018 | Conditional Approval | TED RIES |
| Footing/Foundation/Slab | 8/10/2018 | Partial Inspection | TED RIES |
| Deputy Reinf. Concrete | 8/28/2018 | Conditional Approval | TED RIES |
| Footing/Foundation/Slab | 8/28/2018 | Not Ready for Inspection | TED RIES |
| Green Building Rough | 8/29/2018 | Not Ready for Inspection | TED RIES |
| Reinforced Concrete Frame | 8/29/2018 | Partial Approval | TED RIES |
| Verify Sprinkler Sign Off | 8/29/2018 | Not Ready for Inspection | TED RIES |
| Deputy Drilled-In Anchors | 9/6/2018 | Approved | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 9/18/2018 | Conditional Approval | TED RIES |
| Deputy Reinf. Concrete | 9/25/2018 | Approved | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 10/31/2018 | Approved | TED RIES |
| Footing/Foundation/Slab | 10/31/2018 | Partial Approval | TED RIES |
| Deputy Reinf. Concrete | 11/2/2018 | Approved | TED RIES |
| Reinforced Masonry Frame | 11/7/2018 | Partial Approval | TED RIES |
| Deputy Reinf. Masonry | 11/9/2018 | Approved | TED RIES |
| Footing/Foundation/Slab | 5/31/2019 | Partial Approval | TED RIES |
| Deputy Reinf. Concrete | 7/17/2019 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 7/18/2019 | Conditional Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 7/18/2019 | Partial Inspection | DANIEL MC AULIFFE |
| Masonry Wall/Backfill | 7/19/2019 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 7/22/2019 | Partial Inspection | DANIEL MC AULIFFE |
| Green Building Rough | 7/22/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Reinforced Concrete Frame | 7/22/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 7/22/2019 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 7/24/2019 | Approved | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2019 | Partial Approval | DANIEL MC AULIFFE |
| Structural Steel Frame | 9/19/2019 | Partial Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2019 | Partial Approval | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2020 | Approved | EDWIN GREGORYONA |
| Green Building Rough | 4/3/2020 | Partial Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 4/3/2020 | Approved | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2020 | Partial Approval | DANIEL MC AULIFFE |
| Insulation | 5/29/2020 | Partial Approval | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 5/29/2020 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 6/16/2020 | Partial Inspection | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 6/22/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 6/22/2020 | Partial Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 7/6/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 7/23/2020 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 8/17/2020 | Approved | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2020 | Partial Approval | DANIEL MC AULIFFE |
| Drywall Nailing | 9/17/2020 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 9/29/2020 | Partial Approval | DANIEL MC AULIFFE |
| Interior/Exterior Lathing | 9/30/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 10/2/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Drywall Nailing | 10/7/2020 | Partial Approval | DANIEL MC AULIFFE |
| Green Building Rough | 11/17/2020 | Approved | DANIEL MC AULIFFE |
| Wood Frame | 11/17/2020 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Final | 9/2/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 9/2/2021 | Approved | DANIEL MC AULIFFE |
| Green Building Final | 9/2/2021 | Approved | DANIEL MC AULIFFE |
| Reinforced Concrete Frame | 9/2/2021 | Approved | DANIEL MC AULIFFE |
| SGSOV-Seismic Gas S/O Valve | 9/2/2021 | SGSOV Approved | DANIEL MC AULIFFE |
| Smoke Detectors | 9/2/2021 | Approved | DANIEL MC AULIFFE |
| Wood Frame | 9/2/2021 | Approved | DANIEL MC AULIFFE |
| Final | 9/20/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Final | 9/29/2021 | Not Ready for Inspection | DANIEL MC AULIFFE |
| Final | 10/5/2021 | Conditional Approval | DANIEL MC AULIFFE |