656-658 E CALIFORNIA AVE 90291

Certificate Information: 656-658 E CALIFORNIA AVE 90291

Application / Permit
17010-10000-03163
Plan Check / Job No.
B17LA14944
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-story, two family dwelling with 4- car attached garage..
Permit Issued
Issued on 12/18/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2017 APPLICANT
Green Plans Picked Up 8/30/2017 APPLICANT
Assigned to Plan Check Engineer 9/20/2017 KESETE HAREGOT
Corrections Issued 10/2/2017 KESETE HAREGOT
Quality Review Completed 10/16/2017 CHARLES CHANG
Building Plans Picked Up 10/18/2017 APPLICANT
Applicant returned to address corrections 6/21/2018 KESETE HAREGOT
Applicant returned to address corrections 9/28/2018 KESETE HAREGOT
Plan Check Approved 12/13/2018 KESETE HAREGOT
Issued 12/18/2018 LADBS
CofO in Progress 8/31/2021 JOHNNY MIRANDA
CofO in Progress 8/31/2021 JOHNNY MIRANDA
CofO Issued 9/14/2021 DANIEL ORRANTE
Permit Finaled 9/14/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/2/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/2/2018 STEVE MELGAR
Highway dedication Cleared 8/2/2018 STEVE MELGAR
Miscellaneous Cleared 8/2/2018 FIPE LEILUA
Miscellaneous Cleared 8/2/2018 FIPE LEILUA
Permit Cleared 8/2/2018 STEVE MELGAR
Hydrant and Access approval Cleared 8/6/2018 ROBERT DUFF
Green Code Cleared 8/9/2018 KATHRYN BUTTERWORTH
Low Impact Development Cleared 9/13/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 9/13/2018 KARAN PATEL
Miscellaneous Cleared 12/13/2018 IRA BROWN
Sewer availability Cleared 12/13/2018 NAZILA NOORIFAR
Specific Plan Cleared 12/13/2018 IRA BROWN
Tract Map conditions Cleared 12/13/2018 BLAYNE SUTTON-WILLS
ZA Case Cleared 12/13/2018 BLAYNE SUTTON-WILLS
ZA Case Cleared 12/13/2018 BLAYNE SUTTON-WILLS

Contact Information

Contractor Owner-Builder       ,
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Polon,, Gordon Leonard; Lic. No.: C28564 709 19TH STREET      SANTA MONICA, CA 90402

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 1/4/2019 Partial Inspection CRAIG DAVIS
Underground Mechanical 5/17/2019 Corrections Issued KENNETH NAGLE
Underground Mechanical 5/22/2019 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 5/31/2019 Partial Approval DAVID HEINE
Deputy Reinf. Concrete 6/4/2019 Partial Approval DAVID HEINE
Deputy Steel/Welding 7/2/2019 No Access for Inspection CRAIG DAVIS
Underground Mechanical 7/3/2019 Not Ready for Inspection CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 8/6/2019 Partial Approval DAVID HEINE
Deputy Reinf. Concrete 8/13/2019 Approved DAVID HEINE
BUILDING-Rough-Frame 9/3/2019 Partial Approval DAVID HEINE
Green Building Rough 9/3/2019 Not Ready for Inspection DAVID HEINE
METHANE-Rough 9/3/2019 Not Ready for Inspection DAVID HEINE
Verify Sprinkler Sign Off 9/3/2019 Not Ready for Inspection DAVID HEINE
Deputy Steel/Welding 9/13/2019 Conditional Approval CRAIG DAVIS
BUILDING-Rough-Frame 9/19/2019 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 9/19/2019 Partial Approval DAVID HEINE
Green Building Rough 9/19/2019 Not Ready for Inspection DAVID HEINE
METHANE-Rough 9/19/2019 Not Ready for Inspection DAVID HEINE
Verify Sprinkler Sign Off 9/19/2019 Not Ready for Inspection DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 10/3/2019 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 10/22/2019 Partial Approval DAVID HEINE
PLUMBING-Rough 11/26/2019 Approved DAVID HEINE
ELECTRICAL-Rough 12/16/2019 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 12/16/2019 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 12/16/2019 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 1/7/2020 Conditional Approval DAVID HEINE
ELECTRICAL-Rough 3/2/2020 Approved DAVID HEINE
HVAC-Rough 3/2/2020 Approved DAVID HEINE
Interior/Exterior Lathing 3/2/2020 Not Ready for Inspection DAVID HEINE
BUILDING-Rough-Frame 3/9/2020 Approved DAVID HEINE
Green Building Rough 3/9/2020 Approved DAVID HEINE
METHANE-Rough 3/9/2020 Approved DAVID HEINE
Verify Sprinkler Sign Off 3/9/2020 Approved DAVID HEINE
Insulation 3/13/2020 Approved DAVID HEINE
Interior/Exterior Lathing 3/13/2020 Partial Approval DAVID HEINE
Drywall Nailing 3/24/2020 Approved DAVID HEINE
Interior/Exterior Lathing 3/24/2020 Approved DAVID HEINE
Shower Pan 3/24/2020 Approved DAVID HEINE
ELECTRICAL-Final 1/21/2021 Corrections Issued JUAN VALENZUELA
Final 1/21/2021 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 1/21/2021 Approved JUAN VALENZUELA
Green Building Final 1/21/2021 Corrections Issued JUAN VALENZUELA
HVAC-Final 1/21/2021 Corrections Issued JUAN VALENZUELA
METHANE-Barrier 1/21/2021 Approved JUAN VALENZUELA
METHANE-Subgrade 1/21/2021 Approved JUAN VALENZUELA
PLUMBING-Final 1/21/2021 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 1/21/2021 SGSOV Not Ready JUAN VALENZUELA
Service/Power Release 1/21/2021 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 1/21/2021 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 1/28/2021 SGSOV Not Ready JOHNNY MIRANDA
Gas Test 2/1/2021 Approved ANTHONY MCDOWALL
ELECTRICAL-Final 2/3/2021 Approved JOHNNY MIRANDA
HVAC-Final 2/3/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 2/3/2021 Approved JOHNNY MIRANDA
Service/Power Release 2/3/2021 Not Ready for Inspection JOHNNY MIRANDA
Final 2/22/2021 Not Ready for Inspection JOHNNY MIRANDA
Green Building Final 2/22/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Final 2/22/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 2/22/2021 SGSOV Not Ready JOHNNY MIRANDA
Service/Power Release 2/22/2021 Not Ready for Inspection JOHNNY MIRANDA
Smoke Detectors 2/22/2021 Approved JOHNNY MIRANDA
Final 8/16/2021 Conditional Approval WILLIAM MICHALAK
Green Building Final 8/16/2021 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/16/2021 SGSOV Approved WILLIAM MICHALAK
Service/Power Release 8/16/2021 Approved WILLIAM MICHALAK
Final 8/26/2021 Corrections Issued JOHNNY MIRANDA
Final 8/31/2021 OK to Issue CofO JOHNNY MIRANDA