16531 S ESTRELLA AVE 90247

Certificate Information: 16531 S ESTRELLA AVE 90247

Application / Permit
17010-10000-03154
Plan Check / Job No.
B17LA14907
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED TWO-STORY SFD WITH ATTACHED GARAGE AT FRONT OF THE LOT
Permit Issued
Issued on 7/20/2020
Issuing Office
Current Status
CofO Issued on 12/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2017 APPLICANT
Assigned to Plan Check Engineer 8/24/2017 SINA KHOSRAVI
Corrections Issued 9/1/2017 SINA KHOSRAVI
Quality Review Completed 9/7/2017 KESETE HAREGOT
Building Plans Picked Up 10/2/2017 APPLICANT
Green Plans Picked Up 2/4/2019 APPLICANT
Plan Check Approved 6/24/2020 SINA KHOSRAVI
Issued 7/20/2020 APPLICANT
CofO in Progress 12/13/2023 JAMES CHAVEZ
Permit Finaled 12/14/2023 DONALD CRICHLOW
CofO Issued 12/14/2023 DONALD CRICHLOW
Permit Finaled 12/14/2023 DONALD CRICHLOW

Permit Application Clearance Information

Address approval Cleared 2/4/2019 ERIK BEASLEY
Green Code Cleared 9/4/2019 WILLIAM ROSE
Low Impact Development Cleared 9/17/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 9/17/2019 ERIK BEASLEY
Miscellaneous Cleared 12/26/2019 JOE LUCKEY
Eng Process Fee Ord 176,300 Cleared 3/6/2020 PAMELA TENEZA
Sewer availability Cleared 3/6/2020 PAMELA TENEZA
Hydrant and Access approval Cleared 6/18/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Madero, Fidencio Jr; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/3/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 11/3/2022 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 11/9/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 11/9/2022 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 12/27/2022 Approved JAMES CHAVEZ
Deputy Reinf. Concrete 1/13/2023 Approved JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 1/20/2023 Corrections Issued JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 1/23/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Approved JAMES CHAVEZ
Underground Mechanical 2/3/2023 Approved JAMES CHAVEZ
Insulation 2/7/2023 Approved JAMES CHAVEZ
Insulation 2/13/2023 Partial Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 3/10/2023 Conditional Approval JAMES CHAVEZ
ELECTRICAL-Rough 4/27/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 4/27/2023 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 4/27/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Rough 5/8/2023 Approved JAMES CHAVEZ
Rough-Elec/Plmb/HVAC 5/8/2023 Approved JAMES CHAVEZ
Insulation 5/12/2023 No Access for Inspection JAMES CHAVEZ
Drywall Nailing 5/17/2023 Approved JAMES CHAVEZ
Insulation 5/17/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 5/17/2023 Approved JAMES CHAVEZ
ELECTRICAL-Final 6/23/2023 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 11/21/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 11/21/2023 Approved JAMES CHAVEZ
Green Building Final 11/21/2023 Approved JAMES CHAVEZ
MERV13>=Rough 11/21/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Not Ready JAMES CHAVEZ
Verify Sprinkler Sign Off 11/21/2023 Approved JAMES CHAVEZ
Final 12/6/2023 Corrections Issued JAMES CHAVEZ
MERV13>=Final 12/6/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 12/6/2023 SGSOV Not Ready JAMES CHAVEZ
Service/Power Release 12/6/2023 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 12/6/2023 Approved JAMES CHAVEZ
Final 12/12/2023 OK to Issue CofO JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 12/12/2023 SGSOV Approved JAMES CHAVEZ
Service/Power Release 12/12/2023 Approved JAMES CHAVEZ