Underground Mechanical
|
6/7/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
9/3/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
9/5/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Excavation/Setback/Form/Re-Bar
|
9/10/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
9/12/2019
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/20/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/22/2019
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/27/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/4/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
12/6/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
12/6/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Wood Frame
|
12/31/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Deputy Wood Construction
|
1/3/2020
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/13/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/17/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
1/29/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Special/Order Compliance
|
1/29/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
1/30/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/18/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/26/2020
|
Partial Approval
|
SCOTT FINNILA
|
|
Drywall Nailing
|
3/6/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
3/11/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
3/19/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
4/2/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/24/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
4/27/2020
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/1/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
5/5/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/27/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
5/28/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
6/2/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
6/4/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
6/4/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/17/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Insulation
|
6/18/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
6/24/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
6/26/2020
|
Partial Inspection
|
SCOTT FINNILA
|
|
ELECTRICAL-Rough
|
6/30/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
6/30/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/7/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
7/7/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
7/14/2020
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
7/14/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
7/14/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
7/14/2020
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/17/2020
|
Corrections Issued
|
ENRIQUE MIRELES
|
|
Special/Order Compliance
|
7/17/2020
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
ELECTRICAL-Rough
|
7/20/2020
|
Not Ready for Inspection
|
MATTHEW NUCKOLLS
|
|
HVAC-Rough
|
7/20/2020
|
Not Ready for Inspection
|
MATTHEW NUCKOLLS
|
|
ELECTRICAL-Rough
|
7/23/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
7/23/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
7/29/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
7/29/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
7/30/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/30/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
7/31/2020
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
8/6/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
8/6/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
8/7/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/11/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
8/11/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
8/11/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Wood Frame
|
8/11/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
8/13/2020
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/14/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
8/17/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
8/17/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
8/17/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Wood Frame
|
8/20/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
8/21/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
8/21/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
9/15/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
9/15/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Insulation
|
9/15/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
9/18/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
9/18/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
9/18/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
9/18/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
9/18/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
9/18/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
9/21/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
9/24/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Gas Test
|
11/18/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
12/16/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
2/11/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
3/2/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
4/30/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
5/20/2021
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Final
|
5/20/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Final
|
5/21/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Final
|
5/21/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
5/28/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Final
|
5/28/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Final
|
5/28/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Final
|
6/18/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
6/18/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Smoke Detectors
|
6/18/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
8/5/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Final
|
8/5/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
8/5/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Green Building Final
|
8/5/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
SGSOV-Seismic Gas S/O Valve
|
8/5/2021
|
SGSOV Approved
|
ALEJANDRO DE ARTOLA
|
|
Structural Steel Frame
|
8/5/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Final
|
8/19/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Final
|
10/8/2021
|
OK to Issue CofO
|
ALEJANDRO DE ARTOLA
|