5004 W MAPLEWOOD AVE 90004
Certificate Information: 5004 W MAPLEWOOD AVE 90004
- Application / Permit
- 17010-10000-03034
- Plan Check / Job No.
- B17LA14142
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY HOME WITH TWO CAR GARAGE IN LOT 5 (UNIT TPYE B) "Small lot subdivision pursuant to Tentative Tract Map No 64363-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded"
- Permit Issued
- Issued on 1/2/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2017 | XIAOZHE ZHANG |
| Green Plans Picked Up | 8/21/2017 | APPLICANT |
| Corrections Issued | 8/30/2017 | XIAOZHE ZHANG |
| Building Plans Picked Up | 9/13/2017 | APPLICANT |
| Quality Review Completed | 9/18/2017 | BILL STUTSMAN |
| Applicant returned to address corrections | 10/11/2017 | XIAOZHE ZHANG |
| Applicant returned to address corrections | 11/28/2017 | XIAOZHE ZHANG |
| Applicant returned to address corrections | 1/4/2018 | XIAOZHE ZHANG |
| Applicant returned to address corrections | 6/26/2018 | HERNAN ARREOLA |
| Plan Check Approved | 11/2/2018 | HERNAN ARREOLA |
| Issued | 1/2/2019 | LADBS |
| CofO in Progress | 10/6/2021 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 10/16/2021 | DEROLD HAUFF |
| CofO Issued | 10/16/2021 | DEROLD HAUFF |
| Permit Finaled | 10/16/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 12/6/2017 | DONALD CRICHLOW |
| Address approval | Cleared | 1/16/2018 | ALFREDO JARA |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2018 | ALFREDO JARA |
| Low Impact Development | Cleared | 3/19/2018 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 4/5/2018 | GEORGE SUCHAND |
| Highway dedication | Cleared | 8/30/2018 | STEVE MELGAR |
| Miscellaneous | Cleared | 8/30/2018 | SOPHEA EK |
| Permit | Cleared | 8/30/2018 | SOPHEA EK |
| Roof/Waste drainage to street | Cleared | 8/30/2018 | SOPHEA EK |
| Sewer availability | Cleared | 8/30/2018 | STEVE MELGAR |
| Miscellaneous | Cleared | 10/22/2018 | MOTOUMI SASAKI |
| Miscellaneous | Cleared | 10/22/2018 | MOTOUMI SASAKI |
| Tract Map conditions | Cleared | 10/22/2018 | MOTOUMI SASAKI |
| Tract Map conditions | Cleared | 10/22/2018 | MOTOUMI SASAKI |
| ZA Case | Cleared | 10/22/2018 | MOTOUMI SASAKI |
Contact Information
| Contractor | Ketter Construction Inc; Lic. No.: 958623-B | 14541 DELANO STREET VAN NUYS, CA 91411 |
| Engineer | Funk, David Lyle; Lic. No.: S5421 | 619 BERYL ST REDONDO BEACH, CA 90277 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/7/2019 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/3/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/5/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Special/Order Compliance | 9/10/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/12/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/6/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/6/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/31/2019 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 1/9/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Light Gage Steel Frame | 1/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Structural Steel Frame | 1/16/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 1/29/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Special/Order Compliance | 1/29/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/30/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2020 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 3/6/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/11/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/19/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/2/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/27/2020 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/5/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/28/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/2/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/4/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/4/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 6/18/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/24/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/26/2020 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/30/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/30/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/7/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/14/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/14/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 7/14/2020 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/14/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Corrections Issued | ENRIQUE MIRELES |
| Special/Order Compliance | 7/17/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/20/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| HVAC-Rough | 7/20/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| ELECTRICAL-Rough | 7/23/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/23/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/29/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/29/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/31/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/6/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/7/2020 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/11/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/11/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/13/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/13/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/9/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/9/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/16/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/16/2020 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 9/16/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/29/2020 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/29/2020 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 11/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/11/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/31/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/12/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/12/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/30/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/19/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/19/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/21/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/21/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/27/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 5/27/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/28/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/11/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/14/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/14/2021 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/14/2021 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/18/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/4/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Structural Steel Frame | 8/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 10/1/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Final | 10/5/2021 | OK to Issue CofO | ALEJANDRO DE ARTOLA |