5002 1/2 W MAPLEWOOD AVE 90004

Certificate Information: 5002 1/2 W MAPLEWOOD AVE 90004

Application / Permit
17010-10000-03033
Plan Check / Job No.
B17LA14142
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY HOME WITH TWO CAR GARAGE IN LOT 4 (UNIT TPYE B)"Small lot subdivision pursuant to Tentative Tract Map No 64363-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded"
Permit Issued
Issued on 1/2/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2017 APPLICANT
Assigned to Plan Check Engineer 8/17/2017 XIAOZHE ZHANG
Green Plans Picked Up 8/21/2017 APPLICANT
Corrections Issued 8/30/2017 XIAOZHE ZHANG
Building Plans Picked Up 9/13/2017 APPLICANT
Quality Review Completed 9/18/2017 BILL STUTSMAN
Applicant returned to address corrections 10/11/2017 XIAOZHE ZHANG
Applicant returned to address corrections 11/28/2017 XIAOZHE ZHANG
Applicant returned to address corrections 1/4/2018 XIAOZHE ZHANG
Applicant returned to address corrections 6/26/2018 HERNAN ARREOLA
Plan Check Approved 11/2/2018 HERNAN ARREOLA
Issued 1/2/2019 LADBS
CofO in Progress 10/9/2021 ALEJANDRO DE ARTOLA
Permit Finaled 10/23/2021 DEROLD HAUFF
CofO Issued 10/23/2021 DEROLD HAUFF
Permit Finaled 10/23/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 12/6/2017 DONALD CRICHLOW
Address approval Cleared 1/16/2018 ALFREDO JARA
Low Impact Development Cleared 3/19/2018 MITESH PATEL
Hydrant and Access approval Cleared 4/5/2018 GEORGE SUCHAND
Highway dedication Cleared 8/30/2018 STEVE MELGAR
Miscellaneous Cleared 8/30/2018 SOPHEA EK
Permit Cleared 8/30/2018 SOPHEA EK
Roof/Waste drainage to street Cleared 8/30/2018 SOPHEA EK
Sewer availability Cleared 8/30/2018 STEVE MELGAR
Miscellaneous Cleared 10/22/2018 MOTOUMI SASAKI
Tract Map conditions Cleared 10/22/2018 MOTOUMI SASAKI
Tract Map conditions Cleared 10/22/2018 MOTOUMI SASAKI
ZA Case Cleared 10/22/2018 MOTOUMI SASAKI
Work Adjacent to Public Way Cleared 10/31/2018 BOK GOH
Building over 3-story or 36-ft Cleared 11/2/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/2/2018 CALOSHA APPROVED
Eng Process Fee Ord 176,300 Cleared 11/6/2018 CELINA MORENO

Contact Information

Contractor Ketter Construction Inc; Lic. No.: 958623-B 14541 DELANO STREET      VAN NUYS, CA 91411
Engineer Funk, David Lyle; Lic. No.: S5421 619 BERYL ST      REDONDO BEACH, CA 90277

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/7/2019 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/3/2019 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/5/2019 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 9/10/2019 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/20/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/22/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/27/2019 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/4/2019 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/6/2019 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 12/6/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/6/2019 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 1/3/2020 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/13/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/16/2020 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/29/2020 Partial Approval ALEJANDRO DE ARTOLA
Special/Order Compliance 1/29/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/30/2020 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 1/31/2020 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/18/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 3/6/2020 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 3/11/2020 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 3/19/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/2/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/24/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/27/2020 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 4/29/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/1/2020 Conditional Approval ALEJANDRO DE ARTOLA
Drywall Nailing 5/4/2020 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 5/4/2020 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 5/5/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/28/2020 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 6/2/2020 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 6/4/2020 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/4/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval ALEJANDRO DE ARTOLA
Insulation 6/18/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/24/2020 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/26/2020 Partial Inspection SCOTT FINNILA
ELECTRICAL-Rough 6/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 6/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 7/7/2020 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/14/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Green Building Rough 7/14/2020 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 7/14/2020 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 7/14/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 7/17/2020 Not Ready for Inspection ENRIQUE MIRELES
Special/Order Compliance 7/17/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 7/24/2020 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/27/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/28/2020 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/7/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/10/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/11/2020 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 8/11/2020 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/4/2020 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 9/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/17/2020 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/23/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/23/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/23/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/25/2020 Approved ALEJANDRO DE ARTOLA
Green Building Rough 9/25/2020 Approved ALEJANDRO DE ARTOLA
Insulation 9/25/2020 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 9/25/2020 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/29/2020 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/2/2020 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 10/5/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/9/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Gas Test 11/18/2020 Partial Approval ALEJANDRO DE ARTOLA
Special/Order Compliance 12/10/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/22/2021 Partial Approval ALEJANDRO DE ARTOLA
Special/Order Compliance 1/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 1/28/2021 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 1/29/2021 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 2/4/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/9/2021 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/12/2021 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/25/2021 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/1/2021 Approved ALEJANDRO DE ARTOLA
Gas Test 3/3/2021 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/8/2021 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/22/2021 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Final 4/22/2021 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/4/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 5/4/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/11/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/12/2021 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/14/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 6/2/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/2/2021 Approved ALEJANDRO DE ARTOLA
Final 6/11/2021 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 6/18/2021 Approved ALEJANDRO DE ARTOLA
Final 8/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/3/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 8/3/2021 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/3/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/3/2021 Approved ALEJANDRO DE ARTOLA
Structural Steel Frame 8/3/2021 Approved ALEJANDRO DE ARTOLA
Final 8/18/2021 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/30/2021 Partial Approval ALEJANDRO DE ARTOLA
Special/Order Compliance 9/30/2021 Approved ALEJANDRO DE ARTOLA
Final 10/8/2021 OK to Issue CofO ALEJANDRO DE ARTOLA