744 S MARIPOSA AVE 1-31 90005

Certificate Information: 744 S MARIPOSA AVE 1-31 90005

Application / Permit
17010-10000-02605
Plan Check / Job No.
B17LA11733
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 6-STORY OVER 1-STORY BASEMENT GARAGE 32 UNIT APARTMENT; 5-STORY (TYPE IIIA) RESIDENTIAL & 2-STORY (TYPE IA) PARKING BELOW
Permit Issued
Issued on 12/24/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2017 APPLICANT
Assigned to Plan Check Engineer 7/27/2017 PRANITA SHAH
Disabled Access Plans Picked Up 8/1/2017 APPLICANT
Green Plans Picked Up 8/2/2017 APPLICANT
Corrections Issued 8/30/2017 PRANITA SHAH
Quality Review Completed 9/8/2017 MINYE PAK
Building Plans Picked Up 9/11/2017 APPLICANT
Applicant returned to address corrections 4/18/2018 PRANITA SHAH
Applicant returned to address corrections 6/6/2018 PRANITA SHAH
Applicant returned to address corrections 6/13/2018 PRANITA SHAH
Applicant returned to address corrections 6/28/2018 PRANITA SHAH
Applicant returned to address corrections 7/13/2018 PRANITA SHAH
Applicant returned to address corrections 11/29/2018 PRANITA SHAH
Plan Check Approved 12/12/2018 PRANITA SHAH
Issued 12/24/2019 LADBS
TCO Issued (Expire Date: 02-21-2023) 8/25/2022 TED RIES
TCO Issued (Expire Date: 08-15-2023) 2/16/2023 TED RIES
CofO in Progress 4/5/2023 RAFAEL ESPINOZA
Permit Finaled 4/10/2023 ERNESTO CORRAL
CofO Issued 4/10/2023 ERNESTO CORRAL
Permit Finaled 4/10/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 9/15/2017 CARLA VALLADARES
Eng Process Fee Ord 176,300 Cleared 10/31/2017 RAVIL MANAPOV
Highway dedication Cleared 10/31/2017 RAVIL MANAPOV
Sewer availability Cleared 10/31/2017 RAVIL MANAPOV
Permit Cleared 11/21/2017 JAMES MORALEZ
Project located in CRA area Cleared 12/7/2017 JIM URQUHART
Hydrant and Access approval Cleared 3/1/2018 JOHN CONNEALLY
Green Code Cleared 6/13/2018 WILLIAM ROSE
Internal circulation Cleared 7/11/2018 JOHNATHAN YU
Frnt yard landscape/Water mgmt Cleared 7/12/2018 SEAN VEAL
Opn space landscape/Water mgmt Cleared 7/12/2018 SEAN VEAL
Prkng lot landscape/Water mgmt Cleared 7/12/2018 SEAN VEAL
ZA Case Cleared 7/12/2018 SEAN VEAL
Construction within easement Cleared 7/17/2018 RIDWAN HARDY
Low Impact Development Cleared 7/31/2018 MARTIN FRAGOSO
DAS Clearance Cleared 8/1/2018 SHINE LIN
Fire Marshall Fire Life Safety Cleared 8/1/2018 DOMINIQUE MEDINA
Roof/Waste drainage to street Cleared 8/1/2018 ADRIAN SANCHEZ
Building over 3-story or 36-ft Cleared 11/29/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 11/29/2018 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 12/12/2018 BOK GOH

Contact Information

Architect Kim, Steve Chulwon; Lic. No.: C19772 2855 W. 7TH ST. #200      LOS ANGELES, CA 90005
Contractor Ketter Construction Inc; Lic. No.: 958623-B 12650 RIVERSIDE DRIVE #100      STUDIO CITY, CA 91607
Engineer Lee, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 15038 CLARK AVE      HACIENDA HEIGHTS, CA 91745

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/7/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/9/2020 Conditional Approval LESLIE TRUJILLO
Drywall Nailing 1/27/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/18/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 2/20/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 3/3/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/4/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 3/5/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/9/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 3/12/2020 No Access for Inspection LESLIE TRUJILLO
Reinforced Concrete Frame 3/16/2020 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 3/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 3/18/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/19/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/20/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/24/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/25/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/27/2020 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 3/31/2020 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 4/1/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/2/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 5/26/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/11/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/12/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 7/10/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/16/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/21/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/22/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/7/2020 Conditional Approval NICK DANERI
Reinforced Concrete Frame 8/11/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/13/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 8/17/2020 Conditional Approval NICK DANERI
Reinforced Concrete Frame 8/19/2020 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 8/20/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 8/26/2020 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 8/26/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/15/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/30/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 10/1/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/5/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 11/2/2020 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/16/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 1/11/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/10/2021 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 2/17/2021 Conditional Approval NICK DANERI
Insulation 2/19/2021 Partial Approval JAMES POWERS
Insulation 2/23/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/23/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/25/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/4/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/4/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Partial Approval RAFAEL ESPINOZA
Insulation 3/9/2021 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 3/16/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 4/8/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 5/6/2021 Approved RAFAEL ESPINOZA
Wood Frame 5/7/2021 Partial Approval DAVID BURKHEAD
Drywall Nailing 5/18/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 5/18/2021 Partial Approval RAFAEL ESPINOZA
Insulation 5/24/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/28/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/11/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/16/2021 Partial Approval EDWIN GREGORYONA
Final 12/2/2021 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 12/2/2021 Approved RAFAEL ESPINOZA
Green Building Final 12/2/2021 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 12/2/2021 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 12/2/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 12/2/2021 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 12/2/2021 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 12/2/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 12/2/2021 Not Ready for Inspection RAFAEL ESPINOZA
Final 3/1/2022 Corrections Issued RAFAEL ESPINOZA
Green Building Final 3/1/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/1/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 3/1/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 3/1/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/1/2022 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 4/7/2022 Corrections Issued RAFAEL ESPINOZA
Special/Order Compliance 4/8/2022 Corrections Issued RAFAEL ESPINOZA
Final 6/6/2022 Partial Inspection RAFAEL ESPINOZA
Green Building Final 6/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 6/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 6/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 6/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 6/8/2022 Corrections Issued RAFAEL ESPINOZA
Special/Order Compliance 6/28/2022 Partial Inspection RAFAEL ESPINOZA
Final 8/2/2022 Not Ready for Inspection NICK DANERI
Green Building Final 8/2/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/2/2022 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 8/2/2022 Not Ready for Inspection NICK DANERI
Smoke Detectors 8/2/2022 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 8/2/2022 Not Ready for Inspection NICK DANERI
Final 8/12/2022 Partial Inspection RAFAEL ESPINOZA
Green Building Final 8/12/2022 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 8/12/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 8/12/2022 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 8/12/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/12/2022 Approved RAFAEL ESPINOZA
Final 8/24/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 8/24/2022 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 8/24/2022 Approved RAFAEL ESPINOZA
Smoke Detectors 8/24/2022 Approved RAFAEL ESPINOZA
Special/Order Compliance 1/25/2023 Partial Inspection GREGORY POMISH
Final 4/5/2023 OK to Issue CofO RAFAEL ESPINOZA