734 N PARKMAN AVE 90026

Certificate Information: 734 N PARKMAN AVE 90026

Application / Permit
17010-10000-02589
Plan Check / Job No.
B17LA11655
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SMALL LOT SUBDIVISION: (N) 3 STORY SFD W/ROOFTOP DECK PER VTT 74164-SL-1A
Permit Issued
Issued on 5/25/2018
Issuing Office
Metro
Current Status
CofO Issued on 7/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2017 APPLICANT
Assigned to Plan Check Engineer 7/13/2017 QUAN NGHIEM
Green Plans Picked Up 7/18/2017 APPLICANT
Corrections Issued 8/1/2017 QUAN NGHIEM
Quality Review Completed 8/7/2017 BILL STUTSMAN
Building Plans Picked Up 8/8/2017 APPLICANT
Applicant returned to address corrections 8/30/2017 QUAN NGHIEM
Applicant returned to address corrections 9/1/2017 QUAN NGHIEM
Applicant returned to address corrections 9/12/2017 QUAN NGHIEM
Applicant returned to address corrections 2/23/2018 QUAN NGHIEM
Plan Check Approved 5/25/2018 QUAN NGHIEM
Issued 5/25/2018 LADBS
CofO in Progress 6/29/2021 SCOTT FINNILA
No Progress 6/29/2021 SCOTT FINNILA
CofO in Progress 7/2/2021 SCOTT FINNILA
Permit Finaled 7/3/2021 DEROLD HAUFF
CofO Issued 7/3/2021 DEROLD HAUFF
Permit Finaled 7/3/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/18/2017 ROBERT DUFF
Green Code Cleared 9/19/2017 KATHRYN BUTTERWORTH
Address approval Cleared 9/21/2017 FATIMA GUERRA
Eng Process Fee Ord 176,300 Cleared 9/21/2017 FATIMA GUERRA
Sewer availability Cleared 9/21/2017 FATIMA GUERRA
Green Code Cleared 9/27/2017 KATHRYN BUTTERWORTH
Miscellaneous Cleared 9/27/2017 DANALYNN DOMINGUEZ
Tract Map conditions Cleared 9/27/2017 DANALYNN DOMINGUEZ
Low Impact Development Cleared 12/11/2017 SAM NAVID
Grading Pre-Inspection Cleared 4/2/2018 QUAN NGHIEM
Highway dedication Cleared 5/11/2018 KAREN LE
Permit Cleared 5/21/2018 SOPHEA EK
Roof/Waste drainage to street Cleared 5/21/2018 SOPHEA EK

Contact Information

Architect Buckingham, Henry Thomas; Lic. No.: C33094 1009 S OAKLAND AVENUE      PASADENA, CA 91106
Contractor Wjk Development Co; Lic. No.: 1005728-B 16520 BAKE PARKWAY SUITE 105      IRVINE, CA 92618
Engineer Funk, David Lyle; Lic. No.: S5421 619 BERYL ST      REDONDO BEACH, CA 90277

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/23/2019 Corrections Issued SCOTT FINNILA
Underground Mechanical 6/3/2019 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 6/5/2019 Not Ready for Inspection SCOTT FINNILA
METHANE-Barrier 6/5/2019 Not Ready for Inspection SCOTT FINNILA
METHANE-Subgrade 6/5/2019 Not Ready for Inspection SCOTT FINNILA
Footing/Foundation/Slab 6/6/2019 Corrections Issued SCOTT FINNILA
METHANE-Rough 6/6/2019 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 6/7/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
METHANE-Barrier 6/7/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
METHANE-Subgrade 6/7/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/13/2019 Partial Approval SCOTT FINNILA
METHANE-Barrier 6/13/2019 Partial Approval SCOTT FINNILA
METHANE-Subgrade 6/13/2019 Partial Approval SCOTT FINNILA
Deputy Methane Barrier 6/27/2019 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 7/1/2019 Conditional Approval SCOTT FINNILA
METHANE-Barrier 7/1/2019 Conditional Approval SCOTT FINNILA
METHANE-Subgrade 7/1/2019 Conditional Approval SCOTT FINNILA
Footing/Foundation/Slab 7/3/2019 Corrections Issued SCOTT FINNILA
METHANE-Barrier 7/3/2019 Approved SCOTT FINNILA
METHANE-Subgrade 7/3/2019 Approved SCOTT FINNILA
Drywall Nailing 8/5/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/5/2019 Partial Approval SCOTT FINNILA
Green Building Rough 8/5/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/23/2019 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/10/2019 Conditional Approval SCOTT FINNILA
Drywall Nailing 9/13/2019 Partial Approval SCOTT FINNILA
Green Building Rough 9/13/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/15/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 10/16/2019 Partial Approval SCOTT FINNILA
Green Building Rough 10/16/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/16/2019 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/8/2020 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 2/3/2020 Partial Approval ALEJANDRO DE ARTOLA
Pre-Inspection 2/3/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 2/13/2020 Partial Inspection SCOTT FINNILA
Green Building Rough 3/4/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/12/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 3/12/2020 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 4/6/2020 No Access for Inspection SCOTT FINNILA
Green Building Rough 4/6/2020 No Access for Inspection SCOTT FINNILA
Special/Order Compliance 4/6/2020 Corrections Issued SCOTT FINNILA
Verify Sprinkler Sign Off 4/6/2020 No Access for Inspection SCOTT FINNILA
Wood Frame 4/6/2020 No Access for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 4/14/2020 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Conditional Approval SCOTT FINNILA
ELECTRICAL-Rough 4/27/2020 Partial Approval SCOTT FINNILA
HVAC-Rough 4/27/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 4/27/2020 Partial Approval SCOTT FINNILA
Wood Frame 4/27/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 5/8/2020 Corrections Issued SCOTT FINNILA
HVAC-Rough 5/8/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 5/8/2020 Conditional Approval SCOTT FINNILA
Wood Frame 5/8/2020 Corrections Issued SCOTT FINNILA
Deputy Wood Construction 5/12/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 5/13/2020 Partial Inspection SCOTT FINNILA
HVAC-Rough 5/13/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 5/13/2020 Corrections Issued SCOTT FINNILA
Wood Frame 5/13/2020 Approved SCOTT FINNILA
ELECTRICAL-Rough 5/18/2020 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 5/18/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 5/18/2020 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 5/18/2020 Not Ready for Inspection ENRIQUE MIRELES
Insulation 5/19/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/19/2020 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 5/20/2020 Not Ready for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 5/22/2020 Approved SCOTT FINNILA
ELECTRICAL-Rough 5/22/2020 Approved SCOTT FINNILA
Green Building Rough 5/22/2020 Approved SCOTT FINNILA
HVAC-Rough 5/22/2020 Approved SCOTT FINNILA
Insulation 5/22/2020 Conditional Approval SCOTT FINNILA
METHANE-Rough 5/22/2020 Approved SCOTT FINNILA
PLUMBING-Rough 5/22/2020 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 5/22/2020 Approved SCOTT FINNILA
Drywall Nailing 6/5/2020 Corrections Issued SCOTT FINNILA
Drywall Nailing 6/10/2020 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 6/10/2020 Partial Inspection SCOTT FINNILA
Interior/Exterior Lathing 6/15/2020 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 6/23/2020 Approved SCOTT FINNILA
Underground Mechanical 9/8/2020 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 9/11/2020 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 11/5/2020 Partial Approval SCOTT FINNILA
Final 12/28/2020 Partial Inspection SCOTT FINNILA
Service/Power Release 1/25/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 3/25/2021 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 3/25/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 4/12/2021 Approved SCOTT FINNILA
Drywall Nailing 5/12/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 5/12/2021 Partial Approval SCOTT FINNILA
Final 5/12/2021 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 5/12/2021 Approved SCOTT FINNILA
Green Building Final 5/12/2021 Approved SCOTT FINNILA
HVAC-Final 5/12/2021 Approved SCOTT FINNILA
PLUMBING-Final 5/12/2021 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 5/12/2021 SGSOV Approved SCOTT FINNILA
Service/Power Release 5/12/2021 Corrections Issued SCOTT FINNILA
Smoke Detectors 5/12/2021 Partial Approval SCOTT FINNILA
Structural Steel Frame 5/12/2021 Approved SCOTT FINNILA
Green Building Final 5/24/2021 Approved SCOTT FINNILA
HVAC-Final 5/24/2021 Approved SCOTT FINNILA
PLUMBING-Final 5/24/2021 Approved SCOTT FINNILA
Smoke Detectors 5/24/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 5/28/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 6/8/2021 Approved SCOTT FINNILA
Final 6/8/2021 Corrections Issued SCOTT FINNILA
Service/Power Release 6/8/2021 Approved SCOTT FINNILA
Final 6/16/2021 Partial Approval SCOTT FINNILA
Final 6/22/2021 Partial Approval SCOTT FINNILA
Final 6/29/2021 OK to Issue CofO SCOTT FINNILA
Final 6/30/2021 Corrections Issued SCOTT FINNILA
Final 7/2/2021 OK to Issue CofO SCOTT FINNILA