Deputy Reinf. Concrete
|
4/24/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
5/10/2019
|
Partial Approval
|
ROBERT COLE
|
|
SWPPP-Const. Storm Water
|
5/10/2019
|
Completed
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
5/13/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
5/20/2019
|
Partial Inspection
|
ROBERT COLE
|
|
Reinforced Concrete Frame
|
5/20/2019
|
Partial Inspection
|
ROBERT COLE
|
|
SWPPP-Const. Storm Water
|
5/20/2019
|
Completed
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/17/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Drilled-In Anchors
|
6/20/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/5/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/8/2019
|
Partial Inspection
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/10/2019
|
Partial Approval
|
ROBERT COLE
|
|
Deputy Reinf. Concrete
|
8/7/2019
|
Conditional Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/26/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/28/2019
|
Approved
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/12/2019
|
Partial Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/18/2019
|
Partial Inspection
|
ROBERT COLE
|
|
Green Building Rough
|
9/18/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
SWPPP-Const. Storm Water
|
9/18/2019
|
Completed
|
ROBERT COLE
|
|
Verify Sprinkler Sign Off
|
9/18/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Wood Frame
|
9/18/2019
|
Partial Inspection
|
ROBERT COLE
|
|
Green Building Rough
|
10/7/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Light Gage Steel Frame
|
10/7/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
SWPPP-Const. Storm Water
|
10/7/2019
|
Not Required
|
ROBERT COLE
|
|
Verify Sprinkler Sign Off
|
10/7/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Wood Frame
|
10/7/2019
|
Partial Inspection
|
ROBERT COLE
|
|
Green Building Rough
|
10/16/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Verify Sprinkler Sign Off
|
10/16/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Wood Frame
|
10/16/2019
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/24/2019
|
Partial Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/29/2019
|
Partial Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
11/20/2019
|
Partial Approval
|
ROBERT COLE
|
|
Special/Order Compliance
|
1/27/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Special/Order Compliance
|
2/4/2020
|
Conditional Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
2/6/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Drywall Nailing
|
2/10/2020
|
Approved
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/11/2020
|
Partial Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/12/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Insulation
|
2/12/2020
|
Partial Approval
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/14/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Interior/Exterior Lathing
|
2/19/2020
|
Partial Approval
|
ROBERT COLE
|
|
Insulation
|
2/20/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Insulation
|
2/28/2020
|
Partial Approval
|
ROBERT COLE
|
|
Insulation
|
3/4/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Special/Order Compliance
|
3/4/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/6/2020
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
3/9/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Drywall Nailing
|
3/12/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Interior/Exterior Lathing
|
3/12/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Drywall Nailing
|
3/13/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Green Building Rough
|
3/23/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Verify Sprinkler Sign Off
|
3/23/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Wood Frame
|
3/23/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Special/Order Compliance
|
3/24/2020
|
Partial Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
3/27/2020
|
Partial Approval
|
ROBERT COLE
|
|
Insulation
|
3/27/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Drywall Nailing
|
3/31/2020
|
Partial Approval
|
ROBERT COLE
|
|
Wood Frame
|
3/31/2020
|
Partial Approval
|
ROBERT COLE
|
|
Insulation
|
4/2/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
4/7/2020
|
Partial Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
4/8/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Wood Frame
|
4/9/2020
|
Partial Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
4/13/2020
|
Partial Approval
|
ROBERT COLE
|
|
Drywall Nailing
|
4/14/2020
|
Partial Approval
|
JEFFREY DURAN
|
|
Insulation
|
4/17/2020
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
4/21/2020
|
Partial Approval
|
ROBERT COLE
|
|
Insulation
|
4/21/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Drywall Nailing
|
5/5/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Interior/Exterior Lathing
|
5/11/2020
|
Partial Approval
|
ROBERT COLE
|
|
Insulation
|
5/13/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Light Gage Steel Frame
|
5/13/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Interior/Exterior Lathing
|
5/18/2020
|
Partial Approval
|
ROBERT COLE
|
|
Excavation/Setback/Form/Re-Bar
|
6/16/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Pre-Inspection
|
6/19/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Final
|
6/30/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
6/30/2020
|
Approved
|
ROBERT COLE
|
|
Green Building Final
|
6/30/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Green Building Rough
|
6/30/2020
|
Approved
|
ROBERT COLE
|
|
SGSOV-Seismic Gas S/O Valve
|
6/30/2020
|
SGSOV Not Ready
|
ROBERT COLE
|
|
SUSMP-Std. Urban Storm Water
|
6/30/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Smoke Detectors
|
6/30/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Verify Sprinkler Sign Off
|
6/30/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Wood Frame
|
6/30/2020
|
Conditional Approval
|
ROBERT COLE
|
|
Special/Order Compliance
|
7/2/2020
|
Partial Inspection
|
ROBERT COLE
|
|
Drywall Nailing
|
7/7/2020
|
Approved
|
ROBERT COLE
|
|
Final
|
7/7/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Footing/Foundation/Slab
|
7/7/2020
|
Approved
|
ROBERT COLE
|
|
Green Building Final
|
7/7/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Insulation
|
7/7/2020
|
Approved
|
ROBERT COLE
|
|
SGSOV-Seismic Gas S/O Valve
|
7/7/2020
|
SGSOV Not Ready
|
ROBERT COLE
|
|
SUSMP-Std. Urban Storm Water
|
7/7/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Smoke Detectors
|
7/7/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Verify Sprinkler Sign Off
|
7/7/2020
|
Not Ready for Inspection
|
ROBERT COLE
|
|
Wood Frame
|
7/7/2020
|
Partial Approval
|
ROBERT COLE
|
|
Final
|
12/1/2020
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
12/1/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
12/1/2020
|
SGSOV Not Ready
|
DANNY RODRIGUEZ
|
|
SUSMP-Std. Urban Storm Water
|
12/1/2020
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
SWPPP-Const. Storm Water
|
12/1/2020
|
Completed
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
12/1/2020
|
Approved
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
12/1/2020
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
12/1/2020
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
4/1/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
4/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
4/1/2021
|
SGSOV Approved
|
DANNY RODRIGUEZ
|
|
SUSMP-Std. Urban Storm Water
|
4/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
4/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Wood Frame
|
4/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Final
|
6/23/2021
|
OK to Issue CofO
|
DANNY RODRIGUEZ
|