8405 N GLENOAKS BLVD 1-19 91352

Certificate Information: 8405 N GLENOAKS BLVD 1-19 91352

Application / Permit
17010-10000-02356
Plan Check / Job No.
B17LA10696
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY , 19 UNIT APARTMENT BUILDING (3 STORY TYPE V-A APARTMENT BUILDING OVER I STORY TYPE I-A PARKING GARAGE).
Permit Issued
Issued on 12/8/2017
Issuing Office
Metro
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2017 APPLICANT
Assigned to Plan Check Engineer 6/29/2017 GARO TELMI
Disabled Access Plans Picked Up 6/30/2017 APPLICANT
Green Plans Picked Up 7/5/2017 APPLICANT
Corrections Issued 7/10/2017 GARO TELMI
Quality Review Completed 7/14/2017 JOHN FRANCIA
Building Plans Picked Up 7/17/2017 APPLICANT
Applicant returned to address corrections 7/27/2017 GARO TELMI
Applicant returned to address corrections 8/8/2017 GARO TELMI
Applicant returned to address corrections 8/22/2017 GARO TELMI
Applicant returned to address corrections 9/11/2017 GARO TELMI
Applicant returned to address corrections 9/20/2017 GARO TELMI
Applicant returned to address corrections 10/11/2017 GARO TELMI
Plan Check Approved 10/30/2017 GARO TELMI
Issued 12/8/2017 LADBS
CofO in Progress 9/20/2023 DANNY RODRIGUEZ
Permit Finaled 9/25/2023 RICKEY JACKSON
CofO Issued 9/25/2023 RICKEY JACKSON
Permit Finaled 9/25/2023 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 7/17/2017 RAVIL MANAPOV
Driveway location Cleared 7/17/2017 COLLINS ALLAN
Encroachment in public way Cleared 7/17/2017 JACOB BIGLER
Eng Process Fee Ord 176,300 Cleared 7/17/2017 RAVIL MANAPOV
Internal circulation Cleared 7/17/2017 COLLINS ALLAN
Hydrant and Access approval Cleared 7/21/2017 JOHN DALLAS
Green Code Cleared 8/3/2017 JOHN KLARIN
Prkng lot landscape/Water mgmt Cleared 9/7/2017 EDBER MACEDO
Construction near power lines Cleared 9/8/2017 OSCAR CASTRO
Construction within easement Cleared 9/8/2017 OSCAR CASTRO
"Q" conditions Cleared 9/14/2017 SARAH GOLDMAN
Clean Up Green Up Cleared 9/14/2017 SARAH GOLDMAN
Frnt yard landscape/Water mgmt Cleared 9/14/2017 SARAH GOLDMAN
Opn space landscape/Water mgmt Cleared 9/14/2017 SARAH GOLDMAN
DAS Clearance Cleared 9/29/2017 WAI LAU
Building over 3-story or 36-ft Cleared 10/11/2017 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 10/17/2017 VIDAL GARCIA
Highway dedication Cleared 10/20/2017 JAMES KHO
Low Impact Development Cleared 10/20/2017 MARTIN FRAGOSO
Miscellaneous Cleared 10/20/2017 JAMES KHO
Permit Cleared 10/20/2017 JAMES KHO
Roof/Waste drainage to street Cleared 10/20/2017 JAMES KHO
Stormwater Pollution Mitigatn Cleared 10/20/2017 MARTIN FRAGOSO
Work Adjacent to Public Way Cleared 10/20/2017 JAMES KHO
Sewer availability Cleared 10/23/2017 FATIMA GUERRA

Contact Information

Architect Deenihan, John Gilmore; Lic. No.: C9147 5931 OAKDALE AVENUE      WOODLAND HILLS, CA 91367
Contractor Owner-Builder       ,
Engineer Jiang, Clarence Tzu-Wei; Lic. No.: GE2477 PO BOX 1891      WEST COVINA, CA 91793
Engineer Li, Dacheng David; Lic. No.: C58075 23240 RIDGELINE DR      DIAMOND BAR, CA 91765
Engineer Tsalyuk, Yefim; Lic. No.: C52871 11278 LOS ALAMITOS BLVD 354      LOS ALAMITOS, CA 90720

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/16/2018 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 8/17/2018 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 8/23/2018 Order to Comply Issued DANNY RODRIGUEZ
Special/Order Compliance 1/16/2019 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 4/3/2019 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 6/12/2019 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 7/17/2019 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 9/11/2019 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 11/7/2019 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 12/3/2019 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 1/13/2020 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 12/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 1/28/2021 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 2/26/2021 Approved DANNY RODRIGUEZ
Special/Order Compliance 3/12/2021 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 4/28/2021 Approved JOE VELASQUEZ
Deputy Reinf. Concrete 4/29/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/6/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 5/6/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/7/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 5/7/2021 Approved HAMID PISHEHVAR
Green Building Rough 5/7/2021 Partial Approval HAMID PISHEHVAR
Reinforced Concrete Frame 5/7/2021 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 5/7/2021 Not Ready for Inspection HAMID PISHEHVAR
Deputy Reinf. Masonry 5/10/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/11/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/12/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/13/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/14/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/17/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/18/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/19/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/20/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 5/21/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 5/24/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 5/25/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 5/26/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 5/27/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 5/28/2021 Conditional Approval JEFFREY DURAN
Reinforced Masonry Frame 6/1/2021 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/18/2021 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 6/18/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/18/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 6/21/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 6/24/2021 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/28/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 10/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 10/22/2021 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 11/23/2021 Conditional Approval DANNY RODRIGUEZ
Wood Frame 11/24/2021 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 12/8/2021 Approved DANNY RODRIGUEZ
Green Building Rough 12/8/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/8/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/8/2021 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 1/7/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/7/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 2/2/2022 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/3/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 2/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 2/4/2022 Approved DANNY RODRIGUEZ
Green Building Rough 2/18/2022 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 2/18/2022 Not Ready for Inspection JOHN KITCKO
Wood Frame 2/18/2022 Corrections Issued JOHN KITCKO
Green Building Rough 2/28/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/28/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 2/28/2022 Partial Approval DANNY RODRIGUEZ
Insulation 3/3/2022 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 3/9/2022 Approved DANNY RODRIGUEZ
Green Building Rough 3/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/9/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/9/2022 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 3/14/2022 Partial Approval KENNETH ROBERTS
Drywall Nailing 3/15/2022 Partial Approval DANNY RODRIGUEZ
Wood Frame 3/15/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 3/18/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/18/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/18/2022 Partial Approval DANNY RODRIGUEZ
Insulation 3/22/2022 Corrections Issued DANNY RODRIGUEZ
Insulation 3/24/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/25/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/31/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/4/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 5/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/3/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 5/3/2022 Partial Approval DANNY RODRIGUEZ
Insulation 5/16/2022 Partial Approval ROBERT DAVIS
Drywall Nailing 5/20/2022 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 5/20/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 6/3/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/7/2022 Corrections Issued DANNY RODRIGUEZ
Drywall Nailing 6/8/2022 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 6/8/2022 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 6/10/2022 Approved DANNY RODRIGUEZ
Insulation 6/21/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/24/2022 No Access for Inspection ANDREW DORSO
Insulation 6/27/2022 Corrections Issued DANNY RODRIGUEZ
Insulation 6/30/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 7/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 7/7/2022 Partial Approval ROBERT DAVIS
Drywall Nailing 7/22/2022 Partial Approval GREGORY POMISH
Drywall Nailing 7/27/2022 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 11/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 11/16/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/25/2023 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 1/25/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/25/2023 Partial Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 2/14/2023 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 2/14/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 2/15/2023 Partial Approval DANNY RODRIGUEZ
Final 3/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 3/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 3/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 3/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 3/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 3/21/2023 Not Ready for Inspection STEVEN LEVITT
Verify Sprinkler Sign Off 3/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 3/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/23/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 3/23/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 3/23/2023 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 3/23/2023 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 3/23/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/23/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 3/23/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/23/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 3/23/2023 Not Ready for Inspection DANNY RODRIGUEZ
T-Bar Ceiling 5/10/2023 No Access for Inspection DANNY RODRIGUEZ
Final 7/18/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 7/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 7/18/2023 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 7/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/18/2023 SGSOV Approved DANNY RODRIGUEZ
Smoke Detectors 7/18/2023 Partial Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/18/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 7/18/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 7/31/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 7/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 7/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Smoke Detectors 7/31/2023 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 7/31/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 8/10/2023 OK to Issue CofO DANNY RODRIGUEZ
Footing/Foundation/Slab 8/10/2023 Approved DANNY RODRIGUEZ
Green Building Final 8/10/2023 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 8/10/2023 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/10/2023 Approved DANNY RODRIGUEZ
Wood Frame 8/10/2023 Approved DANNY RODRIGUEZ