151 S CLIFFWOOD AVE 90049

Certificate Information: 151 S CLIFFWOOD AVE 90049

Application / Permit
17010-10000-02351
Plan Check / Job No.
B17LA10639
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
PROPOSED 1-STORY ACCESSORY LIVING QUARTER.
Permit Issued
Issued on 12/18/2017
Issuing Office
Metro
Current Status
CofO Issued on 4/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2017 APPLICANT
Assigned to Plan Check Engineer 6/29/2017 LAWRENCE QUIRANTE
Corrections Issued 7/3/2017 LAWRENCE QUIRANTE
Quality Review Completed 7/5/2017 JAMESON LEE
Green Plans Picked Up 7/6/2017 APPLICANT
Building Plans Picked Up 7/7/2017 APPLICANT
Applicant returned to address corrections 7/25/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/10/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/11/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/19/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/22/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 10/6/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 11/14/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 11/30/2017 LAWRENCE QUIRANTE
Plan Check Approved 12/12/2017 LAWRENCE QUIRANTE
Issued 12/18/2017 LADBS
CofO in Progress 4/10/2024 ARAM AVEDISIAN
Permit Finaled 4/17/2024 DANIEL ORRANTE
CofO Issued 4/17/2024 DANIEL ORRANTE
Permit Finaled 4/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/18/2017 BRIAN OLSON
CPC Cleared 8/2/2017 FIPE LEILUA
Eng Process Fee Ord 176,300 Cleared 8/2/2017 ALFREDO JARA
Sewer availability Cleared 8/2/2017 ALFREDO JARA
Green Code Cleared 11/13/2017 KATHRYN BUTTERWORTH
Low Impact Development Cleared 11/14/2017 MITESH PATEL
Roof/Waste drainage to street Cleared 12/11/2017 BRIAN KELLY

Contact Information

Architect Pettas, Alexander; Lic. No.: C32981 4230 BALDWIN AVENUE      CULVER CITY, CA 90232
Contractor Heltzer Development Group Inc; Lic. No.: 993371-B 11751 MISSISSIPPI AVENUE   SUITE 100    LOS ANGELES, CA 90025
Engineer Padilla, Juan C; Lic. No.: C79760 3040 CRESENT WAY      THOUSAND OAKS, CA 91362
Engineer Walter, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/15/2019 Partial Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 8/3/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 8/24/2020 Approved JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 9/21/2020 Partial Approval ANDREW NAVE
Deputy Shotcrete 10/2/2020 Approved ROBERT SHELLY
Excavation/Setback/Form/Re-Bar 10/15/2020 Partial Approval JOHN KIDWELL
Deputy Reinf. Concrete 3/5/2021 Corrections Issued ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 4/20/2021 Partial Approval JOHN KIDWELL
PLUMBING-Rough 5/19/2021 Approved JOHN KIDWELL
ELECTRICAL-Rough 8/30/2021 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 8/30/2021 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 8/30/2021 Approved JOHN KIDWELL
ELECTRICAL-Rough 9/8/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 9/8/2021 Corrections Issued CARLOS MATAMOROS
Wood Frame 9/8/2021 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 9/10/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/10/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 9/23/2021 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 9/23/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 9/27/2021 Approved JOHN KIDWELL
HVAC-Rough 9/27/2021 Approved JOHN KIDWELL
Shower Pan 9/27/2021 Not Ready for Inspection JOHN KIDWELL
Wood Frame 9/27/2021 Partial Approval JOHN KIDWELL
Insulation 10/18/2021 Approved JOHN KIDWELL
Drywall Nailing 11/23/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 11/23/2021 Partial Approval KRISTEN CAUSEY
HVAC-Final 3/9/2023 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/30/2024 Approved ARAM AVEDISIAN
Final 1/30/2024 Corrections Issued ARAM AVEDISIAN
Green Building Final 1/30/2024 Approved ARAM AVEDISIAN
Green Building Rough 1/30/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 1/30/2024 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 1/30/2024 Corrections Issued ARAM AVEDISIAN
Verify Sprinkler Sign Off 1/30/2024 Approved ARAM AVEDISIAN
Final 2/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
Service/Power Release 2/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 2/12/2024 Partial Approval MEL KHACHATOURIAN
Final 4/10/2024 OK to Issue CofO ARAM AVEDISIAN
Smoke Detectors 4/10/2024 Approved ARAM AVEDISIAN