3008 W MARATHON ST lot 8 90026
Certificate Information: 3008 W MARATHON ST lot 8 90026
- Application / Permit
- 17010-10000-02317
- Plan Check / Job No.
- B17LA10481
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 3-STORY, TYPE VB, SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE. SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE TRACT MAP NO. VTT-72779-SL. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED. (LOT #8)
- Permit Issued
- Issued on 2/6/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/14/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2017 | PRANITA SHAH |
| Corrections Issued | 8/2/2017 | PRANITA SHAH |
| Quality Review Completed | 8/8/2017 | ROSHANAK VARJAVAND |
| Building Plans Picked Up | 8/16/2017 | APPLICANT |
| Green Plans Picked Up | 8/17/2017 | APPLICANT |
| Applicant returned to address corrections | 10/19/2017 | PRANITA SHAH |
| Applicant returned to address corrections | 1/9/2018 | PRANITA SHAH |
| Applicant returned to address corrections | 1/22/2018 | PRANITA SHAH |
| Plan Check Approved | 2/5/2018 | PRANITA SHAH |
| Issued | 2/6/2018 | LADBS |
| CofO in Progress | 5/13/2020 | SCOTT FINNILA |
| Permit Finaled | 5/14/2020 | DEROLD HAUFF |
| CofO Issued | 5/14/2020 | DEROLD HAUFF |
| Permit Finaled | 5/14/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/13/2017 | MARTIN FRAGOSO |
| Green Code | Cleared | 10/17/2017 | NEGAR NEJAD |
| Highway dedication | Cleared | 10/23/2017 | CELINA MORENO |
| Address approval | Cleared | 10/25/2017 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2017 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 10/25/2017 | NAZILA NOORIFAR |
| Miscellaneous | Cleared | 11/15/2017 | CRISTIAN GUERRERO |
| Permit | Cleared | 11/15/2017 | CRISTIAN GUERRERO |
| Roof/Waste drainage to street | Cleared | 11/21/2017 | CRISTIAN GUERRERO |
| Building over 3-story or 36-ft | Cleared | 12/6/2017 | CALOSHA APPROVED |
| Frnt yard landscape/Water mgmt | Cleared | 1/9/2018 | EDBER MACEDO |
| Hydrant and Access approval | Cleared | 1/9/2018 | JOHN CONNEALLY |
| ZA Case | Cleared | 1/9/2018 | EDBER MACEDO |
| Tract Map conditions | Cleared | 1/17/2018 | DANALYNN DOMINGUEZ |
| GPI Written Notices | Cleared | 1/22/2018 | PRANITA SHAH |
| Grading Pre-Inspection | Cleared | 1/22/2018 | PRANITA SHAH |
| Disturb/Remove Protected Trees | Cleared | 1/26/2018 | LUIS TORRES |
Contact Information
| Architect | Garrison, John Clark; Lic. No.: C16833 | 1401 DOVE STREET SUITE 410 NEWPORT BEACH, CA 92660 |
| Contractor | Owner-Builder | , |
| Engineer | Rybak, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Tosounian, Oshin Bedros; Lic. No.: S3730 | 7136 HASKELL AVE STE 301 VAN NUYS, CA 91406 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/24/2018 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 5/23/2018 | Corrections Issued | SCOTT FINNILA |
| Underground Mechanical | 6/5/2018 | Not Ready for Inspection | SCOTT FINNILA |
| Underground Mechanical | 6/12/2018 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 6/20/2018 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 7/31/2018 | Partial Approval | SCOTT FINNILA |
| METHANE-Subgrade | 10/24/2018 | Partial Approval | SCOTT FINNILA |
| Deputy Methane Barrier | 10/31/2018 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/1/2018 | Approved | SCOTT FINNILA |
| METHANE-Barrier | 11/1/2018 | Approved | SCOTT FINNILA |
| METHANE-Rough | 11/1/2018 | Approved | SCOTT FINNILA |
| METHANE-Subgrade | 11/1/2018 | Approved | SCOTT FINNILA |
| METHANE-Barrier | 11/2/2018 | Approved | SCOTT FINNILA |
| METHANE-Subgrade | 11/2/2018 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2018 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 11/30/2018 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 12/4/2018 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 12/4/2018 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2018 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2019 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/7/2019 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 1/7/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2019 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 2/6/2019 | Partial Approval | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 2/6/2019 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2019 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 2/20/2019 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2019 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 2/22/2019 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 3/8/2019 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2019 | Not Ready for Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2019 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2019 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 5/16/2019 | Approved | SCOTT FINNILA |
| Shower Pan | 5/16/2019 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/22/2019 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 5/22/2019 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 5/22/2019 | Partial Approval | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 5/22/2019 | Not Ready for Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 5/23/2019 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/24/2019 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/24/2019 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/24/2019 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/24/2019 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 5/24/2019 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 6/11/2019 | Approved | SCOTT FINNILA |
| Drywall Nailing | 6/21/2019 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 7/2/2019 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 8/16/2019 | Approved | SCOTT FINNILA |
| Underground Mechanical | 9/6/2019 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/11/2019 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 9/30/2019 | Partial Approval | SCOTT FINNILA |
| Masonry Wall/Backfill | 10/21/2019 | Partial Approval | SCOTT FINNILA |
| Gas Test | 11/18/2019 | Partial Approval | SCOTT FINNILA |
| Masonry Wall/Backfill | 11/18/2019 | Partial Approval | SCOTT FINNILA |
| Gas Test | 2/4/2020 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/4/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/4/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/19/2020 | Corrections Issued | SCOTT FINNILA |
| Service/Power Release | 2/19/2020 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 2/25/2020 | Approved | SCOTT FINNILA |
| Service/Power Release | 2/25/2020 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 3/11/2020 | Partial Inspection | SCOTT FINNILA |
| Gas Test | 3/11/2020 | Partial Inspection | SCOTT FINNILA |
| Service/Power Release | 3/11/2020 | Partial Inspection | SCOTT FINNILA |
| Final | 3/20/2020 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 3/20/2020 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 3/20/2020 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 3/20/2020 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/20/2020 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 3/20/2020 | Approved | SCOTT FINNILA |
| Gas Test | 4/15/2020 | Approved | SCOTT FINNILA |
| Final | 5/6/2020 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 5/6/2020 | Partial Inspection | SCOTT FINNILA |
| HVAC-Final | 5/6/2020 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 5/6/2020 | Approved | SCOTT FINNILA |
| Final | 5/11/2020 | Partial Inspection | SCOTT FINNILA |
| Green Building Final | 5/11/2020 | Approved | SCOTT FINNILA |
| Final | 5/13/2020 | OK to Issue CofO | SCOTT FINNILA |