3008 W MARATHON ST lot 8 90026

Certificate Information: 3008 W MARATHON ST lot 8 90026

Application / Permit
17010-10000-02317
Plan Check / Job No.
B17LA10481
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
3-STORY, TYPE VB, SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE. SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE TRACT MAP NO. VTT-72779-SL. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED. (LOT #8)
Permit Issued
Issued on 2/6/2018
Issuing Office
Metro
Current Status
CofO Issued on 5/14/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2017 APPLICANT
Assigned to Plan Check Engineer 6/29/2017 PRANITA SHAH
Corrections Issued 8/2/2017 PRANITA SHAH
Quality Review Completed 8/8/2017 ROSHANAK VARJAVAND
Building Plans Picked Up 8/16/2017 APPLICANT
Green Plans Picked Up 8/17/2017 APPLICANT
Applicant returned to address corrections 10/19/2017 PRANITA SHAH
Applicant returned to address corrections 1/9/2018 PRANITA SHAH
Applicant returned to address corrections 1/22/2018 PRANITA SHAH
Plan Check Approved 2/5/2018 PRANITA SHAH
Issued 2/6/2018 LADBS
CofO in Progress 5/13/2020 SCOTT FINNILA
Permit Finaled 5/14/2020 DEROLD HAUFF
CofO Issued 5/14/2020 DEROLD HAUFF
Permit Finaled 5/14/2020 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 9/13/2017 MARTIN FRAGOSO
Green Code Cleared 10/17/2017 NEGAR NEJAD
Highway dedication Cleared 10/23/2017 CELINA MORENO
Address approval Cleared 10/25/2017 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 10/25/2017 NAZILA NOORIFAR
Sewer availability Cleared 10/25/2017 NAZILA NOORIFAR
Miscellaneous Cleared 11/15/2017 CRISTIAN GUERRERO
Permit Cleared 11/15/2017 CRISTIAN GUERRERO
Roof/Waste drainage to street Cleared 11/21/2017 CRISTIAN GUERRERO
Building over 3-story or 36-ft Cleared 12/6/2017 CALOSHA APPROVED
Frnt yard landscape/Water mgmt Cleared 1/9/2018 EDBER MACEDO
Hydrant and Access approval Cleared 1/9/2018 JOHN CONNEALLY
ZA Case Cleared 1/9/2018 EDBER MACEDO
Tract Map conditions Cleared 1/17/2018 DANALYNN DOMINGUEZ
GPI Written Notices Cleared 1/22/2018 PRANITA SHAH
Grading Pre-Inspection Cleared 1/22/2018 PRANITA SHAH
Disturb/Remove Protected Trees Cleared 1/26/2018 LUIS TORRES

Contact Information

Architect Garrison, John Clark; Lic. No.: C16833 1401 DOVE STREET SUITE 410      NEWPORT BEACH, CA 92660
Contractor Owner-Builder       ,
Engineer Rybak, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Engineer Tosounian, Oshin Bedros; Lic. No.: S3730 7136 HASKELL AVE STE 301      VAN NUYS, CA 91406

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/24/2018 Corrections Issued SCOTT FINNILA
Underground Mechanical 5/23/2018 Corrections Issued SCOTT FINNILA
Underground Mechanical 6/5/2018 Not Ready for Inspection SCOTT FINNILA
Underground Mechanical 6/12/2018 Partial Approval SCOTT FINNILA
Underground Mechanical 6/20/2018 Partial Approval SCOTT FINNILA
Underground Mechanical 7/31/2018 Partial Approval SCOTT FINNILA
METHANE-Subgrade 10/24/2018 Partial Approval SCOTT FINNILA
Deputy Methane Barrier 10/31/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 11/1/2018 Approved SCOTT FINNILA
METHANE-Barrier 11/1/2018 Approved SCOTT FINNILA
METHANE-Rough 11/1/2018 Approved SCOTT FINNILA
METHANE-Subgrade 11/1/2018 Approved SCOTT FINNILA
METHANE-Barrier 11/2/2018 Approved SCOTT FINNILA
METHANE-Subgrade 11/2/2018 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/28/2018 Partial Approval SCOTT FINNILA
Deputy Wood Construction 11/30/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 12/4/2018 Partial Approval SCOTT FINNILA
Green Building Rough 12/4/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/26/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/2/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 1/7/2019 Partial Approval SCOTT FINNILA
Green Building Rough 1/7/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/22/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/30/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 2/6/2019 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 2/6/2019 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/15/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 2/20/2019 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/20/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 2/22/2019 Partial Approval SCOTT FINNILA
PLUMBING-Rough 3/8/2019 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/13/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/26/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/29/2019 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/1/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/17/2019 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 5/16/2019 Approved SCOTT FINNILA
Shower Pan 5/16/2019 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 5/22/2019 Partial Approval SCOTT FINNILA
Green Building Rough 5/22/2019 Partial Approval SCOTT FINNILA
HVAC-Rough 5/22/2019 Partial Approval SCOTT FINNILA
Verify Sprinkler Sign Off 5/22/2019 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Rough 5/23/2019 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 5/24/2019 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/24/2019 Conditional Approval ALEJANDRO DE ARTOLA
Green Building Rough 5/24/2019 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 5/24/2019 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 5/24/2019 Approved ALEJANDRO DE ARTOLA
Insulation 6/11/2019 Approved SCOTT FINNILA
Drywall Nailing 6/21/2019 Approved SCOTT FINNILA
Interior/Exterior Lathing 7/2/2019 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 8/16/2019 Approved SCOTT FINNILA
Underground Mechanical 9/6/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Underground Mechanical 9/11/2019 Partial Approval SCOTT FINNILA
Underground Mechanical 9/30/2019 Partial Approval SCOTT FINNILA
Masonry Wall/Backfill 10/21/2019 Partial Approval SCOTT FINNILA
Gas Test 11/18/2019 Partial Approval SCOTT FINNILA
Masonry Wall/Backfill 11/18/2019 Partial Approval SCOTT FINNILA
Gas Test 2/4/2020 Approved ALEJANDRO DE ARTOLA
HVAC-Final 2/4/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Final 2/4/2020 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/19/2020 Corrections Issued SCOTT FINNILA
Service/Power Release 2/19/2020 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 2/25/2020 Approved SCOTT FINNILA
Service/Power Release 2/25/2020 Approved SCOTT FINNILA
ELECTRICAL-Final 3/11/2020 Partial Inspection SCOTT FINNILA
Gas Test 3/11/2020 Partial Inspection SCOTT FINNILA
Service/Power Release 3/11/2020 Partial Inspection SCOTT FINNILA
Final 3/20/2020 Corrections Issued SCOTT FINNILA
Green Building Final 3/20/2020 Corrections Issued SCOTT FINNILA
HVAC-Final 3/20/2020 Approved SCOTT FINNILA
PLUMBING-Final 3/20/2020 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/20/2020 SGSOV Approved SCOTT FINNILA
Smoke Detectors 3/20/2020 Approved SCOTT FINNILA
Gas Test 4/15/2020 Approved SCOTT FINNILA
Final 5/6/2020 Corrections Issued SCOTT FINNILA
Green Building Final 5/6/2020 Partial Inspection SCOTT FINNILA
HVAC-Final 5/6/2020 Approved SCOTT FINNILA
PLUMBING-Final 5/6/2020 Approved SCOTT FINNILA
Final 5/11/2020 Partial Inspection SCOTT FINNILA
Green Building Final 5/11/2020 Approved SCOTT FINNILA
Final 5/13/2020 OK to Issue CofO SCOTT FINNILA