3320-3326 E 6TH ST 90023
Certificate Information: 3320-3326 E 6TH ST 90023
- Application / Permit
- 17010-10000-02203
- Plan Check / Job No.
- B17LA09605
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Dwelling - multiple
- Work Description
- New 3 story, Type VB, 4 townhouses 3 with attached two-car garage and 1 with attached 1-car garage.
- Permit Issued
- Issued on 10/15/2018
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 8/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2017 | APPLICANT |
| Disabled Access Plans Picked Up | 6/14/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2017 | KESETE HAREGOT |
| Green Plans Picked Up | 6/22/2017 | APPLICANT |
| Corrections Issued | 6/30/2017 | KESETE HAREGOT |
| Quality Review Completed | 7/13/2017 | CHARLES CHANG |
| Building Plans Picked Up | 7/13/2017 | APPLICANT |
| Applicant returned to address corrections | 10/12/2017 | KESETE HAREGOT |
| Applicant returned to address corrections | 12/21/2017 | KESETE HAREGOT |
| Applicant returned to address corrections | 3/8/2018 | KESETE HAREGOT |
| Plan Check Approved | 8/7/2018 | KESETE HAREGOT |
| No Progress | 8/7/2018 | KESETE HAREGOT |
| Plan Check Approved | 8/7/2018 | KESETE HAREGOT |
| Issued | 10/15/2018 | LADBS |
| CofO in Progress | 8/12/2021 | LANNY MERRICK |
| Permit Finaled | 8/23/2021 | ERNESTO CORRAL |
| CofO Issued | 8/23/2021 | ERNESTO CORRAL |
| Permit Finaled | 8/23/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 9/22/2017 | RICHARD DOCKUS |
| Address approval | Cleared | 10/5/2017 | ALFREDO JARA |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2017 | ALFREDO JARA |
| Permit | Cleared | 10/5/2017 | ALFREDO JARA |
| Sewer availability | Cleared | 10/5/2017 | ALFREDO JARA |
| Hydrant and Access approval | Cleared | 10/6/2017 | JOHN CONNEALLY |
| ZI | Cleared | 10/6/2017 | JUSTIN BILOW |
| Highway dedication | Cleared | 10/16/2017 | RAVIL MANAPOV |
| Low Impact Development | Cleared | 3/9/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/9/2018 | ADRIAN SANCHEZ |
| DAS Clearance | Cleared | 8/7/2018 | SOMKIAT SUPANYACHOTSKUL |
Contact Information
| Engineer | , ; Lic. No.: C81768 | 7941 YOLANDA AVE RESEDA, CA 91335 |
| Engineer | , ; Lic. No.: C86223 | 1840 S. GAFFEY ST. 382 SAN PEDRO, CA 9073 |
| Engineer | Madero, Fidencio Jr; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/26/2018 | No Access for Inspection | ANDEY CHAPARRO |
| Footing/Foundation/Slab | 12/14/2018 | Not Ready for Inspection | LUIS ALVAREZ |
| Footing/Foundation/Slab | 12/18/2018 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 12/24/2018 | Conditional Approval | ERNESTO CORRAL |
| Reinforced Concrete Frame | 12/28/2018 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 12/31/2018 | Partial Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2019 | Partial Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2019 | Partial Inspection | JEFFREY FULTON |
| Green Building Rough | 4/25/2019 | Not Ready for Inspection | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 4/25/2019 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 4/25/2019 | Not Ready for Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2019 | No Access for Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2019 | Not Ready for Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2019 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 8/5/2019 | No Access for Inspection | JEFFREY FULTON |
| Green Building Rough | 8/14/2019 | Approved | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 8/14/2019 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 8/14/2019 | Partial Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2019 | Partial Inspection | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 8/20/2019 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 1/17/2020 | Corrections Issued | RONALD PACHECO |
| Special/Order Compliance | 1/31/2020 | Not Ready for Inspection | RONALD PACHECO |
| Special/Order Compliance | 2/10/2020 | Not Ready for Inspection | RONALD PACHECO |
| Special/Order Compliance | 2/14/2020 | Partial Inspection | RONALD PACHECO |
| Insulation | 2/21/2020 | Approved | RONALD PACHECO |
| Drywall Nailing | 3/17/2020 | Approved | RONALD PACHECO |
| Footing/Foundation/Slab | 7/22/2020 | Corrections Issued | RONALD PACHECO |
| Footing/Foundation/Slab | 7/24/2020 | Partial Approval | RONALD PACHECO |
| Verify Sprinkler Sign Off | 7/24/2020 | Not Ready for Inspection | RONALD PACHECO |
| Final | 7/19/2021 | Not Ready for Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 7/19/2021 | Not Ready for Inspection | LANNY MERRICK |
| Green Building Final | 7/19/2021 | Approved | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 7/19/2021 | SGSOV Approved | LANNY MERRICK |
| Smoke Detectors | 7/19/2021 | Approved | LANNY MERRICK |
| Final | 8/4/2021 | Partial Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 8/4/2021 | Partial Inspection | LANNY MERRICK |
| Deputy Shotcrete | 8/12/2021 | Conditional Approval | LANNY MERRICK |
| Final | 8/12/2021 | OK to Issue CofO | LANNY MERRICK |
| Footing/Foundation/Slab | 8/12/2021 | Approved | LANNY MERRICK |