9229 N WHITE OAK AVE 91325

Certificate Information: 9229 N WHITE OAK AVE 91325

Application / Permit
17010-10000-02106
Plan Check / Job No.
B17LA09256
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
AN ADDITION TO AN EXISTING CARPORT TO CREATE AN ATTACHED RECREATION ROOM AND AN ACCESSORY DWELLING UNIT PER AB2299 AND SB1069 AND A DECK ON SECOND LEVEL
Permit Issued
Issued on 12/22/2017
Issuing Office
Metro
Current Status
CofO Issued on 9/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2017 APPLICANT
Assigned to Plan Check Engineer 6/22/2017 MINA HABIB
Corrections Issued 7/12/2017 MINA HABIB
Quality Review Completed 7/17/2017 SAI KHUM
Building Plans Picked Up 7/25/2017 APPLICANT
Green Plans Picked Up 7/25/2017 APPLICANT
Applicant returned to address corrections 8/25/2017 MINA HABIB
Applicant returned to address corrections 8/31/2017 MINA HABIB
Applicant returned to address corrections 10/18/2017 MINA HABIB
Plan Check Approved 10/19/2017 MINA HABIB
Plan Check Approved 12/22/2017 SUEN LIEU
Issued 12/22/2017 LADBS
CofO in Progress 9/25/2020 MICHAEL TEMPLE
CofO Issued 9/29/2020 MICHAEL SMITH
Permit Finaled 9/29/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/12/2017 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 9/12/2017 RAVIL MANAPOV
Sewer availability Cleared 9/12/2017 RAVIL MANAPOV
Low Impact Development Cleared 10/2/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/2/2017 CELINA MORENO
Hydrant and Access approval Cleared 10/3/2017 GILBERT URREA
Green Code Cleared 10/11/2017 JOHN KLARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Tsai, Willy Y; Lic. No.: C35589 1545 RUBIO DR      SAN MARINO, CA 91108

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/17/2018 Approved MARK JOHNSON
Excavation/Setback/Form/Re-Bar 1/24/2018 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 1/24/2018 Not Ready for Inspection MARK JOHNSON
Excavation/Setback/Form/Re-Bar 1/29/2018 Approved MARK JOHNSON
Footing/Foundation/Slab 1/29/2018 Approved MARK JOHNSON
BUILDING-Rough-Frame 2/21/2018 Partial Inspection MARK JOHNSON
Green Building Rough 2/21/2018 Not Ready for Inspection MARK JOHNSON
Wood Frame 2/21/2018 Approved MARK JOHNSON
BUILDING-Rough-Frame 3/1/2018 Not Ready for Inspection MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 3/1/2018 Approved MARK JOHNSON
Green Building Rough 3/1/2018 Not Ready for Inspection MARK JOHNSON
Interior/Exterior Lathing 3/1/2018 Not Ready for Inspection MARK JOHNSON
Wood Frame 3/1/2018 Not Ready for Inspection MARK JOHNSON
Pre-Inspection 4/12/2018 Approved MARK JOHNSON
PLUMBING-Rough 4/27/2018 Corrections Issued MARK JOHNSON
PLUMBING-Rough 5/3/2018 Approved MARK JOHNSON
BUILDING-Rough-Frame 11/9/2018 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 11/9/2018 Not Ready for Inspection MARK JOHNSON
Green Building Rough 11/9/2018 Approved MARK JOHNSON
HVAC-Rough 11/9/2018 Not Ready for Inspection MARK JOHNSON
Wood Frame 11/9/2018 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/6/2018 Approved MARK JOHNSON
Deck 12/6/2018 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 12/6/2018 Approved MARK JOHNSON
HVAC-Rough 12/6/2018 Approved MARK JOHNSON
Interior/Exterior Lathing 12/6/2018 Approved MARK JOHNSON
Wood Frame 12/6/2018 Approved MARK JOHNSON
Deck 1/25/2019 Approved GREG ALLTON
Insulation 1/25/2019 Approved GREG ALLTON
Shower Pan 2/28/2019 Off-Hour Fees Due
Drywall Nailing 3/11/2019 Approved MICHEL ABAJAN
Shower Pan 3/11/2019 Not Ready for Inspection MICHEL ABAJAN
Shower Pan 4/11/2019 Approved MARK JOHNSON
Service/Power Release 6/12/2019 Not Ready for Inspection CHARLES POWELL
Final 1/17/2020 Not Ready for Inspection MARK JOHNSON
Green Building Final 1/17/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 1/17/2020 SGSOV Approved MARK JOHNSON
Smoke Detectors 1/17/2020 Approved MARK JOHNSON
Final 2/3/2020 Partial Approval DANIEL ORRANTE
Special/Order Compliance 9/2/2020 Corrections Issued MICHAEL TEMPLE
Final 9/25/2020 OK to Issue CofO MICHAEL TEMPLE