7610 N GENTRY AVE 91605
Certificate Information: 7610 N GENTRY AVE 91605
- Application / Permit
- 17010-10000-02008
- Plan Check / Job No.
- B17LA08675
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACCESSORY DWELLING UNIT PER AB 2299 & SB 1069 WITH AN ATTACHED GARAGE.
- Permit Issued
- Issued on 10/26/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2017 | CAROLYNN NEPOMUCENO |
| Green Plans Picked Up | 6/27/2017 | APPLICANT |
| Corrections Issued | 6/28/2017 | CAROLYNN NEPOMUCENO |
| Quality Review Completed | 6/29/2017 | ALLEN MANALANSAN |
| Building Plans Picked Up | 7/5/2017 | APPLICANT |
| Applicant returned to address corrections | 8/11/2017 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 9/7/2017 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 10/3/2017 | CAROLYNN NEPOMUCENO |
| Plan Check Approved | 10/12/2017 | CAROLYNN NEPOMUCENO |
| Issued | 10/26/2017 | LADBS |
| CofO in Progress | 7/17/2025 | MATTHEW NELSON |
| Permit Finaled | 8/13/2025 | RUBEN SALAS |
| CofO Issued | 8/13/2025 | RUBEN SALAS |
| Permit Finaled | 8/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/11/2017 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 8/11/2017 | GILBERT URREA |
| Miscellaneous | Cleared | 8/11/2017 | EDBER MACEDO |
| Permit | Cleared | 8/11/2017 | JAMES MORALEZ |
| ZA Case | Cleared | 8/11/2017 | EDBER MACEDO |
| ZA Case | Cleared | 8/11/2017 | EDBER MACEDO |
| ZA Case | Cleared | 8/11/2017 | EDBER MACEDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2017 | RAVIL MANAPOV |
| Low Impact Development | Cleared | 9/7/2017 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 9/7/2017 | RAVIL MANAPOV |
| Sewer availability | Cleared | 9/7/2017 | RAVIL MANAPOV |
| Green Code | Cleared | 10/3/2017 | NEGAR NEJAD |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang, Kuo-Ping; Lic. No.: C43144 | 730 QUAIL VALLEY LANE WEST COVINA, CA 91791 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 4/9/2020 | No Access for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Sewer | 10/25/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 10/25/2023 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/30/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 10/30/2023 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/7/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Grounding or Bonding | 11/7/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 11/15/2023 | No Access for Inspection | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/19/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/29/2024 | Approved | MATTHEW NELSON |
| Grounding or Bonding | 1/29/2024 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2024 | Partial Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/27/2024 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/27/2024 | No Access for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | No Access for Inspection | MATTHEW NELSON |
| Green Building Rough | 8/27/2024 | No Access for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 8/27/2024 | No Access for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 8/27/2024 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/30/2024 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 8/30/2024 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 9/19/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/24/2024 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 9/24/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 9/24/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/8/2024 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 10/8/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/15/2024 | Partial Approval | MATTHEW NELSON |
| HVAC-Rough | 11/12/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 11/15/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 11/27/2024 | Approved | MATTHEW NELSON |
| Insulation | 11/27/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/27/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Shower Pan | 11/27/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/18/2024 | Approved | MATTHEW NELSON |
| Underground Mechanical | 12/18/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Sewer | 1/22/2025 | Approved | MATTHEW NELSON |
| Final | 7/11/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 7/11/2025 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 7/11/2025 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 7/11/2025 | Approved | MATTHEW NELSON |
| Final | 7/16/2025 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 7/16/2025 | Approved | MATTHEW NELSON |
| Service/Power Release | 7/16/2025 | Approved | MATTHEW NELSON |