714 N LUCILE AVE 90026

Certificate Information: 714 N LUCILE AVE 90026

Application / Permit
17010-10000-01910
Plan Check / Job No.
B17LA08232
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3 STORY S.F.D. WITH ATTACHED GARAGE. " SMALL LOT SUBDIVISIN PURSUANT TO PRELIMINARY PARCEL MAP No. AA-2016-4276-PMLA-SL. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP AS BEEN RECORDED"
Permit Issued
Issued on 11/20/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2017 APPLICANT
Assigned to Plan Check Engineer 6/2/2017 TARIK SAOUD
Green Plans Picked Up 6/2/2017 APPLICANT
Corrections Issued 6/3/2017 TARIK SAOUD
Quality Review Completed 6/7/2017 STEVEN KIM
Building Plans Picked Up 6/28/2017 APPLICANT
Plan Check Approved 11/20/2017 TARIK SAOUD
Issued 11/20/2017 LADBS
Refund in Progress-Status Void 3/19/2018 CHRISTINA TABIRARA
Re-Activate Permit 4/2/2018 CHRISTINA TABIRARA
Refund Completed-Status Void 5/23/2018 CHRISTINA TABIRARA
Re-Activate Permit 1/8/2019 MARY SUM
CofO in Progress 12/21/2023 ALIZAH MAYAGOITIA
CofO Issued 12/22/2023 DEROLD HAUFF
Permit Finaled 12/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/9/2017 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 8/9/2017 ADRIAN SANCHEZ
Green Code Cleared 9/1/2017 RICHARD DOCKUS
Hydrant and Access approval Cleared 9/1/2017 JOHN CONNEALLY
Grading Pre-Inspection Cleared 9/27/2017 BARTON HOLMES
Low Impact Development Cleared 9/27/2017 RYAN HUDSON
Sewer availability Cleared 9/27/2017 STEVE MELGAR
Miscellaneous Cleared 9/28/2017 EDBER MACEDO
Highway dedication Cleared 10/2/2017 STEVE MELGAR
Green Code Cleared 10/11/2017 TARIK SAOUD
Miscellaneous Cleared 11/14/2017 MARKOS PEREZ-BRAN
Permit Cleared 11/14/2017 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 11/14/2017 MARKOS PEREZ-BRAN

Contact Information

Architect Vanos, Vincent Jay; Lic. No.: C22269 2747 MARQUETTE DR      TOPANGA, CA 90290
Contractor J Z J B Cnst Inv; Lic. No.: 1013600-B 10236 LAKEWOOD BLVD STE B      DOWNEY, CA 90241
Engineer Sheikh, Ijaz Ahmed; Lic. No.: S2392 5505 LAKEVIEW CANYON RD      WESTLAKE VILLAGE, CA 91362
Engineer Walter, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401
Geologist Barrett, Mark A; Lic. No.: EG2088 11966 HONEYBROOK CT.      MOORPARK, CA 93021

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/1/2017 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 1/30/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 1/30/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 3/9/2018 Not Ready for Inspection SCOTT FINNILA
Footing/Foundation/Slab 3/13/2018 Corrections Issued SCOTT FINNILA
Green Building Rough 3/13/2018 Not Ready for Inspection SCOTT FINNILA
Structural Steel Frame 3/13/2018 Not Ready for Inspection SCOTT FINNILA
Verify Sprinkler Sign Off 3/13/2018 Not Ready for Inspection SCOTT FINNILA
Footing/Foundation/Slab 4/17/2018 Conditional Approval SCOTT FINNILA
Pre-Inspection 1/10/2019 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 6/4/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 6/4/2019 Partial Approval SCOTT FINNILA
Insulation 6/11/2019 Approved SCOTT FINNILA
PLUMBING-Rough 7/31/2019 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 8/2/2019 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 8/2/2019 Approved SCOTT FINNILA
BUILDING-Rough-Frame 9/4/2019 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/4/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Wood Frame 10/16/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/25/2019 Partial Approval SCOTT FINNILA
Insulation 10/25/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/8/2019 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 11/8/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/20/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/21/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/2/2020 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/3/2020 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/10/2020 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/23/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 2/5/2020 Not Ready for Inspection MICHAEL FAUNCE
HVAC-Rough 2/5/2020 Not Ready for Inspection MICHAEL FAUNCE
Interior/Exterior Lathing 2/5/2020 Conditional Approval MICHAEL FAUNCE
ELECTRICAL-Rough 2/10/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 2/10/2020 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/11/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 2/11/2020 Not Ready for Inspection SCOTT FINNILA
Green Building Rough 2/11/2020 Approved SCOTT FINNILA
HVAC-Rough 2/11/2020 Not Ready for Inspection SCOTT FINNILA
Verify Sprinkler Sign Off 2/11/2020 Approved SCOTT FINNILA
ELECTRICAL-Rough 2/18/2020 Approved SCOTT FINNILA
HVAC-Rough 2/18/2020 Approved SCOTT FINNILA
BUILDING-Rough-Frame 2/19/2020 Approved SCOTT FINNILA
Insulation 2/24/2020 Approved SCOTT FINNILA
Interior/Exterior Lathing 4/24/2020 Approved SCOTT FINNILA
Gas Test 10/9/2020 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 10/9/2020 Partial Inspection SCOTT FINNILA
Sewer 10/9/2020 Partial Inspection SCOTT FINNILA
Underground Mechanical 10/13/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 10/20/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 10/20/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 11/14/2022 Corrections Issued SCOTT FINNILA
HVAC-Final 11/14/2022 Corrections Issued SCOTT FINNILA
PLUMBING-Final 11/14/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 1/30/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 1/30/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 12/5/2023 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 12/5/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 12/5/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/12/2023 Conditional Approval ALIZAH MAYAGOITIA
Final 12/12/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/12/2023 Approved ALIZAH MAYAGOITIA
Gas Test 12/12/2023 Approved ALIZAH MAYAGOITIA
Green Building Final 12/12/2023 Approved ALIZAH MAYAGOITIA
HVAC-Final 12/12/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 12/12/2023 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/12/2023 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 12/12/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Structural Steel Frame 12/12/2023 Approved ALIZAH MAYAGOITIA
Final 12/18/2023 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 12/18/2023 Approved ALIZAH MAYAGOITIA