8840 N BALBOA BLVD 91325

Certificate Information: 8840 N BALBOA BLVD 91325

Application / Permit
17010-10000-01595
Plan Check / Job No.
B17LA06734
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW HOUSE (A) TWO STORIES MULTIPLE 1 OF 3
Permit Issued
Issued on 4/10/2019
Issuing Office
Valley
Current Status
CofO Issued on 9/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2017 APPLICANT
Assigned to Plan Check Engineer 5/11/2017 XIAOZHE ZHANG
Green Plans Picked Up 5/17/2017 APPLICANT
Corrections Issued 5/22/2017 XIAOZHE ZHANG
Quality Review Completed 5/30/2017 BILL STUTSMAN
Building Plans Picked Up 6/7/2017 APPLICANT
Applicant returned to address corrections 10/19/2017 XIAOZHE ZHANG
Applicant returned to address corrections 2/28/2018 XIAOZHE ZHANG
Applicant returned to address corrections 8/2/2018 DEAN RYAN REYES
Applicant returned to address corrections 10/25/2018 DEAN RYAN REYES
Applicant returned to address corrections 11/14/2018 DEAN RYAN REYES
Applicant returned to address corrections 12/13/2018 DEAN RYAN REYES
Applicant returned to address corrections 2/7/2019 DEAN RYAN REYES
Applicant returned to address corrections 2/14/2019 DEAN RYAN REYES
Applicant returned to address corrections 2/25/2019 DEAN RYAN REYES
Applicant returned to address corrections 3/27/2019 DEAN RYAN REYES
Plan Check Approved 4/5/2019 DEAN RYAN REYES
Issued 4/10/2019 LADBS
CofO in Progress 8/31/2021 JACK KARGODORIAN
Permit Finaled 9/9/2021 MICHAEL SMITH
CofO Issued 9/9/2021 MICHAEL SMITH
Permit Finaled 9/9/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/21/2017 CARLA VALLADARES
Green Code Cleared 7/21/2017 JOHN KLARIN
Miscellaneous Cleared 8/23/2017 STEVEN WECHSLER
Miscellaneous Cleared 8/23/2017 STEVEN WECHSLER
Miscellaneous Cleared 8/23/2017 STEVEN WECHSLER
Address approval Cleared 9/29/2017 HOWARD COOPER
Hydrant and Access approval Cleared 10/18/2017 JOHN DALLAS
Sewer availability Cleared 2/26/2018 KAYLA PEJI
Miscellaneous Cleared 5/31/2018 VICENTE CORDERO
Highway dedication Cleared 7/9/2018 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/9/2018 LEE GUILBEAUX
Private street Cleared 10/18/2018 STEVEN WECHSLER
Tract Map conditions Cleared 10/18/2018 STEVEN WECHSLER
Low Impact Development Cleared 1/22/2019 MARTIN FRAGOSO
"T" removal Cleared 1/31/2019 RICK TORRES
Miscellaneous Cleared 2/1/2019 RICK TORRES

Contact Information

Contractor B D S Construction Inc; Lic. No.: 614706-B 23615 WELBY WAY      WEST HILLS, CA 91307
Engineer Melchor, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 4/16/2019 Not Ready for Inspection JACK KARGODORIAN
Pre-Inspection 4/16/2019 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 7/17/2019 Corrections Issued BEAU COLLINS
PLUMBING-Rough 7/22/2019 Partial Approval JACK KARGODORIAN
Special/Order Compliance 7/22/2019 Partial Inspection JACK KARGODORIAN
Footing/Foundation/Slab 8/16/2019 Approved JOHN HAYES
BUILDING-Rough-Frame 9/9/2019 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 9/9/2019 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 9/9/2019 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 9/12/2019 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 9/12/2019 Approved JACK KARGODORIAN
Special/Order Compliance 9/12/2019 Partial Approval JACK KARGODORIAN
Verify Sprinkler Sign Off 9/12/2019 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/12/2019 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 12/6/2019 Approved JACK KARGODORIAN
HVAC-Rough 12/11/2019 Approved JACK KARGODORIAN
ELECTRICAL-Rough 12/20/2019 Approved JACK KARGODORIAN
HVAC-Rough 12/20/2019 Approved JACK KARGODORIAN
PLUMBING-Rough 12/20/2019 Approved JACK KARGODORIAN
ELECTRICAL-Rough 12/30/2019 Approved JACK KARGODORIAN
HVAC-Rough 12/30/2019 Approved JACK KARGODORIAN
PLUMBING-Rough 12/30/2019 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/9/2020 Not Ready for Inspection JACK KARGODORIAN
Drywall Nailing 1/9/2020 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/9/2020 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 1/9/2020 Approved JACK KARGODORIAN
Deputy Wood Construction 1/17/2020 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/17/2020 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/28/2020 Approved JACK KARGODORIAN
Insulation 1/28/2020 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 1/28/2020 Partial Approval JACK KARGODORIAN
Verify Sprinkler Sign Off 1/28/2020 Approved JACK KARGODORIAN
Insulation 2/4/2020 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 2/4/2020 Partial Approval JACK KARGODORIAN
Drywall Nailing 2/11/2020 Approved JACK KARGODORIAN
Shower Pan 3/25/2020 Approved MICHEL ABAJAN
Underground Mechanical 6/24/2020 Partial Inspection JENNIFER RABUCHIN
Sewer 10/15/2020 Corrections Issued MICHAEL TEMPLE
Pre-Inspection 10/19/2020 Partial Inspection MICHAEL TEMPLE
Sewer 10/22/2020 Corrections Issued CHARLES POWELL
PLUMBING-Rough 10/27/2020 Corrections Issued MICHAEL TEMPLE
Sewer 10/27/2020 Approved MICHAEL TEMPLE
PLUMBING-Rough 11/10/2020 Partial Inspection ARTHUR SARGSYAN
Pre-Inspection 11/19/2020 No Access for Inspection ARTHUR SARGSYAN
Pre-Inspection 11/24/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 12/8/2020 Not Ready for Inspection ARTHUR SARGSYAN
Masonry Wall/Backfill 12/21/2020 Approved ARTHUR SARGSYAN
PLUMBING-Final 1/21/2021 Partial Approval MICHAEL TEMPLE
Service/Power Release 6/25/2021 Not Ready for Inspection MICHAEL TEMPLE
Gas Test 7/1/2021 Approved JACK KARGODORIAN
ELECTRICAL-Final 7/6/2021 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 7/12/2021 Approved JACK KARGODORIAN
HVAC-Final 7/12/2021 Approved JACK KARGODORIAN
HVAC-Final 7/15/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 7/20/2021 Approved JACK KARGODORIAN
PLUMBING-Final 8/27/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 8/31/2021 OK to Issue CofO JACK KARGODORIAN
Green Building Final 8/31/2021 Approved JACK KARGODORIAN
PLUMBING-Final 8/31/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Approved JACK KARGODORIAN
Service/Power Release 8/31/2021 Approved JACK KARGODORIAN
Smoke Detectors 8/31/2021 Approved JACK KARGODORIAN