4735 W ELMWOOD AVE 90004

Certificate Information: 4735 W ELMWOOD AVE 90004

Application / Permit
17010-10000-01579
Plan Check / Job No.
B17LA06700
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
LOT 1 New 4- story single family dwelling with attached 2- car garage in a Small Lot Subdivision pursuant to Tract Map No. 74646-SL.
Permit Issued
Issued on 6/26/2018
Issuing Office
Metro
Current Status
CofO Issued on 7/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2017 APPLICANT
Assigned to Plan Check Engineer 5/18/2017 ARMEN SARKISIAN
Green Plans Picked Up 6/2/2017 APPLICANT
Corrections Issued 6/23/2017 ARMEN SARKISIAN
Quality Review Completed 7/5/2017 BINH PHAN
Building Plans Picked Up 7/6/2017 APPLICANT
Applicant returned to address corrections 7/28/2017 ARMEN SARKISIAN
Applicant returned to address corrections 12/5/2017 KESETE HAREGOT
Plan Check Approved 1/11/2018 KESETE HAREGOT
Issued 6/26/2018 LADBS
CofO in Progress 7/15/2022 ALEJANDRO DE ARTOLA
Permit Finaled 7/21/2022 DEROLD HAUFF
CofO Issued 7/21/2022 DEROLD HAUFF
Permit Finaled 7/21/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/20/2017 RAVIL MANAPOV
Address approval Cleared 7/20/2017 RAVIL MANAPOV
Construction near power lines Cleared 7/20/2017 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 7/20/2017 RAVIL MANAPOV
Miscellaneous Cleared 7/28/2017 JESSE RAMOS
Hydrant and Access approval Cleared 8/1/2017 ROBERT DUFF
Green Code Cleared 8/25/2017 WILLIAM ROSE
Sewer availability Cleared 8/25/2017 RAVIL MANAPOV
Frnt yard landscape/Water mgmt Cleared 9/12/2017 JESSE RAMOS
Miscellaneous Cleared 9/12/2017 JESSE RAMOS
Tract Map conditions Cleared 9/12/2017 JESSE RAMOS
ZA Case Cleared 9/27/2017 JESSE RAMOS
ZA Case Cleared 9/27/2017 JESSE RAMOS
Highway dedication Cleared 11/3/2017 ROCHELLE DUNGCA
Low Impact Development Cleared 11/3/2017 MICHAEL SCADUTO
Permit Cleared 11/3/2017 ROCHELLE DUNGCA
Roof/Waste drainage to street Cleared 11/3/2017 ROCHELLE DUNGCA

Contact Information

Contractor Assen Homes Inc; Lic. No.: 789611-B 223 ALICE STREET # B      ARCADIA, CA 91006
Engineer Jong, Hank Hsing-Lian; Lic. No.: GE2305 11819 GOLDRING ROAD UNIT A      ARCADIA, CA 91006
Engineer Lee, Jaeyol; Lic. No.: C51639 430 S GARFIELD AVE #320      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/10/2018 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 1/30/2019 Partial Approval LUIS BARRALES
PLUMBING-Rough 1/30/2019 Partial Approval LUIS BARRALES
Footing/Foundation/Slab 2/26/2019 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/4/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/4/2019 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 4/4/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 4/4/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/15/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 4/22/2019 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 4/22/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/7/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/15/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 5/21/2019 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 5/21/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/17/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/27/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/2/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/1/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/22/2019 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/26/2019 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 9/4/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 9/27/2019 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/12/2019 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/7/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/10/2020 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 1/16/2020 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 1/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/5/2020 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 3/5/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/24/2020 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 4/24/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 5/13/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/19/2020 Conditional Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/29/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/14/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/27/2020 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/31/2020 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/6/2020 Approved ALEJANDRO DE ARTOLA
Green Building Rough 8/6/2020 Approved ALEJANDRO DE ARTOLA
Insulation 8/6/2020 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 8/6/2020 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 8/17/2020 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/19/2020 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/29/2020 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 10/15/2020 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 4/28/2021 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 4/30/2021 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 5/5/2021 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/16/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 11/10/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 4/4/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/6/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/26/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/26/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 5/2/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 5/2/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/2/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 5/4/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/4/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 5/13/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/13/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/1/2022 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 7/1/2022 Approved ALEJANDRO DE ARTOLA
Final 7/12/2022 Partial Approval ALEJANDRO DE ARTOLA
Green Building Final 7/12/2022 Partial Approval ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Final 7/14/2022 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 7/14/2022 Approved ALEJANDRO DE ARTOLA