6417 N FIGUEROA ST 1-21 90042
Certificate Information: 6417 N FIGUEROA ST 1-21 90042
- Application / Permit
- 17010-10000-01480
- Plan Check / Job No.
- B17LA06195
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New 2-story type V-B 21-unit apt building over type I-A podium open garage.
- Permit Issued
- Issued on 1/8/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 4/18/2017 | APPLICANT |
Assigned to Plan Check Engineer | 5/19/2017 | TARIK SAOUD |
Corrections Issued | 5/21/2017 | TARIK SAOUD |
Quality Review Completed | 5/24/2017 | STEVEN KIM |
Green Plans Picked Up | 5/24/2017 | APPLICANT |
Building Plans Picked Up | 5/30/2017 | APPLICANT |
Disabled Access Plans Picked Up | 5/30/2017 | APPLICANT |
Plan Check Approved | 1/8/2018 | TARIK SAOUD |
Issued | 1/8/2018 | LADBS |
CofO in Progress | 4/20/2021 | DANIEL COLLINS |
CofO in Progress | 4/22/2021 | DANIEL COLLINS |
Permit Finaled | 4/26/2021 | ERNESTO CORRAL |
CofO Issued | 4/26/2021 | ERNESTO CORRAL |
Permit Finaled | 4/26/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
Address approval | Cleared | 6/20/2017 | FATIMA GUERRA |
Permit | Cleared | 6/20/2017 | FATIMA GUERRA |
Work Adjacent to Public Way | Cleared | 6/20/2017 | HOK CHI CHIU |
Construction near power lines | Cleared | 8/22/2017 | RIDWAN HARDY |
Eng Process Fee Ord 176,300 | Cleared | 9/19/2017 | FATIMA GUERRA |
Frnt yard landscape/Water mgmt | Cleared | 9/19/2017 | EDBER MACEDO |
Opn space landscape/Water mgmt | Cleared | 9/19/2017 | EDBER MACEDO |
Sewer availability | Cleared | 9/19/2017 | FATIMA GUERRA |
Highway dedication | Cleared | 9/22/2017 | ROCHELLE DUNGCA |
Housing density bonus | Cleared | 10/10/2017 | KENNETH LE |
Hydrant and Access approval | Cleared | 10/16/2017 | JOHN CONNEALLY |
Fire Marshall Fire Life Safety | Cleared | 10/17/2017 | PEJMAN NOORI |
Green Code | Cleared | 10/27/2017 | RICHARD DOCKUS |
DAS Clearance | Cleared | 11/8/2017 | EDDIE GARIN |
Low Impact Development | Cleared | 1/2/2018 | MICHAEL SCADUTO |
Roof/Waste drainage to street | Cleared | 1/2/2018 | NAZILA NOORIFAR |
Building over 3-story or 36-ft | Cleared | 1/8/2018 | CALOSHA APPROVED |
Excavation more than 5-ft deep | Cleared | 1/8/2018 | CALOSHA APPROVED |
Grading Pre-Inspection | Cleared | 1/8/2018 | TARIK SAOUD |
Contact Information
Architect | Lee, Wan; Lic. No.: C30792 | 530 MOLINO STREET SUITE 220 LOS ANGELES, CA 90013 |
Contractor | Owner-Builder | , |
Engineer | Berkoz, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Engineer | Smith, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
JEFFREY FULTON, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 4/11/2018 | Approved | ERNESTO CORRAL |
Deputy Reinf. Concrete | 4/26/2018 | Conditional Approval | ERNESTO CORRAL |
Footing/Foundation/Slab | 4/30/2018 | Partial Approval | ERNESTO CORRAL |
Deputy Reinf. Concrete | 5/25/2018 | Conditional Approval | NICK DANERI |
Deputy Reinf. Concrete | 5/29/2018 | Conditional Approval | ERNESTO CORRAL |
Reinforced Concrete Frame | 6/1/2018 | Partial Inspection | ERNESTO CORRAL |
Footing/Foundation/Slab | 6/6/2018 | Partial Approval | FELIX CEBALLOS |
Deputy Shotcrete | 6/14/2018 | Conditional Approval | LARRY ARNICK |
Deputy Shotcrete | 6/15/2018 | Conditional Approval | LARRY ARNICK |
Deputy Reinf. Masonry | 6/25/2018 | Conditional Approval | LARRY ARNICK |
Deputy Reinf. Masonry | 6/26/2018 | Conditional Approval | ERNESTO CORRAL |
Deputy Reinf. Masonry | 6/27/2018 | Conditional Approval | ERNESTO CORRAL |
Deputy Reinf. Masonry | 6/28/2018 | Conditional Approval | ERNESTO CORRAL |
Deputy Reinf. Masonry | 6/29/2018 | Conditional Approval | ERNESTO CORRAL |
Deputy Reinf. Masonry | 7/3/2018 | Conditional Approval | ERNESTO CORRAL |
Deputy Reinf. Masonry | 7/5/2018 | Conditional Approval | DAVID TSAU |
Deputy Reinf. Masonry | 7/10/2018 | Conditional Approval | ERNESTO CORRAL |
Reinforced Masonry Frame | 7/12/2018 | Partial Inspection | ERNESTO CORRAL |
Footing/Foundation/Slab | 8/31/2018 | Partial Approval | ERNESTO CORRAL |
Pre-Inspection | 10/15/2018 | Partial Inspection | LESLIE TRUJILLO |
Excavation/Setback/Form/Re-Bar | 10/30/2018 | Not Ready for Inspection | JAMES POWERS |
Footing/Foundation/Slab | 10/30/2018 | Not Ready for Inspection | JAMES POWERS |
Footing/Foundation/Slab | 11/1/2018 | Partial Approval | JAMES POWERS |
Reinforced Concrete Frame | 11/1/2018 | Partial Approval | JAMES POWERS |
Deputy Wood Construction | 12/24/2018 | Conditional Approval | ERNESTO CORRAL |
Floor/Roof Diaphrgm/Shear Wall | 12/24/2018 | Partial Inspection | ERNESTO CORRAL |
Green Building Rough | 12/26/2018 | Approved | ERNESTO CORRAL |
Verify Sprinkler Sign Off | 12/26/2018 | Not Ready for Inspection | ERNESTO CORRAL |
Wood Frame | 12/26/2018 | Partial Inspection | ERNESTO CORRAL |
Footing/Foundation/Slab | 2/25/2019 | No Access for Inspection | ERNESTO CORRAL |
Floor/Roof Diaphrgm/Shear Wall | 4/12/2019 | Approved | ERNESTO CORRAL |
Pre-Inspection | 4/12/2019 | Approved | ERNESTO CORRAL |
Verify Sprinkler Sign Off | 4/12/2019 | Approved | ERNESTO CORRAL |
Wood Frame | 4/12/2019 | Partial Inspection | ERNESTO CORRAL |
Pre-Inspection | 5/2/2019 | Approved | ERNESTO CORRAL |
Wood Frame | 5/6/2019 | Partial Inspection | ERNESTO CORRAL |
Floor/Roof Diaphrgm/Shear Wall | 5/15/2019 | Partial Inspection | ERNESTO CORRAL |
Interior/Exterior Lathing | 7/3/2019 | Partial Inspection | ERNESTO CORRAL |
Interior/Exterior Lathing | 8/19/2019 | Approved | ERNESTO CORRAL |
Interior/Exterior Lathing | 8/21/2019 | Approved | JEFFREY FULTON |
Insulation | 9/16/2019 | Not Ready for Inspection | ERNESTO CORRAL |
Wood Frame | 10/25/2019 | No Access for Inspection | JEFFREY FULTON |
Wood Frame | 11/1/2019 | Approved | JAMES POWERS |
Insulation | 11/7/2019 | Partial Inspection | ERNESTO CORRAL |
Insulation | 11/12/2019 | Partial Inspection | ERNESTO CORRAL |
Insulation | 11/13/2019 | Approved | JEFFREY FULTON |
Drywall Nailing | 11/20/2019 | Partial Approval | DANIEL COLLINS |
Drywall Nailing | 11/26/2019 | Approved | DANIEL COLLINS |
Pre-Inspection | 7/20/2020 | Partial Inspection | NICK DANERI |
Pre-Inspection | 8/7/2020 | Not Ready for Inspection | KATY RAMIREZ |
Special/Order Compliance | 10/20/2020 | Partial Inspection | KATY RAMIREZ |
Final | 11/17/2020 | Partial Inspection | DANIEL COLLINS |
Footing/Foundation/Slab | 11/17/2020 | Approved | DANIEL COLLINS |
Green Building Final | 11/17/2020 | Not Ready for Inspection | DANIEL COLLINS |
Reinforced Concrete Frame | 11/17/2020 | Approved | DANIEL COLLINS |
Reinforced Masonry Frame | 11/17/2020 | Not Ready for Inspection | DANIEL COLLINS |
SGSOV-Seismic Gas S/O Valve | 11/17/2020 | SGSOV Approved | DANIEL COLLINS |
Smoke Detectors | 11/17/2020 | Approved | DANIEL COLLINS |
Excavation/Setback/Form/Re-Bar | 11/23/2020 | Partial Approval | NICK DANERI |
Final | 12/15/2020 | Not Ready for Inspection | NICK DANERI |
Green Building Final | 12/15/2020 | Not Ready for Inspection | NICK DANERI |
Reinforced Masonry Frame | 12/15/2020 | Approved | NICK DANERI |
Footing/Foundation/Slab | 12/18/2020 | Approved | DANIEL COLLINS |
Green Building Final | 12/18/2020 | Not Ready for Inspection | DANIEL COLLINS |
Green Building Final | 12/23/2020 | Approved | DANIEL COLLINS |
Reinforced Concrete Frame | 12/23/2020 | Approved | DANIEL COLLINS |
Final | 12/30/2020 | Not Ready for Inspection | DANIEL COLLINS |
Final | 1/7/2021 | Partial Approval | DANIEL COLLINS |
Final | 1/25/2021 | Partial Inspection | DANIEL COLLINS |
Final | 4/21/2021 | OK to Issue CofO | DANIEL COLLINS |