8876 W PICO BLVD 90035

Certificate Information: 8876 W PICO BLVD 90035

Application / Permit
17010-10000-01302
Plan Check / Job No.
B17LA04948
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 6 story ( 4story type III-A above 2 story type I-A), 47 affordable senior apartment with one management unit over 2 levels of public parking garage & one level of subterranean public parking.
Permit Issued
Issued on 11/22/2017
Issuing Office
Metro
Current Status
CofO Issued on 1/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2017 APPLICANT
Assigned to Plan Check Engineer 4/20/2017 GARO TELMI
Corrections Issued 4/26/2017 GARO TELMI
Quality Review Completed 5/24/2017 JOHN FRANCIA
Building Plans Picked Up 5/24/2017 APPLICANT
Applicant returned to address corrections 5/27/2017 GARO TELMI
Applicant returned to address corrections 5/28/2017 GARO TELMI
Applicant returned to address corrections 8/3/2017 GARO TELMI
Applicant returned to address corrections 8/15/2017 GARO TELMI
Applicant returned to address corrections 8/24/2017 GARO TELMI
Applicant returned to address corrections 10/18/2017 GARO TELMI
Plan Check Approved 11/17/2017 GARO TELMI
Issued 11/22/2017 LADBS
TCO Issued (Expire Date: 02-03-2021) 8/7/2020 TED RIES
CofO in Progress 11/5/2020 JEFF BYTHEWAY
Permit Finaled 1/25/2021 HENRY BAGHDASSARIAN
CofO Issued 1/25/2021 HENRY BAGHDASSARIAN
Permit Finaled 1/25/2021 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Address approval Cleared 5/30/2017 ROCHELLE DUNGCA
Highway dedication Cleared 5/30/2017 ROCHELLE DUNGCA
Eng Process Fee Ord 176,300 Cleared 6/5/2017 FATIMA GUERRA
Driveway location Cleared 7/19/2017 COLLINS ALLAN
Internal circulation Cleared 7/19/2017 COLLINS ALLAN
Encroachment in public way Cleared 7/26/2017 JACOB BIGLER
Sewer availability Cleared 8/14/2017 NAZILA NOORIFAR
Building over 3-story or 36-ft Cleared 8/18/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 8/18/2017 CALOSHA APPROVED
Miscellaneous Cleared 8/18/2017 GARO TELMI
Permit Cleared 8/21/2017 ARMENIA AGUILAR
Site Plan review Cleared 8/28/2017 SARAH GOLDMAN
Hydrant and Access approval Cleared 8/29/2017 ROBERT DUFF
Green Code Cleared 9/21/2017 DONALD CRICHLOW
Low Impact Development Cleared 10/5/2017 IDA MEISAMI-FARD
DAS Clearance Cleared 10/13/2017 GARO TELMI
Construction near power lines Cleared 10/16/2017 WALTER RAMIREZ
Fire Marshall Fire Life Safety Cleared 10/17/2017 MENOA AGHAJANI
Roof/Waste drainage to street Cleared 10/17/2017 ARMENIA AGUILAR
DCP conditions approval Cleared 11/9/2017 NICHOLAS KAWAZOE
Housing density bonus Cleared 11/9/2017 NICHOLAS KAWAZOE
Methane Ordinance Cleared 11/17/2017 PEJMAN NOORI
Work Adjacent to Public Way Cleared 11/17/2017 CHIU TAM
CPC Cleared 11/20/2017 ERIC CLAROS
Miscellaneous Cleared 11/20/2017 ERIC CLAROS
Opn space landscape/Water mgmt Cleared 11/20/2017 ERIC CLAROS
Tract Map conditions Cleared 11/20/2017 IVORY CHAMBESHI

Contact Information

Architect Bornstein, Lise Michelle; Lic. No.: C30835 1625 OLYMPIC BLVD      SANTA MONICA, CA 90404
Engineer Berliner, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Cefali, David Allen; Lic. No.: S3658 4344 LAUREL CANYON BLVD_STE 3      STUDIO CITY, CA 91604
Engineer Conaway, Johnny Ray; Lic. No.: C19689 PO BOX 155      OAK VIEW, CA 93022
Engineer Ghodsi, Afshin; Lic. No.: S3248 3621 HARBOR BL 125      SANTA ANA, CA 92704
Engineer Luong, John Tuan; Lic. No.: C65214 8171 INGRAM CIR      WESTMINSTER, CA 92683
Engineer Voorheis, Jeff Stuart; Lic. No.: L7570 17049 SUNBURST ST      NORTHRIDGE, CA 91325

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 7/2/2018 Approved TONY HARTONO
Pre-Inspection 7/2/2018 Partial Inspection TONY HARTONO
Special/Order Compliance 7/3/2018 Approved JASON BORUTA
METHANE-Subgrade 7/30/2018 Not Ready for Inspection JASON BORUTA
Pre-Inspection 7/30/2018 Approved JASON BORUTA
Deputy Shotcrete 8/15/2018 Approved JASON BORUTA
Pre-Inspection 8/15/2018 Approved JASON BORUTA
METHANE-Barrier 8/24/2018 Not Ready for Inspection JASON BORUTA
Footing/Foundation/Slab 8/27/2018 Partial Approval JASON BORUTA
METHANE-Subgrade 8/27/2018 Partial Approval JASON BORUTA
Deputy Methane Barrier 8/28/2018 Conditional Approval JASON BORUTA
Deputy Reinf. Concrete 8/28/2018 Conditional Approval JASON BORUTA
Deputy Methane Barrier 8/29/2018 Conditional Approval TONY HARTONO
Deputy Methane Barrier 8/30/2018 Approved JASON BORUTA
Deputy Methane Barrier 8/31/2018 Conditional Approval JASON BORUTA
Deputy Methane Barrier 9/4/2018 Conditional Approval JASON BORUTA
Deputy Methane Barrier 9/5/2018 Conditional Approval JASON BORUTA
Deputy Methane Barrier 9/6/2018 Approved JASON BORUTA
Deputy Steel/Welding 9/6/2018 Conditional Approval JASON BORUTA
Deputy Methane Barrier 9/7/2018 Conditional Approval JASON BORUTA
METHANE-Barrier 9/14/2018 Partial Approval JASON BORUTA
METHANE-Final 9/18/2018 Approved JASON BORUTA
Excavation/Setback/Form/Re-Bar 9/20/2018 Not Ready for Inspection JASON BORUTA
Pre-Inspection 9/20/2018 Not Ready for Inspection JASON BORUTA
Excavation/Setback/Form/Re-Bar 9/27/2018 Partial Inspection TONY HARTONO
Footing/Foundation/Slab 9/27/2018 Partial Inspection TONY HARTONO
METHANE-Barrier 9/27/2018 Partial Approval TONY HARTONO
METHANE-Subgrade 9/27/2018 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 10/11/2018 Not Ready for Inspection JASON BORUTA
Footing/Foundation/Slab 10/12/2018 Partial Approval JASON BORUTA
METHANE-Barrier 10/12/2018 Approved JASON BORUTA
Deputy Shotcrete 10/19/2018 Approved TONY HARTONO
Deputy Shotcrete 10/22/2018 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 10/22/2018 Corrections Issued TONY HARTONO
Green Building Rough 10/22/2018 Not Ready for Inspection TONY HARTONO
Reinforced Concrete Frame 10/22/2018 Partial Inspection TONY HARTONO
Verify Sprinkler Sign Off 10/22/2018 Not Ready for Inspection TONY HARTONO
Deputy Shotcrete 10/23/2018 Approved DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/23/2018 Partial Approval DANIEL MC AULIFFE
Deputy Shotcrete 10/24/2018 Conditional Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 10/24/2018 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Shotcrete 10/25/2018 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 10/25/2018 Partial Approval TONY HARTONO
Deputy Shotcrete 10/26/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 10/29/2018 Conditional Approval TONY HARTONO
Deputy Shotcrete 10/29/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 10/30/2018 Conditional Approval TONY HARTONO
Deputy Reinf. Concrete 10/30/2018 No Access for Inspection TONY HARTONO
Deputy Shotcrete 10/30/2018 No Access for Inspection TONY HARTONO
Excavation/Setback/Form/Re-Bar 10/30/2018 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 10/31/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 10/31/2018 No Access for Inspection TONY HARTONO
Deputy Shotcrete 10/31/2018 No Access for Inspection TONY HARTONO
Deputy Reinf. Concrete 11/1/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 11/1/2018 No Access for Inspection TONY HARTONO
Deputy Shotcrete 11/1/2018 Approved TONY HARTONO
Deputy Shotcrete 11/1/2018 No Access for Inspection TONY HARTONO
Deputy Reinf. Concrete 11/2/2018 Approved TONY HARTONO
Deputy Shotcrete 11/2/2018 Approved TONY HARTONO
Deputy Shotcrete 11/2/2018 No Access for Inspection TONY HARTONO
Deputy Reinf. Concrete 11/8/2018 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 11/8/2018 Partial Approval TONY HARTONO
Excavation/Setback/Form/Re-Bar 11/9/2018 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 11/27/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 11/28/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 11/30/2018 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 11/30/2018 Partial Inspection TONY HARTONO
Deputy Reinf. Concrete 12/7/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 12/10/2018 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 12/10/2018 Partial Approval TONY HARTONO
Footing/Foundation/Slab 12/10/2018 Not Ready for Inspection TONY HARTONO
Deputy Reinf. Concrete 12/13/2018 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 12/13/2018 Partial Approval TONY HARTONO
Deputy Shotcrete 12/14/2018 Approved TONY HARTONO
Deputy Reinf. Masonry 12/17/2018 Conditional Approval JASON BORUTA
Green Building Rough 12/17/2018 Approved JASON BORUTA
Reinforced Masonry Frame 12/17/2018 Partial Approval JASON BORUTA
Verify Sprinkler Sign Off 12/17/2018 Not Ready for Inspection JASON BORUTA
Deputy Reinf. Concrete 12/18/2018 Approved TONY HARTONO
Deputy Shotcrete 12/18/2018 Approved TONY HARTONO
Reinforced Masonry Frame 12/18/2018 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 12/19/2018 Approved TONY HARTONO
Deputy Reinf. Masonry 12/19/2018 Approved TONY HARTONO
Deputy Shotcrete 12/19/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 12/20/2018 Approved TONY HARTONO
Deputy Reinf. Masonry 12/20/2018 Approved TONY HARTONO
Deputy Shotcrete 12/20/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 12/21/2018 Approved TONY HARTONO
Deputy Reinf. Masonry 12/21/2018 Approved TONY HARTONO
Deputy Shotcrete 12/21/2018 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 12/21/2018 Partial Approval TONY HARTONO
Masonry Wall/Backfill 12/21/2018 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 12/24/2018 Approved TONY HARTONO
Deputy Shotcrete 12/24/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 12/27/2018 Conditional Approval TONY HARTONO
Deputy Shotcrete 12/27/2018 Approved TONY HARTONO
Deputy Reinf. Concrete 12/28/2018 Conditional Approval TONY HARTONO
Special/Order Compliance 12/31/2018 No Access for Inspection TONY HARTONO
Deputy Reinf. Concrete 1/11/2019 Approved TONY HARTONO
Deputy Reinf. Concrete 1/14/2019 Conditional Approval TONY HARTONO
Deputy Reinf. Concrete 1/15/2019 No Access for Inspection TONY HARTONO
Deputy Reinf. Concrete 1/16/2019 No Access for Inspection TONY HARTONO
Deputy Reinf. Concrete 1/17/2019 Conditional Approval TONY HARTONO
Deputy Reinf. Concrete 1/22/2019 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 1/22/2019 Conditional Approval TONY HARTONO
Deputy Reinf. Concrete 1/23/2019 Approved TONY HARTONO
Pre-Inspection 1/24/2019 Partial Approval TONY HARTONO
Excavation/Setback/Form/Re-Bar 1/28/2019 Partial Approval TONY HARTONO
Masonry Wall/Backfill 1/28/2019 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 1/29/2019 Approved TONY HARTONO
Deputy Shotcrete 1/29/2019 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 1/29/2019 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 1/30/2019 Approved TONY HARTONO
Deputy Reinf. Masonry 1/30/2019 Approved TONY HARTONO
Deputy Shotcrete 1/30/2019 Approved TONY HARTONO
Deputy Reinf. Concrete 1/31/2019 No Access for Inspection TONY HARTONO
Deputy Reinf. Masonry 1/31/2019 No Access for Inspection TONY HARTONO
Deputy Shotcrete 1/31/2019 No Access for Inspection TONY HARTONO
Deputy Reinf. Concrete 2/1/2019 Approved TONY HARTONO
Deputy Reinf. Masonry 2/1/2019 Approved TONY HARTONO
Deputy Shotcrete 2/1/2019 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 2/1/2019 Partial Approval TONY HARTONO
Deputy Shotcrete 2/8/2019 Approved TONY HARTONO
Masonry Wall/Backfill 2/13/2019 Partial Approval TONY HARTONO
Excavation/Setback/Form/Re-Bar 2/19/2019 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 2/27/2019 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 2/28/2019 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/4/2019 Partial Inspection TONY HARTONO
Deputy Drilled-In Anchors 3/6/2019 Approved TONY HARTONO
Deputy Other (see comments) 3/6/2019 Approved TONY HARTONO
Deputy Reinf. Concrete 3/6/2019 Approved TONY HARTONO
Deputy Shotcrete 3/6/2019 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 3/6/2019 Partial Approval TONY HARTONO
Deputy Drilled-In Anchors 3/7/2019 Approved TONY HARTONO
Deputy Other (see comments) 3/7/2019 Approved TONY HARTONO
Deputy Reinf. Concrete 3/7/2019 Approved TONY HARTONO
Deputy Shotcrete 3/7/2019 Approved TONY HARTONO
Deputy Drilled-In Anchors 3/8/2019 Approved TONY HARTONO
Deputy Other (see comments) 3/8/2019 Approved TONY HARTONO
Deputy Reinf. Concrete 3/8/2019 Approved TONY HARTONO
Deputy Shotcrete 3/8/2019 Approved TONY HARTONO
Deputy Drilled-In Anchors 3/11/2019 Conditional Approval JASON BORUTA
Deputy Other (see comments) 3/11/2019 Conditional Approval JASON BORUTA
Deputy Reinf. Concrete 3/11/2019 Conditional Approval JASON BORUTA
Deputy Shotcrete 3/11/2019 Conditional Approval JASON BORUTA
Deputy Drilled-In Anchors 3/12/2019 Approved DERRICK SPENCER
Deputy Other (see comments) 3/12/2019 Approved DERRICK SPENCER
Deputy Reinf. Concrete 3/12/2019 Approved DERRICK SPENCER
Deputy Shotcrete 3/12/2019 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/12/2019 Not Ready for Inspection DERRICK SPENCER
Reinforced Masonry Frame 3/12/2019 Partial Approval DERRICK SPENCER
Verify Sprinkler Sign Off 3/12/2019 Approved DERRICK SPENCER
Deputy Reinf. Masonry 3/13/2019 Approved DERRICK SPENCER
Deputy Reinf. Masonry 3/14/2019 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/14/2019 Partial Approval DERRICK SPENCER
Deputy Reinf. Masonry 3/15/2019 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/15/2019 Not Ready for Inspection DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/18/2019 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 4/5/2019 Partial Approval TONY HARTONO
Excavation/Setback/Form/Re-Bar 4/10/2019 Partial Approval TONY HARTONO
Deputy Reinf. Concrete 4/12/2019 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 4/15/2019 Partial Inspection TONY HARTONO
Deputy Reinf. Concrete 4/23/2019 Approved TONY HARTONO
Deputy Reinf. Concrete 4/24/2019 Approved TONY HARTONO
Excavation/Setback/Form/Re-Bar 4/24/2019 Conditional Approval TONY HARTONO
Excavation/Setback/Form/Re-Bar 4/26/2019 Corrections Issued TONY HARTONO
Pre-Inspection 5/8/2019 Approved DERRICK SPENCER
Deputy Wood Construction 5/29/2019 Approved TONY HARTONO
Deputy Wood Construction 5/30/2019 Approved TONY HARTONO
Floor/Roof Diaphrgm/Shear Wall 5/30/2019 Partial Inspection TONY HARTONO
Deputy Wood Construction 5/31/2019 Approved TONY HARTONO
Floor/Roof Diaphrgm/Shear Wall 5/31/2019 Partial Approval TONY HARTONO
Drywall Nailing 6/4/2019 Partial Approval TONY HARTONO
Excavation/Setback/Form/Re-Bar 6/11/2019 Partial Approval TONY HARTONO
Masonry Wall/Backfill 6/11/2019 Partial Approval TONY HARTONO
Masonry Wall/Backfill 6/14/2019 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 6/20/2019 Partial Approval TONY HARTONO
Drywall Nailing 6/24/2019 Partial Approval DERRICK SPENCER
Deputy Wood Construction 7/9/2019 Approved TONY HARTONO
Floor/Roof Diaphrgm/Shear Wall 7/9/2019 Partial Approval TONY HARTONO
Drywall Nailing 7/12/2019 Partial Approval NICK LAROCCA
Floor/Roof Diaphrgm/Shear Wall 7/19/2019 Partial Approval TONY HARTONO
Insulation 7/19/2019 Partial Inspection TONY HARTONO
Pre-Inspection 7/19/2019 Partial Inspection TONY HARTONO
Insulation 7/22/2019 Partial Approval TONY HARTONO
Drywall Nailing 7/24/2019 Not Ready for Inspection TONY HARTONO
Floor/Roof Diaphrgm/Shear Wall 7/29/2019 Partial Approval TONY HARTONO
Deputy Wood Construction 7/31/2019 Approved TONY HARTONO
Floor/Roof Diaphrgm/Shear Wall 8/1/2019 Partial Inspection TONY HARTONO
Drywall Nailing 8/2/2019 Partial Inspection TONY HARTONO
Deputy Wood Construction 8/6/2019 Approved TONY HARTONO
Deputy Wood Construction 8/7/2019 Approved TONY HARTONO
Deputy Wood Construction 8/8/2019 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 8/8/2019 Partial Approval DERRICK SPENCER
Special/Order Compliance 8/13/2019 Corrections Issued TONY HARTONO
Drywall Nailing 8/16/2019 Partial Approval TONY HARTONO
Drywall Nailing 8/19/2019 Partial Approval DERRICK SPENCER
Wood Frame 9/16/2019 Partial Inspection TONY HARTONO
Insulation 9/18/2019 Partial Approval DERRICK SPENCER
Deputy Wood Construction 9/19/2019 Conditional Approval TONY HARTONO
Insulation 9/20/2019 Partial Approval TONY HARTONO
Insulation 10/2/2019 Partial Approval TONY HARTONO
Insulation 10/4/2019 Partial Approval TONY HARTONO
Light Gage Steel Frame 10/8/2019 Partial Approval TONY HARTONO
Interior/Exterior Lathing 10/11/2019 Partial Approval TONY HARTONO
Light Gage Steel Frame 10/24/2019 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 10/28/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 10/29/2019 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 11/6/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 11/8/2019 Partial Approval TED RIES
Interior/Exterior Lathing 11/22/2019 Partial Approval JEFF BYTHEWAY
Light Gage Steel Frame 11/22/2019 Not Ready for Inspection JEFF BYTHEWAY
Light Gage Steel Frame 11/26/2019 Partial Approval TED RIES
Deputy Steel/Welding 1/27/2020 Approved JEFF BYTHEWAY
Deputy Steel/Welding 1/28/2020 Approved JEFF BYTHEWAY
Special/Order Compliance 2/13/2020 Corrections Issued JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 2/18/2020 Approved JEFF BYTHEWAY
Masonry Wall/Backfill 2/18/2020 Approved JEFF BYTHEWAY
Deputy Steel/Welding 2/26/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 3/18/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 3/19/2020 Approved JEFF BYTHEWAY
Masonry Wall/Backfill 3/19/2020 Not Ready for Inspection JEFF BYTHEWAY
Deputy Reinf. Masonry 3/20/2020 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 3/20/2020 Partial Approval JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 3/27/2020 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 3/31/2020 Partial Approval JEFF BYTHEWAY
Wood Frame 3/31/2020 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 4/8/2020 Partial Approval JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 4/10/2020 Partial Approval JEFF BYTHEWAY
Interior/Exterior Lathing 4/21/2020 Corrections Issued DERRICK SPENCER
Light Gage Steel Frame 4/21/2020 Partial Approval DERRICK SPENCER
Drywall Nailing 4/27/2020 Not Ready for Inspection JEFF BYTHEWAY
Interior/Exterior Lathing 4/27/2020 Partial Approval JEFF BYTHEWAY
Drywall Nailing 4/28/2020 Partial Approval JEFF BYTHEWAY
Special/Order Compliance 5/28/2020 Partial Inspection JEFF BYTHEWAY
Light Gage Steel Frame 6/9/2020 Not Ready for Inspection JEFF BYTHEWAY
Special/Order Compliance 6/9/2020 Not Ready for Inspection JEFF BYTHEWAY
Final 6/10/2020 Not Ready for Inspection JEFF BYTHEWAY
Footing/Foundation/Slab 6/10/2020 Approved JEFF BYTHEWAY
Green Building Final 6/10/2020 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 6/10/2020 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 6/10/2020 Approved JEFF BYTHEWAY
SGSOV-Seismic Gas S/O Valve 6/10/2020 SGSOV Approved JEFF BYTHEWAY
Smoke Detectors 6/10/2020 Approved JEFF BYTHEWAY
Special/Order Compliance 6/10/2020 Approved JEFF BYTHEWAY
Green Building Final 6/12/2020 Approved JEFF BYTHEWAY
Final 6/30/2020 Partial Approval JEFF BYTHEWAY
Final 7/7/2020 Partial Approval JEFF BYTHEWAY
Final 7/15/2020 Partial Inspection JEFF BYTHEWAY
Final 7/17/2020 Conditional Approval JEFF BYTHEWAY
Pre-Inspection 7/29/2020 Partial Inspection JEFF BYTHEWAY
Final 8/5/2020 OK for TCO JEFF BYTHEWAY
Final 11/4/2020 OK to Issue CofO JEFF BYTHEWAY
Special/Order Compliance 5/19/2021 Approved NICK LAROCCA