10909 W OTSEGO ST 91601

Certificate Information: 10909 W OTSEGO ST 91601

Application / Permit
17010-10000-01282
Plan Check / Job No.
B17LA04771
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONSTRUCT 1 NEW 3 STORY SFD w/ ATT. GARAGE and ROOF DECK. Fully sprinkler, NFPA-13D. 20 HOME SMALL LOTSUBDIVISON
Permit Issued
Issued on 3/8/2018
Issuing Office
Metro
Current Status
CofO Issued on 6/4/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2017 APPLICANT
Assigned to Plan Check Engineer 4/13/2017 SAM CHANG
Green Plans Picked Up 4/18/2017 APPLICANT
Corrections Issued 5/1/2017 SAM CHANG
Quality Review Completed 5/9/2017 SUEN LIEU
Building Plans Picked Up 5/9/2017 APPLICANT
Applicant returned to address corrections 8/24/2017 SAM CHANG
Applicant returned to address corrections 9/19/2017 SAM CHANG
Applicant returned to address corrections 9/29/2017 SAM CHANG
Applicant returned to address corrections 10/4/2017 SAM CHANG
Applicant returned to address corrections 10/13/2017 SAM CHANG
Applicant returned to address corrections 11/22/2017 SAM CHANG
Applicant returned to address corrections 12/13/2017 SAM CHANG
Applicant returned to address corrections 1/4/2018 SAM CHANG
Applicant returned to address corrections 1/9/2018 SAM CHANG
Applicant returned to address corrections 1/11/2018 SAM CHANG
Plan Check Approved 1/12/2018 SAM CHANG
Issued 3/8/2018 LADBS
CofO in Progress 6/1/2020 JOSEPH SAGEN
Permit Finaled 6/4/2020 DONALD SUNSERI
CofO Issued 6/4/2020 DONALD SUNSERI
Permit Finaled 6/4/2020 DONALD SUNSERI

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 5/15/2017 SARAH GOLDMAN
Eng Process Fee Ord 176,300 Cleared 6/6/2017 CELINA MORENO
Address approval Cleared 6/19/2017 CELINA MORENO
Sewer availability Cleared 7/10/2017 HISASHI KOBAYAKAWA
"Q" conditions Cleared 8/25/2017 FIPE LEILUA
Miscellaneous Cleared 8/25/2017 FIPE LEILUA
Highway dedication Cleared 10/19/2017 LEE GUILBEAUX
Permit Cleared 10/19/2017 LEE GUILBEAUX
Green Code Cleared 11/14/2017 WILLIAM ROSE
Low Impact Development Cleared 12/7/2017 RYAN HUDSON
Miscellaneous Cleared 12/14/2017 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/14/2017 LEE GUILBEAUX
Building over 3-story or 36-ft Cleared 1/4/2018 CALOSHA APPROVED
Hydrant and Access approval Cleared 1/8/2018 JOHN DALLAS

Contact Information

Architect Leavitt, Derek Chase; Lic. No.: C31212 425 MARINE STREET # 6      SANTA MONICA, CA 90405
Contractor Warmington Residential California Inc; Lic. No.: 852282-B 3090 PULLMAN STREET      COSTA MESA, CA 92626
Engineer Nguyen, Huan Ngoc; Lic. No.: C64238 7015 PINNACLE POINTE      ORANGE, CA 92869
Geologist Kirkgard, Susan Franzen; Lic. No.: EG1754 1481 STONEBROOK STREET      AZUSA, CA 91702

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/4/2018 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 6/12/2018 Partial Approval DONALD SUNSERI
Footing/Foundation/Slab 7/13/2018 Approved JOHN KIDWELL
Underground Mechanical 8/24/2018 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 10/3/2018 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 10/10/2018 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 10/19/2018 Partial Approval DONALD SUNSERI
Drywall Nailing 11/7/2018 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 11/14/2018 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/5/2018 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/13/2018 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/18/2018 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/3/2019 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/28/2019 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/13/2019 Partial Approval DONALD SUNSERI
ELECTRICAL-Rough 3/29/2019 Approved DONALD SUNSERI
PLUMBING-Rough 3/29/2019 Approved DONALD SUNSERI
ELECTRICAL-Rough 4/25/2019 Approved DONALD SUNSERI
PLUMBING-Rough 4/25/2019 Approved DONALD SUNSERI
BUILDING-Rough-Frame 4/26/2019 Not Ready for Inspection DONALD SUNSERI
Green Building Rough 4/26/2019 Approved DONALD SUNSERI
HVAC-Rough 4/26/2019 Not Ready for Inspection DONALD SUNSERI
Verify Sprinkler Sign Off 4/26/2019 Approved DONALD SUNSERI
BUILDING-Rough-Frame 5/1/2019 Not Ready for Inspection DONALD SUNSERI
BUILDING-Rough-Frame 5/2/2019 Approved DONALD SUNSERI
Drywall Nailing 5/10/2019 Approved DONALD SUNSERI
Interior/Exterior Lathing 5/10/2019 Approved DONALD SUNSERI
Gas Test 7/18/2019 Not Ready for Inspection JOSEPH SAGEN
Gas Test 10/10/2019 Approved JOSEPH SAGEN
Underground Mechanical 10/10/2019 Partial Approval JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 10/24/2019 SGSOV Approved JOSEPH SAGEN
ELECTRICAL-Final 12/5/2019 Not Ready for Inspection JOSEPH SAGEN
HVAC-Final 12/5/2019 Approved JOSEPH SAGEN
PLUMBING-Final 12/5/2019 Approved JOSEPH SAGEN
ELECTRICAL-Final 12/17/2019 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Final 2/13/2020 Approved JOSEPH SAGEN
Service/Power Release 2/28/2020 Approved JOSEPH SAGEN
Final 4/15/2020 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 4/15/2020 Approved JOSEPH SAGEN
Smoke Detectors 4/15/2020 Approved JOSEPH SAGEN
Final 5/29/2020 OK to Issue CofO JOSEPH SAGEN