2825-2827 S SYCAMORE AVE 90016
Certificate Information: 2825-2827 S SYCAMORE AVE 90016
- Application / Permit
- 17010-10000-01243
- Plan Check / Job No.
- B17LA04624
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW TWO STORY DUPLEX .
- Permit Issued
- Issued on 1/25/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2017 | APPLICANT |
| Green Plans Picked Up | 4/12/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2017 | GEORGE BANNING |
| Corrections Issued | 4/20/2017 | GEORGE BANNING |
| Quality Review Completed | 4/24/2017 | CHARLES CHANG |
| Applicant returned to address corrections | 6/21/2017 | GEORGE BANNING |
| Plan Check Approved | 1/25/2018 | GEORGE BANNING |
| Issued | 1/25/2018 | LADBS |
| CofO in Progress | 12/12/2020 | DAVID CHAN |
| Permit Finaled | 5/19/2021 | DEROLD HAUFF |
| CofO Issued | 5/19/2021 | DEROLD HAUFF |
| Permit Finaled | 5/19/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2017 | ALFREDO JARA |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2017 | ALFREDO JARA |
| Permit | Cleared | 6/12/2017 | ALFREDO JARA |
| Sewer availability | Cleared | 6/12/2017 | ALFREDO JARA |
| ZI | Cleared | 6/12/2017 | EDBER MACEDO |
| Housing rent stabilization | Cleared | 6/14/2017 | DANIEL WILLIAMS |
| Green Code | Cleared | 8/4/2017 | JOHN KLARIN |
| Frnt yard landscape/Water mgmt | Cleared | 12/18/2017 | JESSE RAMOS |
| Low Impact Development | Cleared | 1/23/2018 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 1/25/2018 | CARLA VALLADARES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo, Margarito; Lic. No.: S4808 | 1327 LOMA AVE LONG BEACH, CA 90804 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2018 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 9/21/2018 | Not Ready for Inspection | DAVID CHAN |
| Pre-Inspection | 6/24/2019 | Approved | KATHRYN BUTTERWORTH |
| Sewer | 6/24/2019 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 7/17/2019 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 7/17/2019 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/28/2019 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 8/28/2019 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 8/28/2019 | Partial Approval | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 8/28/2019 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2019 | Partial Approval | MATTHEW NUCKOLLS |
| Insulation | 9/3/2019 | Partial Approval | MATTHEW NUCKOLLS |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2019 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 10/4/2019 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2019 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 12/27/2019 | Approved | DANIEL GONZALEZ |
| ELECTRICAL-Rough | 1/17/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Rough | 1/17/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 1/23/2020 | Corrections Issued | ELMER BLAND |
| HVAC-Rough | 1/23/2020 | Corrections Issued | ELMER BLAND |
| ELECTRICAL-Rough | 1/30/2020 | Approved | DAVID CHAN |
| HVAC-Rough | 1/30/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 2/4/2020 | Corrections Issued | DAVID CHAN |
| Green Building Rough | 2/4/2020 | Approved | DAVID CHAN |
| Verify Sprinkler Sign Off | 2/4/2020 | Approved | DAVID CHAN |
| Insulation | 2/6/2020 | Not Ready for Inspection | ELMER BLAND |
| Insulation | 2/18/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 2/18/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 2/26/2020 | Approved | DAVID CHAN |
| Shower Pan | 3/16/2020 | Approved | MATTHEW NUCKOLLS |
| Service/Power Release | 5/20/2020 | Corrections Issued | DAVID CHAN |
| Gas Test | 6/11/2020 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Final | 6/23/2020 | Approved | DAVID CHAN |
| HVAC-Final | 6/23/2020 | Not Ready for Inspection | DAVID CHAN |
| PLUMBING-Final | 6/23/2020 | Not Ready for Inspection | DAVID CHAN |
| HVAC-Final | 7/9/2020 | Approved | DAVID CHAN |
| PLUMBING-Final | 8/17/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 10/22/2020 | Approved | DAVID CHAN |
| Final | 10/22/2020 | Conditional Approval | DAVID CHAN |
| Green Building Final | 10/22/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Approved | DAVID CHAN |
| Service/Power Release | 10/22/2020 | Partial Inspection | DAVID CHAN |
| Smoke Detectors | 10/22/2020 | Approved | DAVID CHAN |
| Final | 11/12/2020 | OK to Issue CofO | DAVID CHAN |
| Service/Power Release | 11/12/2020 | Approved | DAVID CHAN |