2825-2827 S SYCAMORE AVE 90016

Certificate Information: 2825-2827 S SYCAMORE AVE 90016

Application / Permit
17010-10000-01243
Plan Check / Job No.
B17LA04624
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW TWO STORY DUPLEX .
Permit Issued
Issued on 1/25/2018
Issuing Office
Metro
Current Status
CofO Issued on 5/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2017 APPLICANT
Green Plans Picked Up 4/12/2017 APPLICANT
Assigned to Plan Check Engineer 4/13/2017 GEORGE BANNING
Corrections Issued 4/20/2017 GEORGE BANNING
Quality Review Completed 4/24/2017 CHARLES CHANG
Applicant returned to address corrections 6/21/2017 GEORGE BANNING
Plan Check Approved 1/25/2018 GEORGE BANNING
Issued 1/25/2018 LADBS
CofO in Progress 12/12/2020 DAVID CHAN
Permit Finaled 5/19/2021 DEROLD HAUFF
CofO Issued 5/19/2021 DEROLD HAUFF
Permit Finaled 5/19/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/12/2017 ALFREDO JARA
Eng Process Fee Ord 176,300 Cleared 6/12/2017 ALFREDO JARA
Permit Cleared 6/12/2017 ALFREDO JARA
Sewer availability Cleared 6/12/2017 ALFREDO JARA
ZI Cleared 6/12/2017 EDBER MACEDO
Housing rent stabilization Cleared 6/14/2017 DANIEL WILLIAMS
Green Code Cleared 8/4/2017 JOHN KLARIN
Frnt yard landscape/Water mgmt Cleared 12/18/2017 JESSE RAMOS
Low Impact Development Cleared 1/23/2018 SAM NAVID
Roof/Waste drainage to street Cleared 1/25/2018 CARLA VALLADARES

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo, Margarito; Lic. No.: S4808 1327 LOMA AVE      LONG BEACH, CA 90804

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/19/2018 Corrections Issued KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 9/21/2018 Not Ready for Inspection DAVID CHAN
Pre-Inspection 6/24/2019 Approved KATHRYN BUTTERWORTH
Sewer 6/24/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 7/17/2019 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 7/17/2019 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/28/2019 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 8/28/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 8/28/2019 Partial Approval KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 8/28/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 9/3/2019 Partial Approval MATTHEW NUCKOLLS
Insulation 9/3/2019 Partial Approval MATTHEW NUCKOLLS
Floor/Roof Diaphrgm/Shear Wall 9/10/2019 Partial Approval KATHRYN BUTTERWORTH
Deputy Wood Construction 10/4/2019 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 10/7/2019 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 12/27/2019 Approved DANIEL GONZALEZ
ELECTRICAL-Rough 1/17/2020 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Rough 1/17/2020 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 1/23/2020 Corrections Issued ELMER BLAND
HVAC-Rough 1/23/2020 Corrections Issued ELMER BLAND
ELECTRICAL-Rough 1/30/2020 Approved DAVID CHAN
HVAC-Rough 1/30/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 2/4/2020 Corrections Issued DAVID CHAN
Green Building Rough 2/4/2020 Approved DAVID CHAN
Verify Sprinkler Sign Off 2/4/2020 Approved DAVID CHAN
Insulation 2/6/2020 Not Ready for Inspection ELMER BLAND
Insulation 2/18/2020 Approved DAVID CHAN
Interior/Exterior Lathing 2/18/2020 Approved DAVID CHAN
Drywall Nailing 2/26/2020 Approved DAVID CHAN
Shower Pan 3/16/2020 Approved MATTHEW NUCKOLLS
Service/Power Release 5/20/2020 Corrections Issued DAVID CHAN
Gas Test 6/11/2020 Partial Approval SABAS ALONSO
ELECTRICAL-Final 6/23/2020 Approved DAVID CHAN
HVAC-Final 6/23/2020 Not Ready for Inspection DAVID CHAN
PLUMBING-Final 6/23/2020 Not Ready for Inspection DAVID CHAN
HVAC-Final 7/9/2020 Approved DAVID CHAN
PLUMBING-Final 8/17/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 10/22/2020 Approved DAVID CHAN
Final 10/22/2020 Conditional Approval DAVID CHAN
Green Building Final 10/22/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 10/22/2020 SGSOV Approved DAVID CHAN
Service/Power Release 10/22/2020 Partial Inspection DAVID CHAN
Smoke Detectors 10/22/2020 Approved DAVID CHAN
Final 11/12/2020 OK to Issue CofO DAVID CHAN
Service/Power Release 11/12/2020 Approved DAVID CHAN