2704 1/4 W AVENUE 33 90065

Certificate Information: 2704 1/4 W AVENUE 33 90065

Application / Permit
17010-10000-01210
Plan Check / Job No.
B17LA04388
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SMALL LOT SUBDIVISION PURSUANT TO PARCEL MAP VTT-73674-SL. PARCEL 5: NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ROOF DECK. A CERTIFICATE OF OCCUPANCY (TEMP OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
Permit Issued
Issued on 9/7/2017
Issuing Office
Metro
Current Status
CofO Issued on 10/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2017 APPLICANT
Assigned to Plan Check Engineer 4/13/2017 CAROLYNN NEPOMUCENO
Corrections Issued 4/26/2017 CAROLYNN NEPOMUCENO
Green Plans Picked Up 4/26/2017 APPLICANT
Quality Review Completed 4/28/2017 CHARLES CHANG
Building Plans Picked Up 5/2/2017 APPLICANT
Applicant returned to address corrections 5/31/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 6/8/2017 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 7/18/2017 CAROLYNN NEPOMUCENO
Plan Check Approved 8/1/2017 CAROLYNN NEPOMUCENO
Issued 9/7/2017 LADBS
CofO in Progress 10/20/2020 SCOTT FINNILA
Permit Finaled 10/21/2020 DEROLD HAUFF
CofO Issued 10/21/2020 DEROLD HAUFF
Permit Finaled 10/21/2020 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 6/9/2017 NOAH MCCOY
Frnt yard landscape/Water mgmt Cleared 6/20/2017 NOAH MCCOY
Address approval Cleared 6/21/2017 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 7/7/2017 ALFREDO JARA
Sewer availability Cleared 7/7/2017 ALFREDO JARA
Hydrant and Access approval Cleared 7/13/2017 JOHN CONNEALLY
GPI Written Notices Cleared 7/18/2017 CAROLYNN NAPOMUCENO
Grading Pre-Inspection Cleared 7/18/2017 CAROLYNN NAPOMUCENO
Highway dedication Cleared 7/18/2017 CARLA VALLADARES
Low Impact Development Cleared 7/18/2017 MITESH PATEL
Miscellaneous Cleared 7/19/2017 JOHN DACEY
Supp. Use District POD/CDO/TDO Cleared 7/19/2017 JOHN DACEY
Tract Map conditions Cleared 7/19/2017 JOHN DACEY
Green Code Cleared 7/28/2017 DONALD CRICHLOW
Building over 3-story or 36-ft Cleared 8/1/2017 CALOSHA APPROVED
Miscellaneous Cleared 8/1/2017 LINDA MARGARET
Permit Cleared 8/1/2017 LINDA MARGARET
Roof/Waste drainage to street Cleared 8/1/2017 LINDA MARGARET

Contact Information

Contractor L A Green Designs; Lic. No.: 988980-B P O BOX 411603      LOS ANGELES, CA 90041
Engineer Phillips, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Engineer Uhles, Scott Delane; Lic. No.: C72391 2909 ARIZONA AVE 5      SANTA MONICA, CA 90404

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/24/2019 Partial Approval SCOTT FINNILA
Underground Mechanical 4/24/2019 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 4/25/2019 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 5/22/2019 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 6/21/2019 Partial Inspection SCOTT FINNILA
Drywall Nailing 7/8/2019 Not Ready for Inspection SCOTT FINNILA
Green Building Rough 7/8/2019 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 9/5/2019 Conditional Approval MICHAEL FAUNCE
Green Building Rough 9/5/2019 Not Ready for Inspection MICHAEL FAUNCE
Footing/Foundation/Slab 9/9/2019 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/13/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 9/25/2019 Conditional Approval MICHAEL FAUNCE
Green Building Rough 9/25/2019 Not Ready for Inspection MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 10/9/2019 Not Ready for Inspection MICHAEL FAUNCE
Floor/Roof Diaphrgm/Shear Wall 10/10/2019 Conditional Approval SCOTT FINNILA
Drywall Nailing 10/18/2019 Partial Approval SCOTT FINNILA
Green Building Rough 10/18/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 10/22/2019 Partial Approval SCOTT FINNILA
Green Building Rough 10/22/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/25/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 11/4/2019 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/4/2019 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/2/2019 Partial Inspection SCOTT FINNILA
Green Building Rough 12/20/2019 Partial Approval SCOTT FINNILA
Wood Frame 1/6/2020 Partial Approval SCOTT FINNILA
Insulation 1/9/2020 Not Ready for Inspection SCOTT FINNILA
Wood Frame 1/9/2020 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/22/2020 Partial Inspection SCOTT FINNILA
Wood Frame 1/22/2020 Partial Approval SCOTT FINNILA
Verify Sprinkler Sign Off 1/31/2020 Not Ready for Inspection MICHAEL FAUNCE
Wood Frame 1/31/2020 Not Ready for Inspection MICHAEL FAUNCE
BUILDING-Rough-Frame 2/3/2020 Not Ready for Inspection MICHAEL FAUNCE
Green Building Rough 2/3/2020 Not Ready for Inspection MICHAEL FAUNCE
Wood Frame 2/3/2020 Not Ready for Inspection MICHAEL FAUNCE
Wood Frame 2/4/2020 Not Ready for Inspection BRAD BESCOS
Wood Frame 2/11/2020 Partial Approval SCOTT FINNILA
Wood Frame 2/14/2020 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Rough 2/24/2020 Not Ready for Inspection SCOTT FINNILA
HVAC-Rough 2/24/2020 Not Ready for Inspection SCOTT FINNILA
PLUMBING-Rough 2/24/2020 Not Ready for Inspection SCOTT FINNILA
Rough-Elec/Plmb/HVAC 2/26/2020 Partial Inspection SCOTT FINNILA
Insulation 3/3/2020 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 3/3/2020 Partial Inspection SCOTT FINNILA
Rough-Elec/Plmb/HVAC 3/3/2020 Conditional Approval SCOTT FINNILA
Insulation 3/5/2020 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 3/5/2020 Conditional Approval SCOTT FINNILA
Drywall Nailing 3/16/2020 Corrections Issued SCOTT FINNILA
Green Building Rough 3/16/2020 Approved SCOTT FINNILA
Drywall Nailing 3/20/2020 Partial Approval MICHAEL FAUNCE
Interior/Exterior Lathing 4/9/2020 Approved SCOTT FINNILA
Underground Mechanical 5/14/2020 Partial Approval SCOTT FINNILA
Gas Test 5/18/2020 Approved ENRIQUE MIRELES
Underground Mechanical 5/18/2020 Approved ENRIQUE MIRELES
Gas Test 5/28/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 7/6/2020 Partial Inspection SCOTT FINNILA
HVAC-Final 7/6/2020 Partial Inspection SCOTT FINNILA
PLUMBING-Final 7/6/2020 Partial Inspection SCOTT FINNILA
Gas Test 8/19/2020 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/20/2020 Approved SCOTT FINNILA
Drywall Nailing 8/20/2020 Approved SCOTT FINNILA
Final 8/20/2020 Partial Inspection SCOTT FINNILA
Green Building Final 8/20/2020 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 8/20/2020 SGSOV Approved SCOTT FINNILA
Service/Power Release 8/20/2020 Corrections Issued SCOTT FINNILA
Smoke Detectors 8/20/2020 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 8/20/2020 Approved SCOTT FINNILA
Final 8/24/2020 Corrections Issued SCOTT FINNILA
Green Building Final 8/24/2020 Approved SCOTT FINNILA
Service/Power Release 8/24/2020 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 9/1/2020 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/1/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/1/2020 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 9/1/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/4/2020 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/4/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/4/2020 Approved ALEJANDRO DE ARTOLA
Service/Power Release 9/4/2020 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 9/25/2020 Corrections Issued SCOTT FINNILA
Service/Power Release 10/6/2020 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 10/7/2020 Approved SCOTT FINNILA
Final 10/7/2020 Partial Approval SCOTT FINNILA
PLUMBING-Final 10/7/2020 Approved SCOTT FINNILA
Service/Power Release 10/7/2020 Approved SCOTT FINNILA
Final 10/20/2020 OK to Issue CofO SCOTT FINNILA
Final 10/20/2020 Partial Approval SCOTT FINNILA