1940 N LUCILE AVE 90039

Certificate Information: 1940 N LUCILE AVE 90039

Application / Permit
17010-10000-01018
Plan Check / Job No.
B17LA03610
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW CONSTRUCTION OF 2 STORY SINGLE FAMILY RESIDENCE OVER 2 LEVEL BASEMENT, fully sprinkler, NFPA-13D
Permit Issued
Issued on 5/2/2018
Issuing Office
Metro
Current Status
CofO Issued on 5/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2017 APPLICANT
Assigned to Plan Check Engineer 3/30/2017 SAM CHANG
Green Plans Picked Up 3/31/2017 APPLICANT
Corrections Issued 4/13/2017 SAM CHANG
Quality Review Completed 4/13/2017 DAVID CHANG
Building Plans Picked Up 4/17/2017 APPLICANT
Applicant returned to address corrections 12/7/2017 SAM CHANG
Applicant returned to address corrections 12/22/2017 SAM CHANG
Applicant returned to address corrections 1/12/2018 SAM CHANG
Applicant returned to address corrections 2/22/2018 SAM CHANG
Plan Check Approved 3/16/2018 SAM CHANG
Issued 5/2/2018 LADBS
CofO in Progress 3/30/2022 JOSEPH MCGARRY
Permit Finaled 5/6/2022 DEROLD HAUFF
CofO Issued 5/6/2022 DEROLD HAUFF
Permit Finaled 5/6/2022 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/26/2017 CARLA VALLADARES
BHO/Hillside ordinance Cleared 4/26/2017 CARLA VALLADARES
BHO/Hillside ordinance Cleared 4/26/2017 CARLA VALLADARES
Eng Process Fee Ord 176,300 Cleared 4/26/2017 CARLA VALLADARES
Permit Cleared 4/26/2017 CARLA VALLADARES
Sewer availability Cleared 5/11/2017 CARLA VALLADARES
Green Code Cleared 6/13/2017 SAM CHANG
Hydrant and Access approval Cleared 6/13/2017 JOHN CONNEALLY
Construction near power lines Cleared 6/14/2017 RIDWAN HARDY
Low Impact Development Cleared 12/4/2017 MATTHEW JIMENEZ
Roof/Waste drainage to street Cleared 12/4/2017 RAVIL MANAPOV
Building over 3-story or 36-ft Cleared 12/7/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/7/2017 CALOSHA APPROVED
Grading Pre-Inspection Cleared 12/7/2017 SAM CHANG

Contact Information

Architect Neubert, Aaron Douglas; Lic. No.: C29005 3052 BERKELEY CIRCLE      LOS ANGELES, CA 90026
Contractor Owner-Builder       ,
Engineer Phillips, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Geologist Triebold, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 7/19/2018 Corrections Issued BRAD BESCOS
Footing/Foundation/Slab 7/31/2018 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 8/10/2018 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 9/12/2018 Corrections Issued BRAD BESCOS
Footing/Foundation/Slab 9/14/2018 Not Ready for Inspection BRAD BESCOS
Footing/Foundation/Slab 10/16/2018 Partial Approval BRAD BESCOS
Deputy Drilled-In Anchors 10/17/2018 No Access for Inspection BRAD BESCOS
Footing/Foundation/Slab 10/26/2018 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 11/6/2018 Partial Approval BRAD BESCOS
Deputy Grading 11/21/2018 No Access for Inspection BRAD BESCOS
Deputy Grading 12/4/2018 Approved BRAD BESCOS
Excavation/Setback/Form/Re-Bar 12/18/2018 Partial Approval BRAD BESCOS
Green Building Rough 12/18/2018 Not Ready for Inspection BRAD BESCOS
Verify Sprinkler Sign Off 12/18/2018 Not Ready for Inspection BRAD BESCOS
Piling/Pier/Caisson 12/20/2018 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 12/27/2018 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 1/11/2019 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 2/12/2019 Approved BRAD BESCOS
Deputy Reinf. Concrete 2/13/2019 Approved BRAD BESCOS
Excavation/Setback/Form/Re-Bar 3/15/2019 Partial Approval BRAD BESCOS
Excavation/Setback/Form/Re-Bar 9/26/2019 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 9/30/2019 Approved BRAD BESCOS
Footing/Foundation/Slab 10/9/2019 Partial Approval BRAD BESCOS
Deputy Reinf. Concrete 10/11/2019 Approved BRAD BESCOS
Footing/Foundation/Slab 11/15/2019 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 2/7/2020 No Access for Inspection JOSEPH MCGARRY
Deputy Grading 2/25/2020 Approved JOSEPH MCGARRY
Underground Mechanical 2/25/2020 Partial Approval JOSEPH MCGARRY
Piling/Pier/Caisson 2/28/2020 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 3/2/2020 Partial Approval JOSEPH MCGARRY
Underground Mechanical 3/4/2020 Partial Approval JOSEPH MCGARRY
Underground Mechanical 3/10/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 3/27/2020 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 4/3/2020 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 5/21/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/26/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 5/26/2020 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 6/3/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/9/2020 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/17/2020 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 6/19/2020 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 7/7/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 7/20/2020 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 8/11/2020 Not Ready for Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 8/13/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 8/31/2020 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 9/3/2020 Conditional Approval DAVID FEILER
Deputy Steel/Welding 10/1/2020 No Access for Inspection DONALD CRICHLOW
BUILDING-Rough-Frame 10/9/2020 Not Ready for Inspection DAVID FEILER
Green Building Rough 10/9/2020 Not Ready for Inspection DAVID FEILER
Verify Sprinkler Sign Off 10/9/2020 Not Ready for Inspection DAVID FEILER
Wood Frame 10/9/2020 Partial Approval DAVID FEILER
Wood Frame 10/19/2020 Partial Approval JOSEPH MCGARRY
Underground Mechanical 11/24/2020 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Conditional Approval JOSEPH MCGARRY
Wood Frame 12/16/2020 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 12/21/2020 Partial Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 12/28/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 1/15/2021 Partial Approval JOSEPH MCGARRY
Underground Mechanical 1/26/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 2/22/2021 Partial Approval JOSEPH MCGARRY
HVAC-Rough 2/22/2021 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 3/17/2021 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 3/17/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 3/31/2021 Conditional Approval JOSEPH MCGARRY
Green Building Rough 3/31/2021 Approved JOSEPH MCGARRY
Insulation 3/31/2021 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 3/31/2021 Approved JOSEPH MCGARRY
Drywall Nailing 4/13/2021 Approved ROBERT VORHIS
Interior/Exterior Lathing 4/13/2021 Approved ROBERT VORHIS
Shower Pan 6/7/2021 Approved CHRIS CHRISTENSEN
Deck 6/16/2021 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 9/15/2021 Approved JOSEPH MCGARRY
Gas Test 1/21/2022 Approved CRAIG DAVIS
PLUMBING-Final 1/21/2022 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 2/16/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Final 2/16/2022 Approved JOSEPH MCGARRY
Final 2/16/2022 Corrections Issued JOSEPH MCGARRY
Green Building Final 2/16/2022 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Final 2/16/2022 Approved JOSEPH MCGARRY
PLUMBING-Final 2/16/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 2/16/2022 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 2/16/2022 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 2/16/2022 Approved JOSEPH MCGARRY
Final 3/3/2022 Not Ready for Inspection JOSEPH MCGARRY
Green Building Final 3/3/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 3/3/2022 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 3/3/2022 Approved JOSEPH MCGARRY
Final 3/30/2022 OK to Issue CofO JOSEPH MCGARRY
Gas Test 3/30/2022 Approved JOSEPH MCGARRY
Service/Power Release 3/30/2022 Approved JOSEPH MCGARRY