10010-10024 S JUNIPER ST BLDG 6-7 90002

Certificate Information: 10010-10024 S JUNIPER ST BLDG 6-7 90002

Application / Permit
17010-10000-00975
Plan Check / Job No.
B17LA03497
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY, 7 UNIT TYPE V-B APARTMENT BUILDING
Permit Issued
Issued on 6/21/2018
Issuing Office
Metro
Current Status
CofO Issued on 6/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2017 APPLICANT
Disabled Access Plans Picked Up 4/20/2017 APPLICANT
Green Plans Picked Up 4/25/2017 APPLICANT
Assigned to Plan Check Engineer 5/5/2017 GARO TELMI
Corrections Issued 10/5/2017 GARO TELMI
Quality Review Completed 10/13/2017 JOHN FRANCIA
Plan Check Approved 3/20/2018 GARO TELMI
Issued 6/21/2018 LADBS
TCO Issued (Expire Date: 06-12-2021) 12/14/2020 ERNESTO CORRAL
CofO in Progress 6/18/2021 JAMES POWERS
Permit Finaled 6/21/2021 ERNESTO CORRAL
CofO Issued 6/21/2021 ERNESTO CORRAL
Permit Finaled 6/21/2021 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 5/1/2017 CARL MILLS
Work Adjacent to Public Way Cleared 5/1/2017 KENNETH PHAM
Miscellaneous Cleared 5/15/2017 ALAN COMO
Specific Plan Cleared 5/15/2017 ALAN COMO
Encroachment in public way Cleared 12/21/2017 JACOB BIGLER
Eng Process Fee Ord 176,300 Cleared 12/21/2017 CARLA VALLADARES
Private street Cleared 2/13/2018 BRIDGETTE WOOTEN
Tract Map conditions Cleared 2/13/2018 BRIDGETTE WOOTEN
Sewer availability Cleared 2/28/2018 MICHAEL CASTILLO
Low Impact Development Cleared 3/6/2018 AMMAR ELTAWIL
DAS Clearance Cleared 3/8/2018 JOHN FRANCIA
Driveway location Cleared 3/8/2018 TAIMOUR TANAVOLI
Internal circulation Cleared 3/8/2018 TAIMOUR TANAVOLI
Green Code Cleared 3/9/2018 DONALD CRICHLOW
Hydrant and Access approval Cleared 3/9/2018 JOHN CONNEALLY
Permit Cleared 3/9/2018 ZEMAMU GEBREWOLD
Roof/Waste drainage to street Cleared 3/9/2018 ZEMAMU GEBREWOLD
Frnt yard landscape/Water mgmt Cleared 3/14/2018 HERMAN VAN BUREN
Fire Marshall Fire Life Safety Cleared 3/15/2018 ANDREW KO
Highway dedication Cleared 3/15/2018 ADRIAN SANCHEZ
Specific Plan Cleared 3/19/2018 STACY FARFAN
Building over 3-story or 36-ft Cleared 3/20/2018 CALOSHA APPROVED

Contact Information

Architect Vasquez, Ernesto M; Lic. No.: C9135 3 MACARTHUR PL. #850      SANTA ANA, CA 92707
Contractor Wpic Construction Llc; Lic. No.: 1029691-B 125 W. MAPLE AVE      MONROVIA, CA 91016
Engineer Nam, Young-Keun; Lic. No.: S4029 17 SANTA EUGENIA      IRVINE, CA 92606
Engineer Schales, Debra Valle; Lic. No.: C43101 8192 EVELYNE CIRCLE      HUNTINGTON BEACH, CA 92646
Geologist Feffer, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 12/26/2018 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/26/2018 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/26/2018 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/27/2018 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/28/2018 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/3/2019 Partial Approval TED RIES
Deputy Reinf. Concrete 1/4/2019 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 1/28/2019 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/8/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/20/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/27/2019 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/14/2019 Partial Approval JAMES POWERS
Insulation 3/29/2019 Partial Approval JAMES POWERS
Deputy Wood Construction 4/10/2019 Partial Approval JAMES POWERS
Insulation 4/19/2019 Not Ready for Inspection TED RIES
Insulation 4/23/2019 Partial Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 5/2/2019 Approved JOEY BUCHANAN
Green Building Rough 5/2/2019 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 5/2/2019 Approved JOEY BUCHANAN
Deputy Wood Construction 5/7/2019 Approved JOEY BUCHANAN
Deputy Wood Construction 5/13/2019 Approved JOEY BUCHANAN
Wood Frame 6/10/2019 Corrections Issued JOEY BUCHANAN
Insulation 6/17/2019 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 6/24/2019 Conditional Approval JOEY BUCHANAN
Wood Frame 6/27/2019 Partial Approval JOEY BUCHANAN
Wood Frame 7/1/2019 Approved JAMES POWERS
Insulation 7/15/2019 Partial Approval JAMES POWERS
Interior/Exterior Lathing 7/22/2019 Approved JAMES POWERS
Drywall Nailing 7/25/2019 Approved JOEY BUCHANAN
Footing/Foundation/Slab 10/3/2019 Partial Approval JAMES POWERS
Final 7/1/2020 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/1/2020 Approved JAMES POWERS
Green Building Final 7/1/2020 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/1/2020 SGSOV Not Ready JAMES POWERS
Smoke Detectors 7/1/2020 Approved JAMES POWERS
Final 12/10/2020 OK for TCO JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/10/2020 SGSOV No Gas JAMES POWERS
Special/Order Compliance 5/19/2021 Approved JAMES POWERS
Final 6/18/2021 OK to Issue CofO JAMES POWERS