2300-2398 E CENTURY BLVD BLDG 4A-1 90002
Certificate Information: 2300-2398 E CENTURY BLVD BLDG 4A-1 90002
- Application / Permit
- 17010-10000-00966
- Plan Check / Job No.
- B17LA03488
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- PROPOSED 3-STORY, 17-UNIT APARTMENT BUILDING, TYPE V-A, FULLY SPRINKLERED NFPA 13.
- Permit Issued
- Issued on 6/21/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 4/12/2017 | APPLICANT |
Disabled Access Plans Picked Up | 4/20/2017 | APPLICANT |
Green Plans Picked Up | 4/25/2017 | APPLICANT |
Assigned to Plan Check Engineer | 5/5/2017 | JOHN FRANCIA |
Corrections Issued | 6/20/2017 | JOHN FRANCIA |
Quality Review Completed | 9/20/2017 | JAMESON LEE |
Applicant returned to address corrections | 1/23/2018 | JOHN FRANCIA |
Plan Check Approved | 3/21/2018 | JOHN FRANCIA |
Issued | 6/21/2018 | LADBS |
TCO Issued (Expire Date: 03-30-2021) | 10/1/2020 | DAVID TSAU |
TCO Issued (Expire Date: 09-26-2021) | 3/30/2021 | ERNESTO CORRAL |
CofO in Progress | 7/6/2021 | JAMES POWERS |
CofO Issued | 7/9/2021 | ERNESTO CORRAL |
Permit Finaled | 7/9/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
Address approval | Cleared | 5/1/2017 | CARL MILLS |
Work Adjacent to Public Way | Cleared | 5/1/2017 | KENNETH PHAM |
Miscellaneous | Cleared | 5/15/2017 | ALAN COMO |
Specific Plan | Cleared | 5/15/2017 | ALAN COMO |
Encroachment in public way | Cleared | 12/21/2017 | JACOB BIGLER |
Eng Process Fee Ord 176,300 | Cleared | 12/21/2017 | CARLA VALLADARES |
Miscellaneous | Cleared | 2/5/2018 | STACY FARFAN |
Miscellaneous | Cleared | 2/5/2018 | STACY FARFAN |
Private street | Cleared | 2/13/2018 | BRIDGETTE WOOTEN |
Tract Map conditions | Cleared | 2/13/2018 | BRIDGETTE WOOTEN |
Sewer availability | Cleared | 2/28/2018 | MICHAEL CASTILLO |
Low Impact Development | Cleared | 3/6/2018 | AMMAR ELTAWIL |
DAS Clearance | Cleared | 3/8/2018 | JOHN FRANCIA |
Driveway location | Cleared | 3/8/2018 | EDUARDO HERMOSO |
Internal circulation | Cleared | 3/8/2018 | EDUARDO HERMOSO |
Green Code | Cleared | 3/9/2018 | DONALD CRICHLOW |
Hydrant and Access approval | Cleared | 3/9/2018 | JOHN CONNEALLY |
Permit | Cleared | 3/9/2018 | ZEMAMU GEBREWOLD |
Roof/Waste drainage to street | Cleared | 3/9/2018 | ZEMAMU GEBREWOLD |
Frnt yard landscape/Water mgmt | Cleared | 3/14/2018 | HERMAN VAN BUREN |
Fire Marshall Fire Life Safety | Cleared | 3/15/2018 | ANDREW KO |
Highway dedication | Cleared | 3/15/2018 | ADRIAN SANCHEZ |
Specific Plan | Cleared | 3/19/2018 | STACY FARFAN |
Building over 3-story or 36-ft | Cleared | 3/20/2018 | CALOSHA APPROVED |
Miscellaneous | Cleared | 6/19/2018 | NAZILA NOORIFAR |
Contact Information
Architect | Vasquez, Ernesto M; Lic. No.: C9135 | 3 MACARTHUR PL. #850 SANTA ANA, CA 92707 |
Contractor | Wpic Construction Llc; Lic. No.: 1029691-B | 125 W MAPLE AVE MONROVIA, CA 91016 |
Engineer | Nam, Young-Keun; Lic. No.: S4029 | 17 SANTA EUGENIA IRVINE, CA 92606 |
Engineer | Schales, Debra Valle; Lic. No.: C43101 | 8192 EVELYNE CIRCLE HUNTINGTON BEACH, CA 92646 |
Geologist | Feffer, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Excavation/Setback/Form/Re-Bar | 4/9/2019 | Partial Approval | JAMES POWERS |
Footing/Foundation/Slab | 4/9/2019 | Partial Approval | JAMES POWERS |
Excavation/Setback/Form/Re-Bar | 4/16/2019 | Partial Approval | JAMES POWERS |
Footing/Foundation/Slab | 4/16/2019 | Partial Approval | JAMES POWERS |
Drywall Nailing | 4/29/2019 | Not Ready for Inspection | JOEY BUCHANAN |
Floor/Roof Diaphrgm/Shear Wall | 4/29/2019 | Partial Approval | JOEY BUCHANAN |
Green Building Rough | 4/29/2019 | Partial Approval | JOEY BUCHANAN |
Deputy Wood Construction | 4/30/2019 | Approved | JOEY BUCHANAN |
Floor/Roof Diaphrgm/Shear Wall | 5/3/2019 | Not Ready for Inspection | JOEY BUCHANAN |
Drywall Nailing | 5/6/2019 | Partial Approval | HAMID PISHEHVAR |
Excavation/Setback/Form/Re-Bar | 5/6/2019 | Partial Approval | HAMID PISHEHVAR |
Green Building Rough | 5/6/2019 | Partial Inspection | HAMID PISHEHVAR |
Deputy Reinf. Concrete | 5/7/2019 | Partial Approval | JAMES POWERS |
Deputy Wood Construction | 5/7/2019 | Approved | JOEY BUCHANAN |
Deputy Wood Construction | 6/7/2019 | Approved | JOEY BUCHANAN |
Deputy Wood Construction | 6/11/2019 | Partial Approval | JAMES POWERS |
Deputy Wood Construction | 7/23/2019 | Approved | JOEY BUCHANAN |
Green Building Rough | 7/23/2019 | Approved | JOEY BUCHANAN |
Verify Sprinkler Sign Off | 7/23/2019 | Approved | JOEY BUCHANAN |
Wood Frame | 7/23/2019 | Conditional Approval | JOEY BUCHANAN |
Deputy Wood Construction | 7/24/2019 | Partial Approval | JAMES POWERS |
Deputy Wood Construction | 7/25/2019 | Partial Approval | JAMES POWERS |
Deputy Wood Construction | 7/31/2019 | Partial Approval | JAMES POWERS |
Insulation | 9/4/2019 | Approved | JAMES POWERS |
Drywall Nailing | 9/18/2019 | Approved | JAMES POWERS |
Interior/Exterior Lathing | 9/18/2019 | Approved | JAMES POWERS |
Deputy Wood Construction | 11/14/2019 | Partial Approval | JAMES POWERS |
Deputy Drilled-In Anchors | 6/18/2020 | Partial Approval | JAMES POWERS |
Footing/Foundation/Slab | 6/22/2020 | Partial Approval | JAMES POWERS |
Deputy Reinf. Concrete | 6/29/2020 | Partial Approval | JAMES POWERS |
Final | 9/14/2020 | Not Ready for Inspection | JAMES POWERS |
Footing/Foundation/Slab | 9/14/2020 | Approved | JAMES POWERS |
Green Building Final | 9/14/2020 | Approved | JAMES POWERS |
SGSOV-Seismic Gas S/O Valve | 9/14/2020 | SGSOV No Gas | JAMES POWERS |
Smoke Detectors | 9/14/2020 | Approved | JAMES POWERS |
Wood Frame | 9/14/2020 | Approved | JAMES POWERS |
Special/Order Compliance | 3/9/2021 | Partial Approval | JAMES POWERS |
Final | 7/6/2021 | OK to Issue CofO | JAMES POWERS |