667 N LACHMAN LANE 90272
Certificate Information: 667 N LACHMAN LANE 90272
- Application / Permit
- 17010-10000-00803
- Plan Check / Job No.
- B17LA03055
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY HOUSE W/ A BASEMENT AND 2 CAR GARAGE.
- Permit Issued
- Issued on 8/28/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2017 | YOUNG KIM |
| Green Plans Picked Up | 4/14/2017 | APPLICANT |
| Corrections Issued | 5/11/2017 | YOUNG KIM |
| Quality Review Completed | 5/19/2017 | BILL STUTSMAN |
| Building Plans Picked Up | 5/23/2017 | APPLICANT |
| Applicant returned to address corrections | 3/30/2018 | YOUNG KIM |
| Applicant returned to address corrections | 4/27/2018 | YOUNG KIM |
| Applicant returned to address corrections | 7/17/2018 | YOUNG KIM |
| Plan Check Approved | 8/28/2018 | YOUNG KIM |
| Issued | 8/28/2018 | LADBS |
| CofO in Progress | 10/18/2021 | ANDREW NAVE |
| Permit Finaled | 10/21/2021 | DANIEL ORRANTE |
| CofO Issued | 10/21/2021 | DANIEL ORRANTE |
| Permit Finaled | 10/21/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/30/2018 | CARLA VALLADARES |
| BHO/Hillside ordinance | Cleared | 3/30/2018 | CARLA VALLADARES |
| BHO/Hillside ordinance | Cleared | 3/30/2018 | CARLA VALLADARES |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2018 | CARLA VALLADARES |
| Sewer availability | Cleared | 3/30/2018 | CARLA VALLADARES |
| Excavation more than 5-ft deep | Cleared | 4/27/2018 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/27/2018 | YOUNG KIM |
| Grading Pre-Inspection | Cleared | 4/27/2018 | YOUNG KIM |
| Coastal Zone | Cleared | 7/17/2018 | FIPE LEILUA |
| Low Impact Development | Cleared | 8/9/2018 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 8/22/2018 | NEGAR NEJAD |
| Roof/Waste drainage to street | Cleared | 8/22/2018 | MICHAEL CASTILLO |
Contact Information
| Architect | Khajavi, Sina; Lic. No.: C19510 | 4040 PALOS VERDES DR N STE 201 ROLLING HILLS ESTATES, CA 90274 |
| Contractor | Owner-Builder | , |
| Engineer | Geospectra, Inc.; Lic. No.: C82579 | 2691 DOW SUITE F TUSTIN, CA 92781 |
| Engineer | Greystone, Engineering Group Inc.; Lic. No.: C84000 | 1836 PARNELL AVE. # 202 LOS ANGELES, CA 90025 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/23/2019 | Approved | ANDREW NAVE |
| Pre-Inspection | 12/2/2019 | Partial Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 2/25/2020 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 3/4/2020 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Rough | 3/6/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 3/31/2020 | Partial Approval | ANDREW NAVE |
| Deputy Shotcrete | 4/3/2020 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 4/16/2020 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 4/16/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Corrections Issued | ANDREW NAVE |
| Verify Sprinkler Sign Off | 7/28/2020 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2020 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2020 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 9/17/2020 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 10/21/2020 | Partial Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 10/28/2020 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 11/6/2020 | Approved | ANDREW NAVE |
| HVAC-Rough | 11/17/2020 | Corrections Issued | ANDREW NAVE |
| Interior/Exterior Lathing | 11/17/2020 | Partial Approval | ANDREW NAVE |
| HVAC-Rough | 11/20/2020 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 12/2/2020 | Corrections Issued | ANDREW NAVE |
| BUILDING-Rough-Frame | 12/9/2020 | Approved | ANDREW NAVE |
| Green Building Rough | 12/9/2020 | Approved | ANDREW NAVE |
| Insulation | 12/9/2020 | Partial Approval | ANDREW NAVE |
| Verify Sprinkler Sign Off | 12/9/2020 | Approved | ANDREW NAVE |
| Insulation | 12/15/2020 | Approved | ANDREW NAVE |
| Shower Pan | 12/15/2020 | Approved | ANDREW NAVE |
| Drywall Nailing | 12/30/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 1/27/2021 | Approved | ANDREW NAVE |
| Gas Test | 2/4/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 3/10/2021 | Approved | ANDREW NAVE |
| Gas Test | 4/13/2021 | Partial Approval | ANDREW NAVE |
| Sewer | 4/13/2021 | Approved | ANDREW NAVE |
| Underground Mechanical | 4/13/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 6/25/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 6/29/2021 | Approved | ANDREW NAVE |
| Service/Power Release | 7/2/2021 | Approved | KENNETH NAGLE |
| Deputy Drilled-In Anchors | 7/27/2021 | Conditional Approval | ANDREW NAVE |
| HVAC-Final | 8/6/2021 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Final | 8/10/2021 | Corrections Issued | JOHN KIDWELL |
| HVAC-Final | 8/17/2021 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Final | 8/18/2021 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 8/20/2021 | Approved | ANDREW NAVE |
| PLUMBING-Final | 8/20/2021 | Approved | ANDREW NAVE |
| Final | 8/27/2021 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 8/27/2021 | Approved | ANDREW NAVE |
| Green Building Final | 8/27/2021 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 8/27/2021 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 8/27/2021 | Corrections Issued | ANDREW NAVE |
| Final | 9/24/2021 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Final | 9/24/2021 | Not Ready for Inspection | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 9/24/2021 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 9/24/2021 | Approved | ANDREW NAVE |
| Final | 10/6/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 10/6/2021 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 10/6/2021 | SGSOV Approved | ANDREW NAVE |
| Final | 10/18/2021 | OK to Issue CofO | ANDREW NAVE |
| Special/Order Compliance | 10/18/2021 | Approved | ANDREW NAVE |